10 Day Look Ahead: Renewal Project Construction Activities

The Stanford University Medical Center Renewal Project, which will expand Lucile Packard Children's Hospital, rebuild Stanford Hospital, modernize Hoover Pavilion, and replace School of Medicine laboratories, is underway. Below is a summary of the Renewal Project's anticipated construction activities, hours of activity, and any affected lane or road closures over the next 10 days. Please click here to subscribe to our 10 day look aheads, which will be emailed every Friday and archived on the Renewal Project website.

Please note that that the scope of work and dates of work are subject to change without notice, especially due to weather impacts.

New Stanford Hospital Facility
December 2012 - 2018

Work is under way to construct the new Stanford Hospital facility in order to accommodate advances in medical technology, increase capacity, and meet new seismic safety standards. The 824,000 square foot hospital includes 368 individual patient rooms, state-of-the-art diagnostic and treatment rooms, an expanded Emergency Department, new employee parking structure, five gardens, walking trails and a meditation room. The new hospital is expected to be completed in 2017 and open for patient care in 2018.

This week's activities:

What to expect this weekend (1/7-1/8)
Hours of Construction Activity: 7 am to 6 pm

New Hospital and Parking Garage: Work to rough-in overhead mechanical, electrical and plumbing systems, frame the interiors and fireproof the new hospital may continue on Saturday, 1/7.
 
Weekday Work (1/9-1/13)
Hours of Construction Activity: 7 am to 8 pm for regular construction
 
Former Garden Entry/D Pod: The final concrete deck pour is expected on the pedestrian bridge.
 
New Hospital and Parking Garage:  The installation of the exterior wall systems continues throughout the building. The Helistop is being constructed on the roof of the building. Inside the hospital, interior finishes like ceiling and drywall installation, framing, and painting are underway. Installation of the service and public elevators continues. Work continues in the oxygen yard, and a concrete pour is expected. Roofing installation is also underway.
 
What to expect next weekend (1/14-1/15)
Hours of Construction Activity: 7 am to 6 pm
 
New Hospital and Parking Garage: Work to rough-in overhead mechanical, electrical and plumbing systems, frame the interiors and fireproof the new hospital may continue on Saturday, 1/14.
 
Lucile Packard Children's Hospital Stanford Expansion
August 2011-Summer 2017

The Lucile Packard Children's Hospital Stanford expansion, which will expand the hospital's ability to care for children and expectant mothers, is underway. The new 521,000 square foot facility will add 149 patient beds, more healing spaces, and the latest medical technology. The hospital expansion is expected to be completed and open for patient care in 2017.

*General construction activity on the Lucile Packard Children's Hospital Stanford Expansion site is approved Monday-Friday 6 am to 8 pm and Saturday 7 am to 6 pm. Click here to view construction activity permitted outside of normal construction hours.
  
This week's activities:

What to expect this weekend (1/7-1/8)
Hours of Construction Activity: 7 am to 6 pm for regular construction
 
Work will continue on the expansion site for drywall installation, painting, door framing, ceiling and flooring installation and mechanical and electrical work on Saturday, 1/7. Interior elevator work is expected on Saturday, 1/7 and Sunday, 1/8.
 
Weekday work (1/9-1/13)
Hours of Construction Activity: 6 am to 8 pm for regular construction
 
Lobby glass installation continues.
 
Inside the building, finish construction includes drywall installation, painting, door framing, ceiling and flooring installation, HVAC and mechanical, electrical & plumbing installation in the North and South Towers. Elevator installation continues with four elevators currently in service.
 
The crosswalk on Quarry Road and Quarry Extension (near the construction trailers) will remain closed to accommodate deliveries and concrete pours near the perimeter of the construction site. A pedestrian detour is in place.
 
Access to the rear entrance of Packard Children's will remain open throughout construction although some egress detours will be in place.
 
What to expect next weekend (1/14-1/15)
Hours of Construction Activity: 7 am to 6 pm for regular construction
 
Work will continue on the expansion site for drywall installation, painting, door framing, ceiling and flooring installation and mechanical and electrical work on Saturday, 1/14. Interior elevator work is expected on Saturday, 1/14 and Sunday, 1/15.

School of Medicine BioMedical Innovations Building
January 2017 - Summer 2019

The BioMedical Innovations Building (BMI) will be a state-of-the-art facility that fully supports the talent and vision of the School of Medicine to translate medical research discoveries into treatments and cures. The new building will be approximately 215,500 sf with four above-grade floors of research labs and light-filled gathering places, and a lower basement level with reduced functional square footage for utility support. A connective tunnel to other nearby research facilities is part of the proposed design.
 
Current Activities:
 
Weekday Work (1/9-1/13)
Hours of Construction Activity: 6 am to 4 pm for regular construction
 
Construction fencing has gone up around the project site. Construction is expected to begin in late January 2017 with the demolition of the valet parking lot.
 
To ensure the safety of our patients, visitors and staff during construction, a new sidewalk will be added from our parking garages to the hospital and School of Medicine campus. Please stay on designated paths and take extra precaution when crossing Pasteur Drive.

General Reminders

Motorists: please be mindful of sharing the road with bicyclists. 

 

Consider alternatives to driving, including Stanford's free Marguerite shuttle, biking, carpooling, and transit. Try the do-it-yourself commute planning tool.

 

Cyclists: please be mindful of sharing the sidewalk with pedestrians. Those who choose not to share the road and use the sidewalks must walk their bicycles.

 

Pedestrians: must use the new designated crosswalks on Welch Road. Jaywalking is illegal and especially unsafe in active construction areas. Thank you!