McCULLOUGH AVE AREA DRAINAGE
*  PROJECT UPDATE
*  8.14.18




ROAD CLOSURE:
     E. Euclid Ave. (Erie Ave. to Brooklyn Ave.) 
  • 5.9.18 thru 9.4.18
  • (Street grading, lime treatment, asphalt placement and sidewalk work)
  • Street to be re-opened 9.5.18
  • Barricades in place.
  • Residents and businesses allowed access as needed.
  • Note: Flagmen onsite as needed 
     JULY 2018 ACTIVITIES :
  • Wilmington Ave. (E. Elmira to E. Euclid Ave.): Top soil and sod placement completed.
  • E. Euclid Ave. (Wilmington Ave. to Atlanta): Curb, sidewalk and wheel chair ramps 95% completed. Top soil and sod placement 
  • E. Euclid Ave. (Atlanta to Erie Ave.): Curb, sidewalk and wheel chair ramps 70% completed.
  • E. Euclid Ave. (Erie Ave. to Brooklyn Ave.) Gas service installation. Sewer main completed and pending tie-in at Brooklyn Ave. Storm drain inlet adjustments.
  • Erie Ave. (South of E. Laurel to E. Euclid Ave.): Gas service completed. Storm drain completed. Storm drain inlet adjustments.
  • Miscellaneous street valve adjustments thru-out the project.
  • Debris and trash have been hauled away. 
 
     PLANNED ACTIVITIES FOR THE NEXT 3+ WEEKS:
  • Wilmington Ave. (E. Elmira to E. Euclid Ave.): Clean-up work.
  • E. Euclid Ave. (Wilmington Ave. to Atlanta): Complete remaining curb, sidewalk and wheel chair ramps. Top soil and sod placement.
  • E. Euclid Ave. (Atlanta to Erie Ave.): Complete remaining curb, sidewalk, and wheel chair ramps. 
  • E. Euclid Ave. (Erie Ave. to Brooklyn Ave.) Gas service installation. Sewer main tie-in at Brooklyn Ave. Storm drain inlet adjustments. Street grading, lime treatment, asphalt placement and curb, sidewalk, wheel chair ramps and driveway approaches. 
  • Erie Ave. (South of E. Laurel to E. Euclid Ave.): Storm drain inlet adjustments. Street grading, lime treatment, asphalt placement, curb, sidewalk, wheel chair ramps and driveway approaches. 
  • Miscellaneous street valve adjustments thru-out the project. 
  • Debris and trash to be hauled away. 


New driveway aproach, sidewalk & grass on Wilmington Ave.
Curb inlet installation on E. Euclid Ave.
Curb inlet installation on Erie Ave.
New curb, sidewalk and grass on Wilmington Ave.
New curb, sidewalk and grass on Wilmington Ave.
New curb, sidewalk and driveway approach 
on Wilmington Ave.
New curb, sidewalk and grass on E. Euclid Ave.
New curb, sidewalk, trees and grass on Newell Ave.
New curb, sidewalk, trees and grass at Newell Ave. & E. Elmira

New traffic signals on N. St. Mary's St. & E. Elmira St.
**PLEASE NOTE: ALL WORK IS SUBJECT TO FAVORABLE WEATHER CONDITIONS**  
THANK YOU FOR YOUR PATIENCE AS WE IMPROVE YOUR COMMUNITY.

If you have questions about the project, please contact:
  
Joey Doctor
Capital Projects Officer | TCI - City of San Antonio
210.207.8415 | joe.doctor@sanantonio.gov
or

Transportation & Capital Improvements (TCI)
PO Box 839966
San Antonio, Texas 78283-3966
210-207-8022
 
 
Visit Our Website!
Stay Connected