CRP crews have replaced approximately 21,000 feet of new water mains this fiscal year, (since July 2014). A total of 551,640 feet of new water mains have been installed over the course of the project. In the first weeks of February, CRP crews will have completed work in the Mesa area of Yucca Valley (North of Buena Vista, between Warren Vista and Avalon Avenue). The next area the CRP crew will begin replacing water mains, will be within the Phase 1 area of the sewer project which includes most of the downtown corridor.
|