10 Day Look Ahead: Renewal Project Construction Activities

 

The Stanford University Medical Center Renewal Project, which will expand Lucile Packard Children's Hospital, rebuild Stanford Hospital, modernize Hoover Pavilion, and replace School of Medicine laboratories, is underway. Below is a summary of the Renewal Project's anticipated construction activities, hours of activity, and any affected lane or road closures over the next 10 days. Please click here to subscribe to our 10 day look aheads, which will be emailed every Friday and archived on the Renewal Project website.

 

Please note that that the scope of work and dates of work are subject to change without notice, especially due to weather impacts.

Intermittent Lane Closures on Welch Road 


Welch Rd Re-Opens

 

The right hand turn lane on eastbound Welch Road near the Packard Children's construction site will be closed intermittently in order to accommodate steel deliveries onto the site. During this time, the remaining lane of traffic on eastbound Welch Road will remain open. As steel deliveries occur, the turn lane will be blocked to through traffic by traffic delineators, cones, and flagmen. Steel deliveries may occur from 6 am to 6 pm, Monday-Saturday. Bikes may share the road with vehicles while the turn lane is occupied.

 

The sidewalk adjacent to the Packard Children's construction site is closed. A pedestrian detour is in place and badge access will remain available at the back entrance of Packard Children's Hospital from Quarry Road. 

 

New Stanford Hospital Facility 

December 2012- 2018

 

Work is under way to construct the new Stanford Hospital facility in order to accommodate advances in medical technology, increase capacity, and meet new seismic safety standards. The 824,000 square foot hospital includes 368 individual patient rooms, state-of-the-art diagnostic and treatment rooms, an expanded Emergency Department, new employee parking structure, five gardens, walking trails and a meditation room. The new hospital is expected to be completed in 2017 and open for patient care in early 2018. 

 

General Updates:

 

This week's activities:

Weekday work (1/6-1/10)

Hours of Construction Activity: 7 am - 6 pm

 

Former Garden Entry/D Pod: Work to finish demolishing the former MRI offices near the hospital will continue. Off haul will continue to remove concrete walls and footings. Tunnel excavation and shoring work will continue.

 

New Hospital and Parking Garage: Hospital foundation pile installation, forming work, rebar and placement preparations for the foundation will continue. Waterproofing work will also occur.  

 

New Parking Garage: Forming work, rebar and placement of the garage concrete structure will continue this week. 

 

Lucile Packard Children's Hospital Expansion

August 2011-December 2016

 

The Packard Children's Hospital expansion, which will expand Packard's ability to care for children and expectant mothers, is under way. The new 521,000 square foot facility will add 150 patient beds, more healing spaces, and the latest medical technology. The Packard expansion is scheduled to open in 2016.

 

This week's activities:

Weekday work (1/6-1/10)

Hours of Construction: 7 am to 6 pm

 

The right hand turn lane on eastbound Welch Road near the Packard Children's construction site will be closed intermittently in order to accommodate steel deliveries onto the site. During this time, the remaining lane of traffic on eastbound Welch Road will remain open. As steel deliveries occur, the turn lane will be blocked to through traffic by traffic delineators, cones, and flagmen. Steel deliveries may occur from 6 am to 6 pm, Monday-Saturday.

 

The sidewalk adjacent to the Packard Children's construction site has been closed due to the steel deliveries. A pedestrian detour is in place.

 

Structural steel welding, waterproofing and rebar installation will occur on the Packard construction site this week. Concrete pours are scheduled to occur on Tuesday, 1/7, Thursday, 1/9, and Friday, 1/10, on the site.  Rebar deliveries are scheduled to occur Tuesday, 1/7, through Friday, 1/10, at both the Quarry Road and Welch Road construction gates. 

 

Excavation off-haul will occur during off hours during the week as necessary.

 

Access to the rear entrance of Packard Children's will remain open throughout construction although some egress detours will be in place.

 

General Reminders

 

Motorists: please be mindful of sharing the road with bicyclists. 

 

Consider alternatives to driving, including Stanford's free Marguerite shuttle, biking, carpooling, and transit. Try the do-it-yourself commute planning tool.

 

Cyclists: please be mindful of sharing the sidewalk with pedestrians. Those who choose not to share the road and use the sidewalks must walk their bicycles.

 

Pedestrians: must use the new designated crosswalks on Welch Road. Jaywalking is illegal and especially unsafe in active construction areas. Maps with new pedestrian crosswalks are available at www.SUMCRenewal.org. Thank you!

 

Questions?

  

You can find the most up to date information on the Renewal Project website at www.SUMCRenewal.org

 

You can also sign up for project email notices on the website. For additional information regarding site work, email the Renewal Project at info@sumcrenewal.org or call the 24-hour Construction Hotline: (650) 701-SUMC (7862).

 