Phase 1B, Volume 1 | February 27, 2017
Brownsburg High School's renovation and expansion project is expected to be completed in June of 2020.  We will continue to send updates to families who have children in Brownsburg Schools in grades 6-12, to BCSC staff, and to anyone who has subscribed through our website.  These emails will be sent quarterly to provide information specific to each phase of the project, focusing on areas that impact students and their daily routines at Brownsburg High School. 

The next phase will provide a more visible sign that construction is underway.   Encourage other interested parties to subscribe to these emails by clicking the button below.
Overview of Phase 1B
WHAT:  Phase 1B constructs a new heating, cooling, and electrical facility in the area around the current cafeteria. The construction of this space, beginning over Spring Break, will make it possible to maintain services to all parts of the building throughout the project and facilitate future phases.  It requires the closing of the Sandwich Shoppe and the south bus staging area. This will shift most of the school bus pick up and drop off to the current Sycamore Street student parking area. Special Education school bus pick up and drop off will now occur near door #5. 

WHY:  The core of the Brownsburg High School building has been relatively unchanged since it opened in 1971.  With 13 additions over the last 46 years, the infrastructure of the building is in dire need of an upgrade.  These upgrades will accommodate technology needs for teachers and students that weren't in place in 1971 and maintain a comfortable learning environment with updates to the aging HVAC system. 


COMPLETION DATE FOR PHASE 1B: 
December 2017
Impact Areas - after March 1 through May 2017
  • Visitor Parking
    The south parking lot near doors 5, 6, & 7 will be blocked off for construction staging.

  • Student Parking 
    Students who are assigned to Lot #8 (Sycamore Lot) have been reassigned to Lot #1 (North Lot).  Students will be notified of this change via email and will begin parking in Lot #1 on Monday April 3. 

  • Pick up/Drop Off
    Parent pick up and drop off will not be affected.

    Special Education bus staging will relocate to the west side of the building with general education buses dropping off students in the southwest student parking area.  
  • Passing Periods
    No Impact

  • Possible Services Affected
    No services will be affected during school days, but there may be intermittent service interruptions over Spring Break as wiring is being relocated in advance of summer work.  Anyone using the facility at the time of the outages will be notified. 
  • Classrooms & Relocation
    While no classrooms will be relocated during the school day in this phase, some preparatory work to remove existing floor coverings and to install new data cabling above ceilings will occur outside of the school day and during Spring Break. 
What's Next
Four different phases will be underway during the summer of 2017.  Phase 2A, 2B, & 2E will start preliminary work in May.  See the timeline below to see how this work is phased in over the next 3 years.   Expect more information to be shared in April. 

CLICK HERE to open a printable PDF of the timeline.  