Phase 2B, 2E & 2C Volume 4 | December 11, 2017
Brownsburg High School's renovation and expansion project is expected to be completed in June of 2020. We will continue to send updates to families who have children in Brownsburg Schools in grades 7-12, to BCSC staff, and to anyone who has subscribed through our website. These emails will be sent quarterly to provide information specific to each phase of the project, focusing on areas that impact students and their daily routines at Brownsburg High School. 

The work in Phases 1B and 2B is wrapping up over Winter Break. Phase 2C will begin after the first of the year and, along with Phase 2E, will continue through spring. The extensive work of Phase 3A begins at spring break. Read on for more details.
Overview of Phases 1B, 2A, 2B, 2E, 3C, & 3A
WHAT:  Since the beginning of the school year, construction activities has continued behind temporary walls in the main part of the high school building. Work on the northeast side of the building for classroom space for physical education, health and performing arts is more visible and continues to progress.

  • Phase 1B - This phase will be completed in the coming days with the new heating, cooling, and electrical facility providing service to all parts of the building throughout the project and future phases.

  • Phase 2B - After Winter Break, students and teachers will be utilizing 21 new and renovated classrooms in the section that were under construction in the first semester. This completed phase also includes expanded corridors and a locker commons up and downstairs.

  • Phase 2E – Work on the classroom space for physical education, health and performing arts will continue into the spring of 2018.

WHY: The core of the Brownsburg High School building has been relatively unchanged since it opened in 1971. With 13 additions over the last 46 years, the infrastructure of the building is in dire need of an upgrade. These upgrades will accommodate technology needs for teachers and students that weren't in place in 1971 and maintain a comfortable learning environment with updates to the aging HVAC system.

COMPLETION DATE FOR CURRENT PHASES OF WORK:
Phase 1B – December 2017 - Nearly complete
Phase 2A – July 2017 - COMPLETED
Phase 2B – December 2017 - Nearly complete
Phase 2C - Starts December 2017, Complete July 2018
Phase 2E – Spring Semester 2018
Impacted Areas - including an updated BHS room number map
(changes for after Winter Break in bold)
Building Access
  • Entry #1 and the main office to Brownsburg High School remain open and accessible. Parking is still available across Odell near the track and field. Student drop off and pick up remains at Entry #12 and #14. Construction activities will move into a portion of the main office, but the office will remain operational and will be accessible from Entry #1.

Student Parking
  • There are no changes to student parking.

Visitor Parking
  • The parking area and access drives at Entry #1 remain out of service and inaccessible through spring 2018. Visitor parking is available across Odell near the track and field. The map is included again below.

Pick up/Drop Off
  • The entry to the parent drop-off/pick-up line remains along Bulldog Boulevard. Students will be entering and exiting the building at Entry #12 or Entry #14. The parent line will continue to exit back out on to Odell Street. The map is included again below.

Passing Periods
  • The BHS administration will monitor the passing periods for potential changes in the future. There are still no planned changes to the BHS bell schedule. Corridors A and C will be narrower during phase 2C while the renovated portions in Phase 2B will be much wider.

Possible Services Affected
  • Bus staging was moved to the south side of the building at Fall Break and no changes to this new location are planned through Spring 2019.

Classrooms & Relocation
  • Teachers in affected classrooms are aware of the changes and the new room assignments will be reflected in BHS student schedules. Schedules are available in PowerSchool starting December 18, 2017. Schedules will reflect new classroom numbers. CLICK HERE for a map that includes the new numbers.

  • The BHS Main Office will stay at Entry #1, but the reception area will move slightly to make room for construction. Team 2019 will move into the main office area near Entry #1.

  • The BHS Clinic will move into Corridor C in the space formerly used by the Top Dog Cafe.

  • Mr. Daghe met with BHS-TV students about the changes in the BHS map for the second semester. Their report was shown during student announcements:
What's Next
As Phase 2C begins, the construction moves north within the building and parts of the A, B, C, and G corridors will be under construction. The BHS Clinic, Team 2019, and some of the front office will relocate over the holidays. Phase 3A is an extensive phase that includes more classrooms and corridors and the renovation of much of the BHS Auditorium, closing that space from Spring Break 2018 through January 2020. I you haven't yet viewed the preview of the renovated auditorium, please see the video below.
CLICK HERE to open a printable PDF of the timeline. (view below)