10 Day Look Ahead: Renewal Project Construction Activities

 

The Stanford University Medical Center Renewal Project, which will expand Lucile Packard Children's Hospital, rebuild Stanford Hospital, modernize Hoover Pavilion, and replace School of Medicine laboratories, is underway. Below is a summary of the Renewal Project's anticipated construction activities, hours of activity, and any affected lane or road closures over the next 10 days. Please click here to subscribe to our 10 day look aheads, which will be emailed every Friday and archived on the Renewal Project website.

 

Please note that that the scope of work and dates of work are subject to change without notice, especially due to weather impacts.

Welch Road Utility Project

August 2011-September 2013

 

One of the first steps in the effort to expand Packard Children's Hospital and rebuild Stanford Hospital includes utility work and surface improvements. The Welch Road Utility Project includes: replacing utility services and information technology infrastructure along Welch and Quarry Roads to serve the new hospital facilities once they are built; the widening of Welch Road; replacement of sidewalks, curbs and gutters; planting of new street trees and installation of planted medians and street lighting.

 

Note: Access to the Emergency Room will be maintained at all times.

 

This week's activities:

 

What to expect this weekend (3/9-3/10)

Hours of Construction Activity: 7 am - 3:30 pm

 

No work scheduled.

 

Weekday work (3/11-3/15)

Hours of Construction Activity: 7 am - 3:30 pm

 

Hot water line work will continue on Welch Road.

 

The bus pick-up and drop-off has returned to the permanent bus stop location on Quarry.

 

Please be cautious of construction trucks entering the road. Access to the Emergency Room will be maintained at all times.

 

What to expect next weekend (3/16-3/17)

Hours of Construction Activity: 7 am - 5 pm

 

Pending weather, no work is currently scheduled. 

 

New Stanford Hospital Facility 

March 2012-March 2013

 

The New Stanford Hospital facility site prep (known as the 'Make-Ready' site) includes surface demolition and utility work on North Pasteur Drive, and the demolition of Parking Structure 3 and 1101 Welch in order to make way for the new hospital facilities. 

 

This week's activities:

 

What to expect this weekend (3/9-3/10)

Hours of Construction Activity: 9 pm - 5 am

 

No work scheduled.

 

Weekday work (3/11-3/15)

Hours of Construction Activity: 7 am - 3:30 pm

 

Foundation work will continue on the North wall of the Make-Ready site.

 

What to expect next weekend (3/16-3/17)

Hours of Construction Activity: 7 am - 4 pm

 

No work is scheduled to occur. 

 

Lucile Packard Children's Hospital Expansion

September 2012-December 2016

 

The Packard Children's Hospital expansion, which will expand Packard's ability to care for children and expectant mothers, is underway. The new facility is scheduled to open in 2016.

 

This week's activities: 

 

What to expect this weekend (3/9-3/10)

Hours of Construction Activity: 7 am - 3:30 pm

 

On Saturday, March 9, a construction project for the Lucile Packard Children's Hospital clinic located at 730 Welch will require the delivery of pre-fab buildings. This work will occur between the hours of 7 am - 7 pm.

 

Due to the significant size of the delivery and the limitations of the existing Vineyard driveway to the property, the trucks will need to make use of Vineyard to queue trucks and use a crane to place the buildings into the 730 site. This may result in traffic being rerouted on Vineyard at times. Traffic will be controlled throughout this exercise with flaggers and guides. Driveways to the Stanford Barn will remain open.

 

Overnight parking at 730 Welch on the evening of Friday, March 8 will not be permitted.

 

Off haul will occur on the expansion site.

 

CT/MRI - The contractor will work this weekend installing control wiring from the ground floor of LPCH to the roof. The contractor will pull wire in conduits previously installed from infection control cubes.

 

Day Hospital - Potential noisy work involving removal of the concrete deck to repair damaged rebar. The work is pending approval.

 

Weekday work (3/11-3/15)

Hours of Construction Activity: 7am - 5 pm

 

Soldier piles will continue to be installed near Packard Children's Hospital. This drilling work is being closely coordinated with the hospital and is not anticipated to cause noise or vibration.

 

Concrete trucks will be on site and in the hole for shot crete activities

 

Excavation work and off hauling of soil will also occur.

 

Demolition of old utilities will also occur on the expansion site.

 

Work will continue in the parking lot of 730 Welch Road to construct a temporary MRI facility.

 

Access to the rear entrance of Packard Children's will remain open throughout construction although some egress detours will be in place.

 

Work will continue on both the CT/MRI and Day Hospital projects.

 

What to expect next weekend (3/16-3/17) 

Hours of Construction Activity: 7 am - 3:30 pm

 

Work will occur on the Packard expansion site including soldier pile installation and excavation.

 

At this time, no work is scheduled to occur on CT/MRI or Day Hospital projects. 

 

Hoover Garage

May 2012-July 2013

 

Hoover Pavilion, the original Palo Alto Hospital, has been renovated and opened December 2012 to accommodate modern medicine and create a cohesive extension of the Medical Center campus. The garage will enable additional parking for patients and staff.

 

This week's activities:

 

What to expect this weekend (3/9-3/10)

Hours of Construction Activity: 7 am- 5:30 pm

 

Work may occur on site.

 

Weekday work (3/11-3/15)

Hours of Construction Activity: 7 am - 5:30 pm

 

Concrete precast panels will continue to be delivered and panel erection will continue.  This will continue through the spring.

 

What to expect next weekend (3/16-3/17)

Hours of Construction Activity: 7 am - 5:30 pm

 

Work may occur on site.

 

General Reminders

 

Motorists: please be mindful of sharing the road with bicyclists. 

 

Consider alternatives to driving, including Stanford's free Marguerite shuttle, biking, carpooling, and transit. Try the do-it-yourself commute planning tool.

 

Cyclists: please be mindful of sharing the sidewalk with pedestrians. Those who choose not to share the road and use the sidewalks must walk their bicycles.

 

Pedestrians must use the new designated crosswalks on Welch Road. Jaywalking is illegal and especially unsafe in active construction areas. Maps with new pedestrian crosswalks are available at www.SUMCRenewal.org. Thank you!

 

Questions?

  

You can find the most up to date information on the Renewal Project website at www.SUMCRenewal.org

 

You can also sign up for project email notices on the website. For additional information regarding site work, email the Renewal Project at info@sumcrenewal.org or call the 24-hour Construction Hotline: (650) 701-SUMC (7862).

 