10 Day Look Ahead: Renewal Project Construction Activities

 

The Stanford University Medical Center Renewal Project, which will expand Lucile Packard Children's Hospital, rebuild Stanford Hospital, modernize Hoover Pavilion, and replace School of Medicine laboratories, is underway. Below is a summary of the Renewal Project's anticipated construction activities, hours of activity, and any affected lane or road closures over the next 10 days. Please click here to subscribe to our 10 day look aheads, which will be emailed every Friday and archived on the Renewal Project website.

 

Please note that that the scope of work and dates of work are subject to change without notice, especially due to weather impacts.

Welch Road Utility Project

August 2011-September 2013


One of the first steps in the effort to expand Packard Children's Hospital and rebuild Stanford Hospital includes utility work and surface improvements. The Welch Road Utility Project includes: replacing utility services and information technology infrastructure along Welch and Quarry Roads to serve the new hospital facilities once they are built; the widening of Welch Road; replacement of sidewalks, curbs and gutters; planting of new street trees and installation of planted medians and street lighting.


Note: Access to the Emergency Room will be maintained at all times.

 

This week's activities:

 

What to expect this weekend (4/21-4/22)

Hours of Construction Activity: 7 am - 3:30 pm

 

Hot water line work behind the K-Rail in Quarry will continue on Saturday, 4/21. Chilled water line work in Welch will also continue, moving south. Power line trenching work in Welch will continue, moving north.

 

Dirt will be off hauled from the Pasteur Drive site.

 

Weekday work (4/23-4/27)

Hours of Construction Activity: 7 am - 3:30 pm

 

Welch Rd is now a one-lane, one-way road going West from Quarry to Pasteur Drive. This change will be in effect for two years. We thank you for your patience regarding this significant change and ask that you please adjust your driving route accordingly. South Pasteur Drive is now a two-way two-lane road. North Pasteur Drive is closed between Blake Wilbur Drive and Sand Hill Road. 

 

K-Rail will remain in place on the inboard side of Quarry Rd (between Welch and continuing up to the Quarry Extension near the turn to the Emergency Department) in order to facilitate ongoing utility work. This reduces Quarry to a two lane, two direction road during this time. Access will be maintained to the Emergency Department at all times.

 

Work will continue to install a new hot water line on Quarry Road. A portion of this work will continue to take place outside of the K-Rail in the quarry Extension. Access to the Emergency Department will be maintained at all times.

 

Work to install new power lines on Quarry Road will also continue.

 

Work on the chilled water line and the new power lines will continue on Welch Rd, moving south. This work will occur near the driveway entrance to 801 Welch next week. Access in and out of the entrance to 801 Welch will be maintained at all times via flagmen and signage.

 

Please be cautious of construction trucks entering the road. Access to the Emergency Room will be maintained at all times.

 

What to expect next weekend (4/28-4/29) 

Hours of Construction Activity: 7 am - 3:30 pm

 

Utility work may occur on Quarry and Welch Roads, pending weather conditions. Dirt may be off hauled from the site.

 

Learn more about the Welch Road Utility Project

 

New Stanford Hospital Facility (Make-Ready Site)

March 2012-March 2013

 

The New Stanford Hospital facility site prep (known as the 'Make-Ready' site) includes surface demolition and utility work on North Pasteur Drive, and the demolition of Parking Structure 3 and 1101 Welch in order to make way for the new hospital facilities. 

 

This week's activities:

 

What to expect this weekend (4/21-4/22)

Hours of Construction Activity: 7 am - 3:30 pm

 

No work is scheduled to occur this weekend.

 

Weekday work (4/23-4/27)

Hours of Construction Activity: 7 am - 3:30 pm

 

Work to construct Kaplan Drive has been permitted and will begin in the coming weeks. Before actual construction work begins, additional tree protection enhancements will be put in place on the Kaplan Lawn site. This work will be contained on the site. All construction traffic will enter and exit on N. Pasteur.

 

The installation of the sanitary sewer on North Pasteur between Welch Rd and Blake Wilbur Drive will continue.

 

Work to install the New Stanford Hospital external mockups display is scheduled to continue next week. A concrete slab has been constructed on top of a small section of landscaping above PS-4 on Welch Rd at N. Pasteur to secure the life-size building samples. All work will be performed behind the construction fence.

