June 8, 2012

 

Photo of the week

Hoover Pavilion
Looking towards Hoover Pavilion from the site of the new parking garage.

10 Day Look Ahead: Renewal Project Construction Activities

 

The Stanford University Medical Center Renewal Project, which will expand Lucile Packard Children's Hospital, rebuild Stanford Hospital, modernize Hoover Pavilion, and replace School of Medicine laboratories, is underway. Below is a summary of the Renewal Project's anticipated construction activities, hours of activity, and any affected lane or road closures over the next 10 days. Please click here to subscribe to our 10 day look aheads, which will be emailed every Friday and archived on the Renewal Project website.

 

Please note that that the scope of work and dates of work are subject to change without notice, especially due to weather impacts.

Welch Road Utility Project

August 2011-September 2013


One of the first steps in the effort to expand Packard Children's Hospital and rebuild Stanford Hospital includes utility work and surface improvements. The Welch Road Utility Project includes: replacing utility services and information technology infrastructure along Welch and Quarry Roads to serve the new hospital facilities once they are built; the widening of Welch Road; replacement of sidewalks, curbs and gutters; planting of new street trees and installation of planted medians and street lighting.


Note: Access to the Emergency Room will be maintained at all times.

 

What to expect this weekend (6/8-6/10)
Hours of Construction Activity: 7am - 3:30 pm; night work will occur on Friday and Saturday night from 4 pm-2 am.

 

Work to install a new hot water line and new communications lines will continue on Quarry Rd.

 

Temporary power poles will continue to be installed on Friday and Saturday night from 800-700 Welch Rd in order to support future utility switchovers.

 

Weekday work (6/4-6/8)
Hours of Construction Activity: 7am - 5:30 pm

 

Welch Rd is now a one-lane, one-way road going West from Quarry to Pasteur Drive. This change will be in effect for two years. We thank you for your patience regarding this significant change and ask that you please adjust your driving route accordingly. South Pasteur Drive is now a two-way two-lane road. North Pasteur Drive is closed between Blake Wilbur Drive and Sand Hill Road.
 

K-Rail will remain in place on the inboard side of Quarry Rd (between Welch and continuing up to the Quarry Extension near the turn to the Emergency Department) in order to facilitate ongoing utility work. This reduces Quarry to a two lane, two direction road during this time. Access will be maintained to the Emergency Department at all times.
 

On Tuesday, 6/12, work will begin to construct a new road near the Blake Wilbur Clinic and 1101 Welch Road. This road will ultimately serve ambulances from Welch Road into the New Stanford Hospital facility. Pedestrian detour signage will be in place on Blake Wilbur Drive. Access to the clinics will be maintained at all times.

 

Early next week, trees may be transported from the Hoover tree farm to the Blake Wilbur lot. This transport will occur in the evening hours.

 

Work will continue to install a new hot water line on Quarry Road. A portion of this work will continue to take place outside of the K-Rail in the Quarry Extension. Access to the Emergency Department will be maintained at all times.

 

The City of Palo Alto will begin work to activate the new power poles on Welch Rd in order to support future utility switchovers.

 

Please be cautious of construction trucks entering the road. Access to the Emergency Room will be maintained at all times.

 

What to expect next weekend (6/16-6/17)

Hours of Construction Activity: 8am - 5 pm

 

On Saturday, 6/16 the City of Palo Alto is currently scheduled to perform electrical switchovers at Blake Wilbur Clinic and 1000 Welch Road from 7 am until 5 pm. These switchovers are being coordinated directly with the properties.

 

Hot water line work will also continue on Quarry Rd. 

 

New Stanford Hospital Facility (Make-Ready Site)

March 2012-March 2013

 

The New Stanford Hospital facility site prep (known as the 'Make-Ready' site) includes surface demolition and utility work on North Pasteur Drive, and the demolition of Parking Structure 3 and 1101 Welch in order to make way for the new hospital facilities. 

 

This week's activities:

 

What to expect this weekend (6/9-6/10)

Hours of Construction Activity: 7 am - 4 pm

 

No work is currently scheduled.

 

Weekday work (6/11-6/15)

Hours of Construction Activity: 7 am - 4 pm

 

Construction will continue on the Kaplan Lawn site in order to build Kaplan Drive, the driveway entrance to the New Stanford Hospital facility. All work will be completely contained within the fenced site.

 

Construction work to reconfigure Parking Structure 4 to support future parking changes as part of the New Stanford Hospital will continue next week. This work includes curb demolition, electrical work and restriping inside the underground parking structure. The permit parking garage will remain open but some parking spaces will be impacted during this time.

