10 Day Look Ahead: Renewal Project Construction Activities

 

The Stanford University Medical Center Renewal Project, which will expand Lucile Packard Children's Hospital, rebuild Stanford Hospital, modernize Hoover Pavilion, and replace School of Medicine laboratories, is underway. Below is a summary of the Renewal Project's anticipated construction activities, hours of activity, and any affected lane or road closures over the next 10 days. Please click here to subscribe to our 10 day look aheads, which will be emailed every Friday and archived on the Renewal Project website.

 

Please note that that the scope of work and dates of work are subject to change without notice, especially due to weather impacts.

Welch Road Utility Project

August 2011-September 2013


One of the first steps in the effort to expand Packard Children's Hospital and rebuild Stanford Hospital includes utility work and surface improvements. The Welch Road Utility Project includes: replacing utility services and information technology infrastructure along Welch and Quarry Roads to serve the new hospital facilities once they are built; the widening of Welch Road; replacement of sidewalks, curbs and gutters; planting of new street trees and installation of planted medians and street lighting.


Note: Access to the Emergency Room will be maintained at all times.

 

This week's activities:

 

What to expect this weekend (4/14-4/15) 

Hours of Construction Activity: 7 am - 3:30 pm

 

Utility work may occur on Welch and Quarry Roads on Saturday, 4/14.

 

Weekday work (4/16-4/20) 

Hours of Construction Activity: 7 am - 3:30 pm


Welch Rd is now a one-lane, one-way road going West from Quarry to Pasteur Drive.
This change will be in effect for two years. We thank you for your patience regarding this significant change and ask that you please adjust your driving route accordingly. South Pasteur Drive is now a two-way two-lane road. North Pasteur Drive is closed between Blake Wilbur Drive and Sand Hill Road. 

  

K-Rail will remain in place on the inboard side of Quarry Rd (between Welch and continuing up to the Quarry Extension near the turn to the Emergency Department) in order to facilitate ongoing utility work. This reduces Quarry to a two lane, two direction road during this time. Access will be maintained to the Emergency Department at all times.

 

Work will continue to install a new hot water line on Quarry Road. This work will require crossing the 'Y' area of the Quarry Extension. Access to the Emergency Department will be maintained at all times with flagmen and signage.

 

Work on the chilled water line will continue in the driveway entrance to Lucile Packard Children's Hospital on Welch Rd. This work was delayed due to weather conditions and is anticipated to be complete by the end of the week. Access in and out of the entrance to the hospital will be maintained at all times via flagmen and signage.

 

Work to install new power line on Quarry Road will continue.

 

Heavy demolition will continue in the lot behind the Blake Wilbur Clinics next week. This work includes the use of a grinding machine to strip the asphalt. Some noise and vibration impacts will occur during this effort.

 

Dirt may be off hauled from the site.

 

Please be cautious of construction trucks entering the road. Access to the Emergency Room will be maintained at all times.

 

What to expect next weekend (4/21-4/22) 

Hours of Construction Activity: 8 am - 5 pm

 

Utility work may occur on Quarry and Welch Roads, pending weather conditions. Dirt may be off hauled from the site.

 

New Stanford Hospital Facility (Make-Ready Site)

March 2012-March 2013

 

The New Stanford Hospital facility site prep (known as the 'Make-Ready' site) includes surface demolition and utility work on North Pasteur Drive, and the demolition of Parking Structure 3 and 1101 Welch in order to make way for the new hospital facilities. 

 

This week's activities:

 

What to expect this weekend (4/14-4/15)

Hours of Construction Activity: 7 am - 3:30 pm

 

Installation of the sanitary sewer on North Pasteur up to Blake Wilbur Drive will continue.

 

Weekday work (4/16-4/20) 

Hours of Construction Activity: 7 am - 3:30 pm

 

Work to construct Kaplan Drive has been permitted and will begin in the coming weeks. Before actual construction work begins, additional tree protection enhancements will be put in place on the Kaplan Lawn site. This work will be contained on the site. All construction traffic will enter and exit on N. Pasteur.