 

What to expect next weekend (4/28-4/29) 

Hours of Construction Activity: 7 am - 3:30 pm

 

Installation of the sanitary sewer on North Pasteur up to Blake Wilbur Drive may continue next weekend.

 

Learn more about the New Stanford Hospital

Lucile Packard Children's Hospital Expansion (Make-Ready Site)

August 2011-October 2012

 

The Packard Children's Hospital expansion site prep (known as the 'Make-Ready' site) includes the demolition of 701 & 703 Welch and the construction of a shoring wall and utility tunnel in preparation for the Packard Children's expansion.

 

This week's activities:

 

What to expect this weekend (4/21-4/22)

Hours of Construction Activity: 7 am - 3:30 pm

 

Work will occur on Saturday, 4/21 to excavate the sewer line and storm drain and perform tie-ins by the temporary bridge on the Make-Ready site. No impacts to the hospital are anticipated. Excavation work will continue for the temporary tunnel; new drilling equipment will be brought on site. Dirt will continue to be off-hauled from the site.

 

Weekday work (4/23-4/27)

Hours of Construction Activity: 7 am - 5 pm

 

Foundation work will continue for the new utility tunnel. This work includes installing rebar, pouring concrete and drilling piles. Excavation of the new Make-Ready site will continue. Note: this work requires extra shifts on the Make-Ready site (see above hours of activity).

 

Work to remove and off haul the top layers of soil from the site will also continue, pending weather conditions. As excavation work occurs, please be mindful of additional hauling trucks entering the road. The retrofit the chilled water line in the tunnel will also continue next week.

 

Installation of shoring walls will continue on site.

 

Utility work continues near the Stanford Hospital & Clinics side of the Falk Building. Access to the Falk Building will be maintained at all times.

 

Access to the rear entrance of Packard Children's will remain open throughout construction.

 

What to expect next weekend (4/28-4/29)

Hours of Construction Activity: 7 am - 3:30 pm

 

Foundation work will continue for the new utility tunnel on Saturday 4/28. Shoring work will continue. Soil will be off-hauled from the site. 


For more information about the Packard Children's Hospital Expansion 

Hoover Pavilion Modernization 

August 2011-July 2013

 

Construction is underway to modernize and restore Hoover Pavilion, the original Palo Alto Hospital, in order to accommodate modern medicine and create a cohesive expansion to the Medical Center campus.


This week's activities:

 

What to expect this weekend (4/21-4/22)

Hours of Construction Activity: 7am - 5:30 pm

 

No work is scheduled to occur this weekend.

 

Weekday work (4/23-4/27)

Hours of Construction Activity: 7 am - 5:30 pm

 

Elevator shaft and stairwell work will continue.  Please note that this work will require the contractor to work 10-hr days and perform Saturday work for one more week (see above hours of activity).

 

Tree removal will occur on the Hoover site beginning Monday, 4/23. These trees will be transported off site in mid-May.

 

A crane will be on site on 4/23 and 4/30 to set the HVAC units on the roof.

 

Site mobilization for the new Hoover parking garage project will begin next week. This work includes the abatement of the auxiliary buildings on the site, followed by demolition.

 

Installation of overhead structural supports will continue; additional localized slab strengthening will occur as needed within the Pavilion; wall framing will continue on the upper floors.

 

Mechanical, electrical, plumbing and fire sprinkler line installation are in progress.

 

Restoration of the exterior concrete continues.

 

What to expect next weekend (4/28-4/29)

Hours of Construction Activity: 7 am - 5:30 pm

 

No work is scheduled to occur next weekend.

 

Learn more about the Hoover Pavilion modernization

General Reminders

 

Motorists: please be mindful of sharing the road with bicyclists. Cyclists who choose not to share the road and use the sidewalks must walk their bicycles.

 

Cyclists: please be mindful of sharing the sidewalk with pedestrians. Those who choose not to share the road and use the sidewalks must walk their bicycles.

 

Pedestrians must use the new designated crosswalks on Welch Road. Jaywalking is illegal and especially unsafe in active construction areas. Maps with new pedestrian crosswalks are available at www.SUMCRenewal.org. Thank you!

 