CONSTRUCTION PROJECTS (ESTIMATED TOTAL COST $53,045,925.90)
A)
US 281: Roadway Rehabilitation and Widening (CSJ: 0220-03-028)
Cost
:
$ 7,709,997.35
Project Length: 3.863 MILES
Contractor: ASAGO, LLC
Working days: 400 Days (20 months)
September 2014 Letting
Work Started: June 11, 2015
Est.Completion Date:February 2017
Preconstruction Meeting: December 10, 2014
Project Manager: David Vera, P.E.
Limits
:
From 0.05 MI W of FM 1479 To 0.24 MI E of FM 506
This project consists of rehabilitation and widening of existing road consisting of: Grading, Lime Treatment, Subgrade, Flexible Base, Asphaltic Concrete Pavement, Pavement Markings & Striping.
55.53 % Complete
70.73 % Time Used
B) South Parallel Corridor: New Construction (CSJ: 0921-06-241) (LOCAL LET)
Cost: $ 3,824,368.25 Project Length: 2.11 MILES
Contractor: Foremost Paving, Inc. Working days: 200 Days (10 months)
Locally Let Work Started: May 21, 2015
Est. Completion Date: August 2016 Preconstruction Meeting: February 25, 2015
Project Manager: Andres Espinoza, P.E.
Limits: From FM 1479 To FM 509
This project consists of constructing a new roadway consisting of: Grading, Lime Treatment, Subgrade, Flexible Base, Asphaltic Concrete Pavement, Flashing Beacons, Culvert Structures, Irrigation Structures, Riprap, Signing, Pavement Markings & Striping.
97.29 % Complete
91.50 % Time Used
C)
FM 106: Roadway Reconstruction (CSJ: 2243-01-009)
Cost:
$ 15,555,191
Project Length: 11.4 MILES
Contractor: Texas SAI, Inc.
Working days: 420 Days (21 months)
September 2014 Letting
Work Started: November 9, 2015
Est. Completion Date: January 2018
Preconstruction Meeting:Sept. 17, 2015
Project Manager: David Vera, P.E.
Limits:
From FM 1847 To FM 510
This project consists of reconstructing an existing roadway consisting of:
Roadway Realignment, Drainage Structures, Lime Treatment, Subgrade, Flexible Base, Asphaltic Concrete Pavement, Signing, Pavement Markings & Striping.
25.61 % Complete
39.87 % Time Used
D)
BSIF AT LOS INDIOS (CSJ: 0921-06-208)
Cost:
$ 6,949,740
Project Length: .001 MILES
Contractor: Foremost Paving, Inc.
Working days: 262 Days (13 months)
August 2014 Letting
Work Started: February 23, 2015
Est.Completion Date: December 2016
Preconstruction Meeting: January 8, 2015
Project Manager: Sergio Sustaita, P.E.
Limits:
At Los Indios Free Trade International Bridge
This project consists of the construction of a Border Safety Inspection Facility(BSIF) (Phase I): Drainage Structures, Lime Treatment, Subgrade, Flexible Base, Asphaltic Concrete Pavement, Concrete Pavement(Continuously Reinforced)(10”), Signing, Pavement Markings & Striping
.
74.90 % Complete
138.17 % Time Used
E)
US 281: Roadway Rehabilitation and Widening (CSJ: 0220-03-027)
Cost
:
$ 5,229,349
Project Length: 2.789 MILES
Contractor: Foremost Paving, Inc.
Working days: 380 Days (19 months)
December 2014 Letting
Work Started: February 18, 2015
Est.Completion Date: February 2017
Preconstruction Meeting:
February 10,
2015
Project Manager: David Vera, P.E.
Limits:
From 0.099 mi. E. of Hidalgo/Cameron County Line to 0.24 mi. E. of FM 506
This project consists of rehabilitation and widening of existing road consisting of:
Grading, Lime Treatment, Subgrade, Flexible Base, Asphaltic Concrete Pavement, Pavement Markings & Striping.
63.80 % Complete
61.84 % Time Used
F) 1 & 2 CR Off System Bridge Replacements: (CSJ: 0921-06-248)
Cost
:
$ 1,371,237
Project Length: Varies
Contractor: Valley Infrastructure
Working days: 240 Days (12 months)
December 2014 Letting
Work Started: February 2016
Est. Completion Date: December 2016
Preconstruction Meeting: November 19, 2015
Project Manager: David Vera, P.E.
This project consists of replacing two off system bridges and their approaches. One bridge is located on Kornegay Rd just south of FM 1561, and the other is located on Mile Line 20 Rd 0.5 MI E of Nelson Rd.
47.79 % Complete
47.50 % Time Used
G)
Bridge Rehabilitation (Rio Hondo Lift Bridge): (CSJ: 0630-02-041)
Cost
:
$ 12,406,043.30
Project Length: 0.117 MILES
Contractor: PCL Civil Contractors. Inc.
Working days: 651 Days (33 months)
July 2015 Letting
Work Started: NA
Est. Completion Date: December 2017
Preconstruction Meeting: NA
Project Manager: Sergio Sustaita, P.E.
This project consists of bridge rehabilitation consisting of: Structural, mechanical, and electrical rehabilitation, fender repairs, bridge railing retrofit and channel bank improvements.
6.45 % Complete
7.83 % Time Used
DESIGN PROJECTS (ESTIMATED TOTAL COST $ 13.37 MILLION)
1. South Parallel Corridor: CSJ: 0921-06-252 New Construction
This project consists of a new roadway connecting the South Parallel Corridor from FM 509 to FM 1577. Proposed typical sections will be given out at a later date. The current estimated cost is $9.57 million. This project has a tentative letting date of May 2017.
2. US 281 Roadway Rehabilitation and Widening: CSJ: 0220-03-030
This project consists of rehabilitation and widening of existing road consisting of: Grading, Lime Treatment, Subgrade, Flexible Base, Asphaltic Concrete Pavement, Pavement Markings & Striping. The current estimated cost is $3.8 million. This project has a tentative letting date of October 2016.
Limits: From 0.05 MI W of FM 1479 to FM 509.