SEGMENT 2 UPDATE

NORTHBOUND AND SOUTHBOUND SR-261 FULL ROAD CLOSURES AT I-5 BRIDGE

Nighttime construction activities and closures are scheduled to start tonight for the demolition of the outer portions of I-5 at SR-261.


Anticipated Schedule

  • Northbound SR-261:
  • Week of June 22
  • Monday night, June 22 through Wednesday night, June 24.
  • Southbound SR-261:
  • Week of June 29
  • Monday night, June 29 through Wednesday night, July 1.


There will be no work or closures on Friday, July 3 in observance of the Fourth of July holiday.


Anticipated Work Hours

Daytime Hours: As early as 7 a.m. to 4 p.m.

Nighttime Hours: As early as 10 p.m. to 5 a.m.


Closures

This work will require full road closures of northbound (NB) and southbound (SB) SR-261 in addition to outside lane closures on I-5. Please note, crews will first close the NB side of SR-261 to complete bridge work. Upon completion, crews will shift activities to SB SR-261 and close that direction to complete work on the other side of the bridge. Inside lanes of I-5 will remain open.


Please check the Google Map below for additional closure and detour information.

Image uses green arrows to outline an approved detour route for full road closures along SR-261 at I-5
Image uses green arrows to outline an approved detour route for full road closures along SR-261 at I-5

*This work may be loud and ongoing. The schedule is subject to change due to inclement weather or unforeseen operational issues.


*Freeway and street lane closures will occur regularly throughout the duration of the project's construction. See closure section below for more information.

Google Map

A clickable preview of the I-5 Improvement Project area on Google Maps. Click this image to view the interactive map on Google Maps.

Bookmark the closures and detours map above for quick access to real-time construction information. Click on the construction icons to view activities and closure and detour information. Plan for additional travel time through the area. Detour signs will be in place to assist motorists.

""

Stay Connected

 

We invite you to sign up for project updates so you’ll be the first to know about upcoming construction activities, traffic changes, and community meetings and when we’ll be out in your community at local events - we hope you’ll stop by and say hello!



This screenshot outlines the I-5 Improvement website where constituents can sign up to receive Project Updates.
 

About the Project

Project Map

A horizontal map of the I-5 Improvement Project in Irvine and Tustin. Click the map to view it as a PDF.

Click to view a larger map

Click to view vertical map on a mobile device

A chart displays the Construction Schedule. Segment 1 is anticipated to be complete in late 2029. Segment 2 is anticipated to be complete in mid-2030. The schedule is subject to change.

For more information, view the Project Website and Fact Sheet:

" "
 
An illustration reads "Follow us on socials!" next to a cell phone on top of an orange background.

STAY CONNECTED

Facebook    X    Instagram    Web

i5Project405to55@octa.net

(888) 209-5550

octa.net/I-5Project

 
A footer image displays OCTA, Caltrans, US Department of Transportation and Building CA logos in a horizontal row..