Construction Updates: U.S. Rt. 62 &
Hamilton Rd.
U.S. Route 62 Resurfacing
Paving on U.S. Route 62 is scheduled to take place on
Friday, October 14 from 8:30 a.m. to 7 p.m. (weather permitting) and the work is expected to last until
Friday, October 21, 2016. Major delays are expected to occur during rush hour and motorists are encouraged to plan their route accordingly.
Read more...
Hamilton Road Central Updates
Good news! Hamilton Road is progressing ahead of schedule. Crews are working quickly to complete base paving operations this Fall on Hamilton Rd. If weather permits, the goal is to complete all curb and base paving operations on Hamilton Road and have both roundabouts functioning by
November 30, 2016.
As time and weather allow this Fall and as we move into Winter, the contractor will continue to work to complete remaining concrete work for driveways and sidewalks, while all final restoration and surface asphalt will be completed in the Spring/Summer of 2017.
Read more...
|