 

Night work (6/11-6/15)

Hours of Construction Activity: 7 pm-3 am

 

Curb demolition work will occur at night in PS-4, the underground permit parking structure. Some noise producing activities may occur during this effort. No impact is anticipated to the hospitals.

 

What to expect next weekend (6/16-6/17)

Hours of Construction Activity: 7 am - 4 pm

 

Possible PS-4 construction work and Make-Ready work may occur on Saturday, 6/17.

Lucile Packard Children's Hospital Expansion (Make-Ready Site)

August 2011-October 2012

 

The Packard Children's Hospital expansion site prep (known as the 'Make-Ready' site) includes the demolition of 701 & 703 Welch and the construction of a shoring wall and utility tunnel in preparation for the Packard Children's expansion.

 

This week's activities:

 

What to expect this weekend (6/9-6/10)

Hours of Construction Activity: 7 am - 3:30 pm

 

Foundation work for the utility tunnel and work on the electrical duct bank will continue on Saturday, 6/9. Dirt will also be off-hauled from the Make-Ready site.

 

Access to the Falk Building will be maintained at all times via the Stanford Hospital side of the building. Please follow the pedestrian detour signage.

 

Weekday work (6/11-6/15)

Hours of Construction Activity: 7 am - 7 pm

 

Foundation work will continue for the new utility tunnel. This work requires extra shifts until 8/7 (see above work hours).

 

The retrofit of the chilled water line in the tunnel will also continue next week.

 

Utility work continues near the Stanford Hospital & Clinics side of the Falk Building. Access to the Falk Building will be maintained at all times via the Stanford Hospital side of the building. Pedestrian detour signage is in place.

 

Work to construct a new electrical duct bank will continue in order to support the Packard Children's Hospital electrical shutdown on 6/16.

 

Access to the rear entrance of Packard Children's will remain open throughout construction.

 

What to expect next weekend (6/16-6/17)

Hours of Construction Activity: 7 am - 3:30 pm

 

At 6 am on Saturday, 6/16, a scheduled power cut-over will occur at Lucile Packard Children's Hospital. This power cut-over should have no major impact to operations of either hospital.

 

Foundation work for the utility tunnel and electrical duct bank work will continue next Saturday. Dirt may be off-hauled from the Make-Ready site. 

Hoover Pavilion Modernization 

August 2011-July 2013

 

Construction is underway to modernize and restore Hoover Pavilion, the original Palo Alto Hospital, in order to accommodate modern medicine and create a cohesive expansion to the Medical Center campus.


This week's activities:

 

What to expect this weekend (6/9-6/10)

Hours of Construction Activity: 7am - 4 pm

 

Work may occur on the Pavilion site on Saturday, 6/9.

 

Weekday work (6/11-6/15)

Hours of Construction Activity: 7 am - 4 pm

 

Interior improvements continue throughout the floors of the Pavilion. Restoration of the exterior concrete will also continue.

 

The installation of the metal screen that covers the mechanical equipment is in progress on the roof. Work to box, store and transport trees on the Hoover site will be completed early next week. These trees are being transported off the site to the tree farm across Palo Road in the evening hours.

 

Site utility construction for the new parking garage is ongoing. Shoring work for the new parking garage is also under way; excavation is scheduled to begin next week. The removal of existing underground storage tanks will be completed next week.

 

What to expect next weekend (6/16-6/17)

Hours of Construction Activity: 7 am - 4 pm

 

No work is scheduled to occur next weekend.

 

General Reminders

 

Motorists: please be mindful of sharing the road with bicyclists. Cyclists who choose not to share the road and use the sidewalks must walk their bicycles.

 

Consider alternatives to driving, including Stanford's free Marguerite shuttle, biking, carpooling, and transit. Try the do-it-yourself commute planning tool.

 

Cyclists: please be mindful of sharing the sidewalk with pedestrians. Those who choose not to share the road and use the sidewalks must walk their bicycles.

 

Pedestrians must use the new designated crosswalks on Welch Road. Jaywalking is illegal and especially unsafe in active construction areas. Maps with new pedestrian crosswalks are available at www.SUMCRenewal.org. Thank you!

 

Questions?

  

You can find the most up to date information on the Renewal Project website at www.SUMCRenewal.org

 

You can also sign up for project email notices on the website. For additional information regarding site work, email the Renewal Project at info@sumcrenewal.org or call the 24-hour Construction Hotline: (650) 701-SUMC (7862).

 

Logos