Project Renewal
Join Our List
Join Our Mailing List
Find out more

Find us on:
 
Find us on Facebook    Follow us on Twitter    View our videos on YouTube

May 18, 2012

 

Photo of the week

 

Making Way for New Hoover Pavilion Parking Structure

 

Hoover Pavilion

Construction crews work to prepare the site of the new parking garage at Hoover Pavilion. Demolition of the auxiliary buildings is complete and shoring work for the new parking garage is scheduled to begin next week.

 

10 Day Look Ahead: Renewal Project Construction Activities

 

The Stanford University Medical Center Renewal Project, which will expand Lucile Packard Children's Hospital, rebuild Stanford Hospital, modernize Hoover Pavilion, and replace School of Medicine laboratories, is underway. Below is a summary of the Renewal Project's anticipated construction activities, hours of activity, and any affected lane or road closures over the next 10 days. Please click here to subscribe to our 10 day look aheads, which will be emailed every Friday and archived on the Renewal Project website.

 

Please note that that the scope of work and dates of work are subject to change without notice, especially due to weather impacts.

Welch Road Utility Project

August 2011-September 2013


One of the first steps in the effort to expand Packard Children's Hospital and rebuild Stanford Hospital includes utility work and surface improvements. The Welch Road Utility Project includes: replacing utility services and information technology infrastructure along Welch and Quarry Roads to serve the new hospital facilities once they are built; the widening of Welch Road; replacement of sidewalks, curbs and gutters; planting of new street trees and installation of planted medians and street lighting.


Note: Access to the Emergency Room will be maintained at all times.

 

This week's activities:

 

What to expect this weekend (5/19-5/20)
Hours of Construction Activity: 7am - 3:30 pm; night work on 5/20 beginning at 8 pm until 5 am on Monday 5/21.

 

Work will occur on Saturday, 5/19 on the south side of the Blake Wilbur walkway near 1101 Welch Road to prepare for the future Ambulance Drive. No egress will be affected at this time.


The City of Palo Alto will be also on site on Saturday at 7 am to perform a gas line connection in front of 777 Welch in the public right of way. This work will not require a shutdown. Access in and out of the building will be maintained at all times.

 

On Sunday, 5/20, water utility work will continue near the AMC in Blake Wilbur Drive. This work will be performed at night and will require some traffic changes between 8 pm-5 am. Some noise is anticipated from saw-cutting, jack hammering and backhoe equipment. The Marguerite shuttle will maintain service to Blake Wilbur Drive. This work is anticipated to be completed in the next couple of weeks.

 

Weekday work (5/21-5/25)

Hours of Construction Activity: 7am - 3:30 pm

 

Welch Rd is now a one-lane, one-way road going West from Quarry to Pasteur Drive. This change will be in effect for two years. We thank you for your patience regarding this significant change and ask that you please adjust your driving route accordingly. South Pasteur Drive is now a two-way two-lane road. North Pasteur Drive is closed between Blake Wilbur Drive and Sand Hill Road.   


K-Rail will remain in place on the inboard side of Quarry Rd (between Welch and continuing up to the Quarry Extension near the turn to the Emergency Department) in order to facilitate ongoing utility work. This reduces Quarry to a two lane, two direction road during this time. Access will be maintained to the Emergency Department at all times.

 

Work will continue to install a new hot water line on Quarry Road. A portion of this work will continue to take place outside of the K-Rail in the Quarry Extension. Access to the Emergency Department will be maintained at all times.

 

The City of Palo Alto will be onsite to continue pre-switchover electrical work on Welch Road. This work should not impact neighboring properties or the hospitals. The first switchover is scheduled to occur on Thursday, 5/24 in Parking Structure 4. This switchover will also affect the traffic lights at the intersection of Welch and S. Pasteur Drive. Traffic guards will be in place as needed to support this switchover.

 

Work on the chilled water line will continue on Welch Rd, moving south.

 

Work to prepare for the replanting of eight trees will occur in the Blake Wilbur lot. Prep work to dig holes for the trees will begin next week. The actual trees will be transported the following week during nighttime hours.

 

Please be cautious of construction trucks entering the road. Access to the Emergency Room will be maintained at all times.

 

Night Work (5/21-5/25)
Hours of Construction Activity: 8 pm- 5 am

 

Water utility work will continue near the AMC in Blake Wilbur Drive. This work will be performed at night and will require some traffic changes between 8 pm-5 am. Some noise is anticipated from saw-cutting, jack hammering and backhoe equipment. The Marguerite shuttle will maintain service to Blake Wilbur Drive. This work is anticipated to be completed in the next couple of weeks.

 

What to expect next weekend (5/26-5/27)
Hours of Construction Activity: 8 am - 5 pm

 

No work is scheduled to occur next weekend or on Memorial Day, Monday, 5/28.

 

Learn more about the Welch Road Utility Project

 

Non-Renewal Related News

 

Oak Road will remain closed through Friday 5/25/12 due to School of Medicine construction activity. Parking Structure 5 will remain open during this time.

New Stanford Hospital Facility (Make-Ready Site)

March 2012-March 2013

 

The New Stanford Hospital facility site prep (known as the 'Make-Ready' site) includes surface demolition and utility work on North Pasteur Drive, and the demolition of Parking Structure 3 and 1101 Welch in order to make way for the new hospital facilities. 

 

This week's activities:

 

What to expect this weekend (5/19-5/20)
Hours of Construction Activity: 7 am - 4 pm

 

Staking work and tree protection measures may occur in Kaplan Lawn; striping for the new bus stop on Blake Wilbur Drive will occur; work in PS-4 will also continue over the weekend.

