Project Renewal
Join Our List
Join Our Mailing List
Find out more

Find us on:
 
Find us on Facebook    Follow us on Twitter    View our videos on YouTube

April 27, 2012

 

Photo of the week

 

Installation of the exterior building materials display.
Installation of the exterior building materials display at Welch Rd. and Pasteur Dr.

This week, work began to install the exterior building samples display. 

 

The external building samples allow the design team to evaluate how these materials perform and respond as part of the campus landscape prior to beginning construction. 

 

These full size samples represent the actual colors, finishes and materials that will be used in the construction of the new facility. 

 

10 Day Look Ahead: Renewal Project Construction Activities

 

The Stanford University Medical Center Renewal Project, which will expand Lucile Packard Children's Hospital, rebuild Stanford Hospital, modernize Hoover Pavilion, and replace School of Medicine laboratories, is underway. Below is a summary of the Renewal Project's anticipated construction activities, hours of activity, and any affected lane or road closures over the next 10 days. Please click here to subscribe to our 10 day look aheads, which will be emailed every Friday and archived on the Renewal Project website.

 

Please note that that the scope of work and dates of work are subject to change without notice, especially due to weather impacts.

Welch Road Utility Project

August 2011-September 2013


One of the first steps in the effort to expand Packard Children's Hospital and rebuild Stanford Hospital includes utility work and surface improvements. The Welch Road Utility Project includes: replacing utility services and information technology infrastructure along Welch and Quarry Roads to serve the new hospital facilities once they are built; the widening of Welch Road; replacement of sidewalks, curbs and gutters; planting of new street trees and installation of planted medians and street lighting.


Note: Access to the Emergency Room will be maintained at all times.

 

This week's activities:


What to expect this weekend (4/28-4/29)

Hours of Construction Activity: 7am - 3:30 pm; night work on 4/29 beginning at 8 pm until 5 am on Monday 4/30.


Hot water line work behind the K-Rail in Quarry will continue on Saturday, 4/28. Chilled water line work in Welch will also continue, moving south.

 

On Sunday, 4/29, water utility work will begin near the AMC in Blake Wilbur Drive. This work will be performed at night and will require some traffic changes between 8 pm-5 am. Some noise is anticipated from saw-cutting, jack hammering and backhoe equipment. The Marguerite shuttle will maintain service to Blake Wilbur Drive. This work is anticipated to be completed in the next couple of weeks.

  

Weekday work (4/30-5/4)

Hours of Construction Activity: 7am - 3:30 pm

 

Welch Rd is now a one-lane, one-way road going West from Quarry to Pasteur Drive. This change will be in effect for two years. We thank you for your patience regarding this significant change and ask that you please adjust your driving route accordingly. South Pasteur Drive is now a two-way two-lane road. North Pasteur Drive is closed between Blake Wilbur Drive and Sand Hill Road. 

K-Rail will remain in place on the inboard side of Quarry Rd (between Welch and continuing up to the Quarry Extension near the turn to the Emergency Department) in order to facilitate ongoing utility work. This reduces Quarry to a two lane, two direction road during this time. Access will be maintained to the Emergency Department at all times.

 

Work will continue to install a new hot water line on Quarry Road. A portion of this work will continue to take place outside of the K-Rail in the Quarry Extension. Access to the Emergency Department will be maintained at all times.

 

Work to install new power line on Quarry Road will also continue.

 

Work on the chilled water line and the new power lines will continue on Welch Rd, moving south. This work will occur near the driveway entrance to 801 Welch next week. Access in and out of the entrance to 801 Welch will be maintained at all times via flagmen and signage. The existing gas main will be exposed in front of 777 Welch. Access in and out of 777 Welch will be maintained at all times. Flaggers will be onsite to assist with traffic flow if needed.

 

Please be cautious of construction trucks entering the road. Access to the Emergency Room will be maintained at all times.

 

Night Work (4/30-5/4)

Hours of Construction Activity: 8 pm-5 am

 

Water utility work will continue near the AMC in Blake Wilbur Drive. This work will be performed at night and will require some traffic changes between 8 pm-5 am. Some noise is anticipated from saw-cutting, jack hammering and backhoe equipment. The Marguerite shuttle will maintain service to Blake Wilbur Drive. This work is anticipated to be completed in the next couple of weeks.

 

What to expect next weekend (5/5-5/6) 

Hours of Construction Activity: 8am - 5 pm; night work on 5/6 beginning at 8 pm until 5 am on Monday 5/7.

 

Utility work may occur on Quarry and Welch Roads, pending weather conditions. Dirt may be off hauled from the site.

 

Water utility work will continue near the AMC in Blake Wilbur Drive. This work will be performed at night and will require some traffic changes between 8 pm-5 am. Some noise is anticipated from saw-cutting, jack hammering and backhoe equipment. The Marguerite shuttle will maintain service to Blake Wilbur Drive. This work is anticipated to be completed in the next couple of weeks. 

 

Learn more about the Welch Road Utility Project

 

New Stanford Hospital Facility (Make-Ready Site)

March 2012-March 2013

 

The New Stanford Hospital facility site prep (known as the 'Make-Ready' site) includes surface demolition and utility work on North Pasteur Drive, and the demolition of Parking Structure 3 and 1101 Welch in order to make way for the new hospital facilities. 

 

This week's activities:

 

What to expect this weekend (4/28-4/29)

Hours of Construction Activity: 7 am - 3:30 pm

 

No work is scheduled to occur this weekend.

