10 Day Look Ahead: Renewal Project Construction Activities

 

The Stanford University Medical Center Renewal Project, which will expand Lucile Packard Children's Hospital, rebuild Stanford Hospital, modernize Hoover Pavilion, and replace School of Medicine laboratories, is underway. Below is a summary of the Renewal Project's anticipated construction activities, hours of activity, and any affected lane or road closures over the next 10 days. Please click here to subscribe to our 10 day look aheads, which will be emailed every Friday and archived on the Renewal Project website.

 

Please note that that the scope of work and dates of work are subject to change without notice, especially due to weather impacts.

Welch Road Utility Project

August 2011-September 2013

 

One of the first steps in the effort to expand Packard Children's Hospital and rebuild Stanford Hospital includes utility work and surface improvements. The Welch Road Utility Project includes: replacing utility services and information technology infrastructure along Welch and Quarry Roads to serve the new hospital facilities once they are built; the widening of Welch Road; replacement of sidewalks, curbs and gutters; planting of new street trees and installation of planted medians and street lighting.

 

Note: Access to the Emergency Room will be maintained at all times.

 

This week's activities:

 

What to expect this weekend (2/9-2/10)

Hours of Construction Activity: 7 am - 3:30 pm

 

No work is scheduled to occur this weekend.

 

Weekday work (2/11-2/15)

Hours of Construction Activity: 7 am - 3:30 pm

 

Hot water line work will continue on Welch Road. The pedestrian crosswalk will remain temporarily relocated in front of Lucile Packard Children's Hospital (725 Welch) next week in order to accommodate this work.

 

City of Palo Alto Gas crews will continue to work on gas lateral switch overs.

 

Please be cautious of construction trucks entering the road. Access to the Emergency Room will be maintained at all times.

 

What to expect next weekend (2/16-2/17)

Hours of Construction Activity: 7 am - 5 pm

 

No work is scheduled to occur next weekend.

 

New Stanford Hospital Facility 

March 2012-March 2013

 

The New Stanford Hospital facility site prep (known as the 'Make-Ready' site) includes surface demolition and utility work on North Pasteur Drive, and the demolition of Parking Structure 3 and 1101 Welch in order to make way for the new hospital facilities. 

 

This week's activities:


What to expect this weekend (2/9-2/10)

Hours of Construction Activity: 7 am - 4 pm

 

Work will continue to construct the temporary valet parking lot (FIM-1) on S. Pasteur Drive near the School of Medicine on Saturday, 2/9.

 

Weekday work (2/4-2/8)

Hours of Construction Activity: 7 am - 4 pm

 

Demolition of 1101 Welch will continue next week. Some additional trees may be relocated from the site onto the University campus.

 

Work will continue to construct the temporary valet parking lot (FIM-1) on S. Pasteur Drive near the School of Medicine.

 

Work will continue to reroute an existing irrigation line at the service drive and N. Pasteur Drive near Stanford Hospital & Clinics.

 

What to expect next weekend (2/16-2/17)

Hours of Construction Activity: 7 am - 4 pm

 

Work on the temporary valet lot (FIM-1) is expected to occur next Saturday, 2/16. 

 

Lucile Packard Children's Hospital Expansion

September 2012-December 2016

 

The Packard Children's Hospital expansion, which will expand Packard's ability to care for children and expectant mothers, is underway. The new facility is scheduled to open in 2016.

 

This week's activities: 

 

What to expect this weekend (2/9-2/10)

Hours of Construction Activity: 7 am - 3:30 pm; nighttime work in parking lot of 730 Welch Road

 

Heavy truck off haul from the Packard expansion site will continue on Saturday, 2/9.

 

Excavation, oxygen line and tie-back work will also continue over the weekend.

 

Construction and trenching activities will occur in the parking lot at 730 Welch Road as part of the temporary MRI construction.

 

Weekday work (2/11-2/15)

Hours of Construction Activity: 7 am - 5 pm; nighttime work in parking lot of 730 Welch Road

 

Crews will continue to off haul dirt from the site next week. Oxygen line work will continue and is scheduled to be complete by the end of the week.

 

Tie back work will continue.

 

Utility work will continue near the Stanford Hospital & Clinics side of the Falk Building. Access to the Falk Building will be maintained at all times via the Stanford Hospital side of the building. Pedestrian detour signage is in place.

 

Access to the rear entrance of Packard Children's will remain open throughout construction.

 

Next week, night work will occur next week in the parking lot of 730 Welch Road in order to perform trenching activities as part of the temporary MRI construction. Staff will not be able to park in the 730 Welch parking lot during this time.

 

What to expect next weekend (2/16-2/17) 

Hours of Construction Activity: 7 am - 3:30 pm

 

Work is scheduled to continue on the Packard expansion site next weekend.

 

Hoover Garage

May 2012-July 2013

 

Hoover Pavilion, the original Palo Alto Hospital, has been renovated and opened December 2012 to accommodate modern medicine and create a cohesive extension of the Medical Center campus. The garage will enable additional parking for patients and staff.

 

This week's activities:


What to expect this weekend (2/9-2/10)

Hours of Construction Activity: 7 am - 5:30 pm

 

Work will continue on Saturday, 2/9, to construct the new parking garage.

 

Weekday work (2/11-2/12)

Hours of Construction Activity: 7 am - 5:30 pm

 

Concrete precast panels will continue to be delivered next week and panel erection will continue.  Panel deliveries and erection will continue through the spring.

 

What to expect next weekend (2/16-2/17)

Hours of Construction Activity: 7 am - 5:30 pm

 

Work may continue on Saturday, 2/16, to construct the new parking garage.

General Reminders

 

Motorists: please be mindful of sharing the road with bicyclists. 

 

Consider alternatives to driving, including Stanford's free Marguerite shuttle, biking, carpooling, and transit. Try the do-it-yourself commute planning tool.

 

Cyclists: please be mindful of sharing the sidewalk with pedestrians. Those who choose not to share the road and use the sidewalks must walk their bicycles.

 

Pedestrians must use the new designated crosswalks on Welch Road. Jaywalking is illegal and especially unsafe in active construction areas. Maps with new pedestrian crosswalks are available at www.SUMCRenewal.org. Thank you!

 

Questions?

  

You can find the most up to date information on the Renewal Project website at www.SUMCRenewal.org

 

You can also sign up for project email notices on the website. For additional information regarding site work, email the Renewal Project at info@sumcrenewal.org or call the 24-hour Construction Hotline: (650) 701-SUMC (7862).

 