 

Weekday work (5/21-5/25)

Hours of Construction Activity: 7 am - 4 pm

 

Contractors will begin to mobilize on the Kaplan Lawn site in order to begin work on Kaplan Drive, the driveway entrance to the New Stanford Hospital facility. This work will take 10 weeks to complete and will be completely contained within the fenced site.

 

Construction work to reconfigure Parking Structure 4 to support future parking changes as part of the New Stanford Hospital will continue. This work includes curb demolition, electrical work and restriping inside the underground parking structure. The permit parking garage will remain open but some parking spaces will be impacted during this time.

 

Work to install the New Stanford Hospital external mockups display is scheduled to continue next week. A concrete slab has been constructed on top of a small section of landscaping above PS-4 on Welch Rd at N. Pasteur to secure the life-size building samples. All work will be performed behind the construction fence.

 

Night work (5/21-5/25) 

Hours of Construction Activity: 7 pm-3 am

 

Curb demolition work will occur at night in PS-4, the underground permit parking structure. Some noise producing activities may occur during this effort. No impact is anticipated to the hospitals.

 

What to expect next weekend (5/26-5/27)

Hours of Construction Activity: 7 am - 4 pm

 

Possible PS-4 construction work and Make-Ready work may occur on Saturday, 5/26. No work is scheduled to occur on Sunday or on Monday, 5/28 (Memorial Day).

  

Learn more about the New Stanford Hospital

Lucile Packard Children's Hospital Expansion (Make-Ready Site)

August 2011-October 2012

 

The Packard Children's Hospital expansion site prep (known as the 'Make-Ready' site) includes the demolition of 701 & 703 Welch and the construction of a shoring wall and utility tunnel in preparation for the Packard Children's expansion.

 

This week's activities:

 

What to expect this weekend (5/19-5/20)
Hours of Construction Activity: 7 am - 3:30 pm

 

The second electrical shutdown at Stanford Hospital & Clinics in relation to the Make-Ready project will occur on 5/19. No impacts to either hospital are anticipated.

 

The steel bridge installation will continue near the Day Hospital and Imaging. Utility work will also continue near the Stanford Hospital & Clinics side of the Falk Building. Access to the Falk Building will be maintained at all times.

 

Weekday work (5/21-5/25) 
Hours of Construction Activity: 7 am - 5 pm

 

Foundation work will continue for the new utility tunnel. This work requires extra shifts until 8/7 (see above work hours).

 

The retrofit the chilled water line in the tunnel will also continue next week.

 

Utility work continues near the Stanford Hospital & Clinics side of the Falk Building. Access to the Falk Building will be maintained at all times.

 

The steel bridge installation near the Day Hospital and Imaging will continue. This work may cause some noise and vibration. This work is being coordinated directly with Imaging in order to minimize impacts. The bridge is anticipated to be complete next week, after which time a door flip will occur.

 

Access to the rear entrance of Packard Children's will remain open throughout construction.

 

What to expect next weekend (5/26-5/27)

Hours of Construction Activity: 7 am - 3:30 pm

 

Foundation work will continue for the new utility tunnel on Saturday, 5/26. No work is anticipated for Sunday (5/27) or Monday (5/28) due to the Memorial Day holiday.

 

For more information about the Packard Children's Hospital Expansion 

Hoover Pavilion Modernization 

August 2011-July 2013

 

Construction is underway to modernize and restore Hoover Pavilion, the original Palo Alto Hospital, in order to accommodate modern medicine and create a cohesive expansion to the Medical Center campus.


This week's activities:

 

What to expect this weekend (5/19-5/20)

Hours of Construction Activity: 7am - 4 pm

 

Work will occur over the weekend to box and store trees on the Hoover Pavilion site.

 

Weekday work (5/21-5/25)

Hours of Construction Activity: 7 am - 4 pm

 

Interior improvements continue (wall framing, sheet rock) throughout the floors of the Pavilion. Work will continue on the hydraulic elevator. The overhead plumbing and fire sprinkler lines are nearly complete on the upper floors; restoration of the exterior concrete continues.

 

The installation of the metal screen that covers the mechanical equipment is in progress on the roof. Work to box, store and transport trees on the Hoover site will continue. These trees are being transported off the site to the tree farm across Palo Road.

 

Demolition of the auxiliary buildings is complete. Site utility construction for the new parking garage is ongoing; shoring work for the new parking garage is scheduled to begin next week.

 

What to expect next weekend (5/26-5/27)

Hours of Construction Activity: 7 am - 4 pm

 

No work is scheduled to occur next weekend or on Monday, 5/28 due to the Memorial Day holiday.

 

Learn more about the Hoover Pavilion modernization

General Reminders

 

Motorists: please be mindful of sharing the road with bicyclists. Cyclists who choose not to share the road and use the sidewalks must walk their bicycles.

 

Consider alternatives to driving, including Stanford's free Marguerite shuttle, biking, carpooling, and transit. Try the do-it-yourself commute planning tool.

 

Cyclists: please be mindful of sharing the sidewalk with pedestrians. Those who choose not to share the road and use the sidewalks must walk their bicycles.

 

Pedestrians must use the new designated crosswalks on Welch Road. Jaywalking is illegal and especially unsafe in active construction areas. Maps with new pedestrian crosswalks are available at www.SUMCRenewal.org. Thank you!

 

Questions?

  

You can find the most up to date information on the Renewal Project website at www.SUMCRenewal.org

 

You can also sign up for project email notices on the website. For additional information regarding site work, email the Renewal Project at info@sumcrenewal.org or call the 24-hour Construction Hotline: (650) 701-SUMC (7862).

 

Logos