 

The installation of the sanitary sewer on North Pasteur between Welch Rd and Blake Wilbur Drive will continue. A temporary tie-in to Blake Wilbur was delayed due to weather conditions.

 

Work to install the base for the New Stanford Hospital external mockups display is scheduled to continue next week. A concrete slab will be poured on top of a small section of landscaping above PS-4 on Welch Rd at N. Pasteur to secure the life size building samples. All work will be performed behind the construction fence.

 

What to expect next weekend (4/21-4/22) 

Hours of Construction Activity: 7 am - 3:30 pm

 

Installation of the sanitary sewer on North Pasteur up to Blake Wilbur Drive may continue next weekend.

 

Lucile Packard Children's Hospital Expansion (Make-Ready Site)

August 2011-October 2012

 

The Packard Children's Hospital expansion site prep (known as the 'Make-Ready' site) includes the demolition of 701 & 703 Welch and the construction of a shoring wall and utility tunnel in preparation for the Packard Children's expansion.

 

This week's activities:

 

What to expect this weekend (4/14-4/15)

Hours of Construction Activity: 7 am - 3:30 pm

 

Work will occur on Saturday, 4/14 to test the tie-backs on the Make-Ready site. Shoring work will also continue.

 

Weekday work (4/16-4/20)
Hours of Construction Activity: 7 am - 5 pm

 

The steel bridge installation near the Day Hospital and Imaging has been delayed. This installation work should begin in the coming weeks.

 

Pending weather conditions, foundation work will continue for the new utility tunnel. This work includes installing rebar, pouring concrete and drilling piles. Excavation of the new Make-Ready site will continue. Note: this work requires extra shifts on the Make-Ready site (see above hours of activity).

 

Work to remove and off haul the top layers of soil from the site will also continue, pending weather conditions. As excavation work occurs, please be mindful of additional hauling trucks entering the road. The retrofit of the chilled water line in the tunnel will also continue next week.

 

Installation of shoring walls will continue on site.

 

Access to the rear entrance of Packard Children's will remain open throughout construction.

 

What to expect next weekend (4/21-4/22)
Hours of Construction Activity: 7 am - 3:30 pm

 

Foundation work may continue for the new utility tunnel on Saturday 4/21. Soil will be off-hauled from the site, pending weather conditions. Utility work near the Falk Building will also continue near the SHC side of the building. Access to the Falk Building will be maintained at all times. 

 

Hoover Pavilion Modernization 

August 2011-July 2013

 

Construction is underway to modernize and restore Hoover Pavilion, the original Palo Alto Hospital, in order to accommodate modern medicine and create a cohesive expansion to the Medical Center campus.


This week's activities:

 

What to expect this weekend (4/14-4/15)

Hours of Construction Activity: 7 am - 5:30 pm

 

Roofing, elevator shaft and stairwell work within the Pavilion will occur on Saturday, 4/14.

 

Weekday work (4/16-4/20)

Hours of Construction Activity: 7 am - 5:30 pm

 

Elevator shaft and stairwell work will continue.  Please note that this work will require the contractor to work 10-hr days and perform Saturday work for two more weeks (see above hours of activity).

 

Installation of overhead structural supports and localized slab strengthening is close to completion.

 

Wall framing will continue on the upper floors.

 

Mechanical, electrical, plumbing and fire sprinkler line installation are in progress.

 

Roofing installation continues on the east wing. Drywall installation will begin this week upon completion of the south wing, drywall installation.

 

Restoration of the exterior concrete continues.

 

What to expect next weekend (4/21-4/22)

Hours of Construction Activity: 7 am - 5:30 pm

 

Elevator shaft and stairwell work within the Pavilion will occur on Saturday, 4/21. 

 

General Reminders

 

Motorists: please be mindful of sharing the road with bicyclists. Cyclists who choose not to share the road and use the sidewalks must walk their bicycles.

 

Cyclists: please be mindful of sharing the sidewalk with pedestrians. Those who choose not to share the road and use the sidewalks must walk their bicycles.

 

Pedestrians must use the new designated crosswalks on Welch Road. Jaywalking is illegal and especially unsafe in active construction areas. Maps with new pedestrian crosswalks are available at www.SUMCRenewal.org. Thank you!

 