Work will take place throughout the week, both day and night.

Details:
 
  • Night work is conducted Sunday thru Thursday from 8 p.m. – 9 a.m.
  • Day work is conducted Monday thru Friday for road and drainage work from 7 a.m. to 5 p.m.
  • Bridge work is conducted Monday thru Saturday from 7 a.m. – 5 p.m.
 
*Expect up to 20-minute delays in the project area.

Construction Schedule Updates:

The Contractor has the following tasks scheduled thru August 17 th :
 
1.) Western Roundabout – Underground utilities work to continue.

2.) Wye Roundabout (SR 28/SR 89 Wye) – Drainage work scheduled at night – traffic control expected.

3.) Utilities and paving work will continue near the Caltrans Maintenance Yard.
4.) New Truckee River Bridge – Construction on the bridge will continue – no traffic impact.

5.) Southwest Gas will continue to work on B Line (between western and eastern roundabouts).
 
Please note that Traffic Control includes:

  • Normal temporary lane closures utilizing flaggers with a maximum 20-minute delay.
  • Flaggers are located at parking lot entrances to allow access.
  • No businesses will be blocked.
  • At the West Roundabout (near the Caltrans Maintenance Yard) K-Rail has been placed with reduced lane widths to 11-ft – same configuration as last year.

Shared-Use Paths for Cyclists and Pedestrians:
  • Detours will be set.
  • No paths will be closed.

Stay Informed and Share with Others:
 
Project web page:   www.FannyBridge.org
Project email for additional questions:   [email protected]
Project construction hotline number:  775-589-5500 ext. 9
 
Project Lead Agency:  Central Federal Lands Highway Division of the Federal Highway Administration (CFLHD-FHWA)
 
Project Local Lead Agency:  Tahoe Transportation District (TTD)
 
Project Delivery Team:  CFLHD-FHWA, Tahoe Transportation District (TTD), Placer County, Tahoe Regional Planning Agency (TRPA), Caltrans, TCPUD, and the United States Forest Service (USFS)