 

Weekday work (4/30-5/4) 

Hours of Construction Activity: 7 am - 3:30 pm

 

Work to construct Kaplan Drive has been permitted and will begin in the coming weeks. Before actual construction work begins, additional tree protection enhancements will be put in place on the Kaplan Lawn site. This work will be contained on the site. All construction traffic will enter and exit on N. Pasteur.

 

The installation of the sanitary sewer on North Pasteur is complete up to Blake Wilbur Drive.

 

Work to install the New Stanford Hospital external mockups display is scheduled to continue next week. A concrete slab has been constructed on top of a small section of landscaping above PS-4 on Welch Rd at N. Pasteur to secure the life-size building samples. All work will be performed behind the construction fence.

 

What to expect next weekend (5/5-5/6) 

Hours of Construction Activity: 7 am - 3:30 pm

 

No work is currently scheduled next weekend.

 

Learn more about the New Stanford Hospital

Lucile Packard Children's Hospital Expansion (Make-Ready Site)

August 2011-October 2012

 

The Packard Children's Hospital expansion site prep (known as the 'Make-Ready' site) includes the demolition of 701 & 703 Welch and the construction of a shoring wall and utility tunnel in preparation for the Packard Children's expansion.

 

This week's activities:

 

What to expect this weekend (4/27-4/29) 

Hours of Construction Activity: 7 am - 3:30 pm

 

Work will begin at midnight on Friday, 4/27, to install a temporary sewer line. This work will be completed at 4 am on Saturday, 4/28.  No impacts to the hospital are anticipated.

 

Utility work will also continue over the weekend. Off-hauling of dirt may also occur.

 

Weekday work (4/30-5/4)
Hours of Construction Activity: 7 am - 5 pm

 

The current phase of shoring work is complete and will not resume until the contractors resume excavation. Foundation work will continue for the new utility tunnel. This work requires extra shifts until 8/7 (see above work hours).

 

The retrofit the chilled water line in the tunnel will also continue next week.

 

Utility work will continue near the Stanford Hospital & Clinics side of the Falk Building. Access to the Falk Building will be maintained at all times.

 

The steel bridge near the Day Hospital and Imaging will be installed on Wednesday, 5/2. This work may cause some noise and vibration. This work is being coordinated directly with Imaging in order to minimize impacts. The bridge is anticipated to take two weeks to install.

 

Access to the rear entrance of Packard Children's will remain open throughout construction.

 

What to expect next weekend (5/5-5/6)
Hours of Construction Activity: 7 am - 3:30 pm

 

On Saturday, 5/5, a Stanford Hospital & Clinics Emergency power cut-over will occur from 8am - 10pm. This work is associated with the Packard Children's Make-Ready project and includes: replacing the emergency power electrical feeders from the power substation to the Phase 1 building switchgear; connecting new conductors to new switchgear; and re-routing connections to the emergency branch of new switchgear. This emergency power cut-over should have no major impacts to operations of either hospital.

 

Foundation work will continue for the new utility tunnel on Saturday, 5/5. Off-hauling of dirt may also occur.

 

For more information about the Packard Children's Hospital Expansion 

Hoover Pavilion Modernization 

August 2011-July 2013

 

Construction is underway to modernize and restore Hoover Pavilion, the original Palo Alto Hospital, in order to accommodate modern medicine and create a cohesive expansion to the Medical Center campus.


This week's activities:

 

What to expect this weekend (4/28-4/29)

Hours of Activity: 7am - 3:30 pm

 

Hazmat abatement will occur within the auxiliary buildings on the Hoover Pavilion site on Saturday, 4/28.

 

Weekday work (4/30-5/4)

Hours of Construction Activity: 7 am - 3:30 pm

 

Work will continue on the elevator and stairwell inside the Pavilion. Work on the hydraulic elevator has begun.

 

The boxing and storing of trees on the Hoover Pavilion site will continue. These trees will be transported off site in mid-May.

 

A crane will be on site on 4/30 to set the HVAC units on the roof.

 

Site mobilization for the new Hoover parking garage will continue. This work includes the abatement of the auxiliary buildings on the site, followed by demolition. Storm drain installation is also under way.

 

Drywall installation on the first and second floors will continue. Demolition of the tower tile roof will begin next week. The restoration of the exterior fa´┐Żade is ongoing; additional localized slab strengthening is occurring as needed within the Pavilion; installation of overhead structural supports will continue; wall framing will continue on the upper floors.

 

Mechanical, electrical, plumbing and fire sprinkler line installation are in progress.

 

What to expect next weekend (5/5-5/6) 

Hours of Construction Activity: 7 am - 5:30 pm

 

No work is scheduled to occur next weekend.

 

Learn more about the Hoover Pavilion modernization

General Reminders

 

Motorists: please be mindful of sharing the road with bicyclists. Cyclists who choose not to share the road and use the sidewalks must walk their bicycles.

 

Cyclists: please be mindful of sharing the sidewalk with pedestrians. Those who choose not to share the road and use the sidewalks must walk their bicycles.

 

Pedestrians must use the new designated crosswalks on Welch Road. Jaywalking is illegal and especially unsafe in active construction areas. Maps with new pedestrian crosswalks are available at www.SUMCRenewal.org. Thank you!

 

Questions?

  

You can find the most up to date information on the Renewal Project website at www.SUMCRenewal.org

 

You can also sign up for project email notices on the website. For additional information regarding site work, email the Renewal Project at info@sumcrenewal.org or call the 24-hour Construction Hotline: (650) 701-SUMC (7862).

 

Logos