SR 89/Fanny Bridge Community Revitalization Project Construction/Road Updates for
 June 28 – July 8, 2018

No Construction Work Will Take Place on
Wednesday, July 4.

Construction work will take place on Friday, June 29;
Monday, July 2; Tuesday, July 3 until 12 p.m. (noon), and Thursday, July 5 – Saturday, July 7.
Items moved from the Tahoe City Wye this week:

The Williamson Blue Spruce Tree has been relocated to above the new rockery wall along SR 89 across from the Caltrans Maintenance Yard.
The Rotary Club time capsule and flagpole have been removed and will be relocated to a new island in front of Save Mart once the Wye Roundabout is completed.
SR 89/Fanny Bridge Community Revitalization Project Area
Additional Project/Road Details:
 
  • Night work is conducted Sunday thru Thursday from 8 p.m. - 9 a.m.
  • Day work is conducted Monday thru Friday for road and drainage work from 7 a.m. to 5 p.m.
  • Bridge work is conducted Monday thru Saturday from 7 a.m. – 5 p.m.

*Expect up to 20-minute delays in the project area.
 
Construction Schedule Updates:
 
The Contractor has the following tasks scheduled thru July 8:

  • Utility locating will take place throughout the project area. Expect traffic controls.
  • Near the East roundabout located along West Lake Blvd near the entrance to the Transit Center – drainage work is ongoing. Controls have been set.
  • Near the West roundabout located along SR 89 coming into Tahoe from Truckee underground utilities will be installed along with a storm drain – most of the work occurs behind temporary barrier rail, however some flagging is necessary for connections. 
  • New Truckee River Bridge – construction work on both abutments – no traffic impacts.
  • In front of Caltrans Maintenance yard, grading and work on the new paved shared-use path will be happening – work occurring behind temporary barrier rail.
  • Grading will continue on the new SR 89 alignment – no traffic impacts.
  • Southwest Gas will continue to work on the realignment.
  • Storm drain work is planned this week at night.
 
Please Note that Traffic Control Includes:
 
  • Normal temporary lane closures utilizing flaggers with a maximum 20-minute delay.
  • Flaggers are located at parking lot entrances to allow access.
  • No businesses will be blocked.
  • At the West Roundabout (near the Caltrans Maintenance Yard) K-Rail has been placed with reduced lane widths to 11-ft – same configuration as last year. K-Rail for the East Roundabout (near the Transit Center entrance) will also reduce lane widths to 11 feet.
 
Shared-Use Paths for Cyclists and Pedestrians:

  • Detours will be set.
  • No paths will be closed.
 
Stay Informed and Share with Others:

Project web page:   www.FannyBridge.org
Project email for additional questions:   suggestions@FannyBridge.org
Project construction hotline number:  775-589-5500 ext. 9
 
Project Lead Agency:  Central Federal Lands Highway Division of the Federal Highway Administration (CFLHD-FHWA)
 
Project Local Lead Agency:  Tahoe Transportation District (TTD)
 
Project Delivery Team:  CFLHD-FHWA, Tahoe Transportation District (TTD), Placer County, Tahoe Regional Planning Agency (TRPA), Caltrans, TCPUD, and the United States Forest Service (USFS)
Tahoe Transportation District
128 Market Street, Suite 3F
Stateline, Nevada 89449

Mailing Address: PO Box 499
Zephyr Cove, NV 89448

Phone: (775) 589-5500 or (530) 541-7149
FAX: (775) 588-0917
TDD/TTY: 711