10 Day Look Ahead: Renewal Project Construction Activities

 

The Stanford University Medical Center Renewal Project, which will expand Lucile Packard Children's Hospital, rebuild Stanford Hospital, modernize Hoover Pavilion, and replace School of Medicine laboratories, is underway. Below is a summary of the Renewal Project's anticipated construction activities, hours of activity, and any affected lane or road closures over the next 10 days. Please click here to subscribe to our 10 day look aheads, which will be emailed every Friday and archived on the Renewal Project website.

 

Please note that that the scope of work and dates of work are subject to change without notice, especially due to weather impacts.

Welch Road Utility Project


Recommended Driving Routes: During 2 pm-6 pm, when the dog leg is open, we recommend the following routes to increase traffic flow on Welch and Pasteur: northbound Sand Hill Road traffic should use Oak; southbound Sand Hill Road traffic should use Pasteur. Dynamic message boards will be used at these intersections to help inform recommended traffic flow.


August 2011-September 2013


One of the first steps in the effort to expand Packard Children's Hospital and rebuild Stanford Hospital includes utility work and surface improvements. The Welch Road Utility Project includes: replacing utility services and information technology infrastructure along Welch and Quarry Roads to serve the new hospital facilities once they are built; the widening of Welch Road; replacement of sidewalks, curbs and gutters; planting of new street trees and installation of planted medians and street lighting.


Note: Access to the Emergency Room will be maintained at all times.

 

This week's activities:


What to expect this weekend (2/3-2/5)
Hours of Construction Activity: 7am - 3:30 pm


Work will continue on Welch Road to install a new water main. Activity will occur near the driveway entrances to 777 Welch and 801 Welch. Access to the driveways will be maintained at all times.


Weekday work (2/6-2/10)
Hours of Construction Activity: 7am - 3:30 pm


Welch Rd is now a one-lane, one-way road going West from Quarry to Pasteur Drive. This change will be in effect for two years. We thank you for your patience regarding this significant change and ask that you please adjust your driving route accordingly. South Pasteur Drive is now a two-way two-lane road. North Pasteur Drive is closed between Blake Wilbur Drive and Sand Hill Road. 


K-Rail will remain in place on the inboard side of Quarry Rd (between Welch and continuing up to the Quarry Extension near the turn to the Emergency Department) in order to facilitate ongoing utility work. This reduces Quarry to a two lane, two direction road during this time. Access will be maintained to the Emergency Department at all times.


Work on the Stanford University Lake Water project will continue in the L-3 parking lot (corner of Quarry at Welch). This is temporarily displacing some 'A' permit parking in L-3. Additional 'A' permit parking is available at the Andronico's site at the Stanford Shopping Center during this time. The Lake Water project is estimated to be completed next Friday, 2/10.


Utility work will continue in the driveway entrances to 777 and 801 Welch Road. Access to the driveways will be maintained at all times, however temporary delays may occur.


Work will begin to demolish existing sewer, water and gas utilities on Quarry Road. Work will also begin to install a new hot and chilled water line on Quarry Road.


Hardscape demolition of the parking lot behind the Blake Wilbur Clinic will continue. 


Please be cautious of construction trucks entering the road. Access to the Emergency Room will be maintained at all times.


Night work (2/6-2/10)
Hours of construction activity: 8 pm-5 am


Beginning Monday, 2/6 work will begin on Blake Wilbur Drive near the AMC to tie-in a communications vault. This work is expected to occur every night next week.


What to expect next weekend (2/10-2/12)
Hours of Construction Activity: 8am - 5 pm


Utility work may occur next weekend on both Welch and Quarry Roads.  

Lucile Packard Children's Hospital Expansion (Make-Ready Site)

August 2011-October 2012

 

The Packard Children's Hospital expansion site prep (known as the 'Make-Ready' site) includes the demolition of 701 & 703 Welch and the construction of a shoring wall and utility tunnel in preparation for the Packard Children's expansion.


This week's activities: 

 

What to expect this weekend (2/3-2/5)
Hours of Construction Activity: 7 am - 3:30 pm


Relocation of the storm drain line will occur at the south shoring wall (near the Day Hospital) on Saturday, 2/4. Work will also occur to excavate for a shoring test at the east shoring wall on the Make-Ready site.


Weekday work (2/6-2/10)
Hours of Construction Activity: 7 am - 3:30 pm


Excavation of the new Make-Ready site will continue. Work to remove and off haul the top layers of soil from the site will also continue. As excavation work occurs, please be mindful of additional hauling trucks entering the road.


Installation of the shoring wall will also occur on site.


Access to the rear entrance of Packard Children's will remain open throughout construction.


Continued utility work requires that the sidewalk connecting the rear entrance of Lucile Packard Children's Hospital to the Falk Building remain closed through February 2012. Access to the Falk Building from Packard Children's has been rerouted through Stanford Hospital & Clinics. Signage has been placed to assist routing from Packard Children's through Stanford Hospital to an exit leading to the west side of the Falk Building. Please note that this door requires badge access. The Outpatient Heart Center will continue to assist families and escort them to and from the Falk Center for appointments.


What to expect next weekend (2/10-2/12)
Hours of Construction Activity: 7 am - 3:30 pm


Shoring and excavation work may continue next weekend on the Make-Ready site.

Hoover Pavilion Modernization 

August 2011-July 2013

 

Construction is underway to modernize and restore Hoover Pavilion, the original Palo Alto Hospital, in order to accommodate modern medicine and create a cohesive expansion to the Medical Center campus.


This week's activities:

 

What to expect this weekend (2/3-2/5)
Hours of Construction Activity: 7 am - 3:30 pm


Structural work within the Pavilion will continue over the weekend.


Weekday work (2/6-2/10)
Hours of Construction Activity: 7 am - 3:30 pm


Structural work is ongoing with the installation of overhead structural supports and localized slab strengthening. This work is targeted to be completed next week.


Wall layout and framing will continue.  Vertical mechanical shaft installation is in progress.


Concrete removal on the exterior fa´┐Żade is close to completion.  The fabric wrap is targeted to be removed by the end of the month.  Installation of the refurbished wood windows will continue on the lower floors of the Pavilion. 

 
What to expect next weekend (2/10-2/12)
Hours of Construction Activity: 7 am - 3:30 pm


No work is scheduled for next weekend.

 

General Reminders

 

Motorists: please be mindful of sharing the road with bicyclists. Cyclists who choose not to share the road and use the sidewalks must walk their bicycles.

 

Pedestrians must use the new designated crosswalks on Welch Road. Jaywalking is illegal and especially unsafe in active construction areas. Maps with new pedestrian crosswalks are available at www.SUMCRenewal.org. Thank you!

 

Consider alternative transportation. Stanford's free Marguerite shuttle service offers convenient connections between the Stanford Medical Center and the Palo Alto Transit Center and other destinations. Eligible university and hospital employees may request free Caltrain and VTA transit passes and those with a Stanford ID ride for free on AC Transit's Line U East Bay Express bus. Consider a do-it-yourself transit and/or bicycle commute plan.

 

Questions?

 
You can find the most up to date information on the Renewal Project website at www.SUMCRenewal.org


You can also sign up for project email notices on the website. For additional information regarding site work, email the Renewal Project at info@stanfordpackard.org or call the 24-hour Construction Hotline: (650) 701-SUMC (7862).

 