Phase 1B, 2B & 2E, Volume 2 | July 26, 2017
Keep reading for lots of information about the next phases of work that has taken place during summer recess and continues into the start of the next school year.

Brownsburg High School's renovation and expansion project is expected to be completed in June of 2020.  We will continue to send updates to families who have children in Brownsburg Schools in grades 7-12, to BCSC staff, and to anyone who has subscribed through our website.  These emails will be sent quarterly to provide information specific to each phase of the project, focusing on areas that impact students and their daily routines at Brownsburg High School. 

The work in Phase 1B continues through the end of 2017 with Phases 2B, 2E beginning at the start of summer recess and continuing into the new school year
A Message from the Brownsburg Fire Territory

"It's back to school time in Brownsburg. The Brownsburg Fire Territory has inspected every school to make sure we are ready for another safe school year.  With the construction at the high school we have been working closely with BCSC and construction contractors. Fire Marshal Jones has been there every day this week and everything is ready for a safe school year.

Every Brownsburg School will be having fire drill at the beginning of school and the Brownsburg Fire Territory will be a part of those drills. We will continue to be actively involved during the construction process to ensure safety."
Overview of Phases 1B, 2A, 2B, 2E
WHAT:  As the 2017-18 school year begins, contractors are wrapping up work in many areas of the building and have turned renovated classrooms back over to the school. Remaining construction activities have been moved behind walls into the main construction limits.

  • Phase 2A - These classrooms have been renovated (picture, lower right), including refurbishment of walls, ceilings, and cabinetry. Carpeting may be placed in selected spaces, but in many areas will be held until work in adjoining areas has been
    completed.

  • Phase 2B - Extensive renovation work will continue in this area (between the old corridor G and the Media Center Courtyard, east of Corridor C - picture upper right) during the fall semester. Students will access the Media Center and the south east corner of the building by using Corridor C and the old Corridor H.

  • Phase 2E –  Work on the new wrestling, weight, and band/guard area began immediately following Commencement and will continue into the Spring of 2018. This work does impact the parent drop-off/pick-up route. (see map below)

WHY: The core of the Brownsburg High School building has been relatively unchanged since it opened in 1971.  With 13 additions over the last 46 years, the infrastructure of the building is in dire need of an upgrade.  These upgrades will accommodate technology needs for teachers and students that weren't in place in 1971 and maintain a comfortable learning environment with updates to the aging HVAC system.

COMPLETION DATE FOR:
Phase 1B – December 2017
Phase 2A – July 2017 - COMPLETED
Phase 2B – Late 2017
Phase 2E – Spring Recess 2019

Impact Area
  • Building Access
    Entry #1 and the main office to Brownsburg High School are open and accessible.  Parking is available across Odell near the track and field. Entry #16 is available only for emergency egress purposes.  Student drop off and pick up will be at entry #14 and #15.

  • Student Parking
    Students parking spaces were assigned at registration.  CLICK HERE to view the student parking packet,

  • Visitor Parking
    The parking area and access drives at Entry #1 are out of service and inaccessible and will remain so through Spring 2018.  Visitor parking is available across Odell near the track and field.  See more details below.

  • Pick up/Drop Off
    The entry to the parent drop-off/pick-up line remains along Bulldog Boulevard. Students will be entering and exiting the building at Entry 14 or Entry 15. The parent line will be exiting back out on to Odell Street.  See more details below.

  • Passing Periods
    The BHS administration will monitor the passing periods for potential changes in the future.  There are no planned changes to the BHS bell schedule.

  • Possible Services Affected
    -Entry #16 will be closed for general access, and the Band program will be using Entry #15 to reach the band lot and football field
    -Bus staging will remain on the west side of the building, Accessing the building through Entry 5 and 7.

  • Classrooms & Relocation
    Student schedules should reflect the correct classroom numbers and teachers for the new year.  Check with your Team Office with specific questions.
PARKING AND PICK UP DROP OFF MAP
Click the photo below for a PDF of the new procedures.
What's Next
Work on phases 1B, 2B, 2E, and 2F will continue into the Fall Semester of 2017. Phase 2B renovations are expected to be completed late in the fall semester and the transition to
Phase 2C is scheduled to occur over the Winter Recess 2017-18.  

CLICK HERE to open a printable PDF of the timeline.  