September 2023 Newsletter

Dear Neighbor,


Over the years, I have highlighted many infrastructure improvements in District 2; that list continues to grow and I am delighted to report on even more positive developments in our district regarding stormwater improvements, seawall replacement and other infrastructure that will be very beneficial for our District 2 neighborhoods in FY2024. 



Major Infrastructure Project Updates in District 2

 


Southeast Isles Seawall Replacement Project


Construction is now underway along the south side of Las Olas Boulevard between Coconut Isle Drive and Royal Plaza Drive where four seawalls are being replaced and new stormwater infrastructure is being installed. The new seawalls will be constructed using corrosion-resistant steel sheet-piles with a concrete cap and will be elevated to 5 feet NAVD in accordance with the City’s seawall ordinance. Nearby stormwater infrastructure, including pipes, catch basins, and tidal valves will be improved to ensure proper drainage near the seawalls. The first seawall to be replaced is between Coconut Isle Drive and Lido Drive and crews will continue to move east along Las Olas Boulevard. This work in the Las Olas Isles neighborhood represents a nearly $3 million investment in our infrastructure that will help reduce tidal flooding, making us better prepared for future king tides and sea level rise. Crews began mobilizing earlier this month and completion is expected in Summer 2024.

 

Infrastructure Improvements for Sailboat Bend


The City has two projects planned for the upcoming year within Sailboat Bend. Within the next 1 to 1.5 months, construction will begin on a $247,000 stormwater improvement project near 1540 Argyle Drive to install five new catch basins and other improvements to drain rainwater from the roadway into the North Fork of the New River. The City also approved $578,279 in its fiscal year 2024 budget for project P12818, Sailboat Bend Stormwater Improvements, which will be used to initiate planning and design for a neighborhood-wide stormwater project. This effort will be part of the second Tranche of the Stormwater Master Plan improvements program.


Federal Funding for Cooley’s Landing in Sailboat Bend


On September 14th, we were given an update from Congressman Jared Moskowitz that the National Park Service has committed $1.1 million to renovate Cooley's Landing. We are undertaking seawall improvements, repairing waterfront access pathways and improving picnic facilities and restrooms. We also are adding new landscaping, lighting and benches.


The improvements at Cooley’s Landing will also be receiving $1.5 million in grants from FIND (Florida Inland Navigation District) and $600,000 from BBIP (Broward Boating Improvement Program) in addition to $1.1 million in Park Bond funding . These funds will help modernize the marina to improve boating and water access. The City Commission will officially accept these grants at an upcoming Commission meeting. This project is currently in the design phase and we will keep you updated regarding timelines, design concepts and much more!



Merle Fogg Seawall replacement Project in Idlewyld


I am so pleased about this next update. The Merle Fogg Seawall replacement project is finally underway. In January, the Commission approved an agreement for Merle Fogg Park Seawall Replacement in the amount of $1,022,459 with Ebsary Foundation Co. This seawall was included in the Seawall Master Plan several years out; however, I advocated for moving the timetable earlier, and a new 130 linear foot proposed seawall will be built to replace the collapsed seawall and will also be constructed to an elevation of five feet NAVD in accordance with the City’s seawall ordinance providing greater protection against future sea level rise. Additional improvements include storm inlet installation, landscaping restoration, and check valve installation. Construction has commenced and is expected to be completed in early 2024. 

 

$13.5 Million Grant for a Progresso Village Project.


In August, the City Commission approved a resolution that authorizes the City Manager to execute a reimbursable grant agreement with the Florida Department of Environmental Protection in the amount of $13.5 million. The funds will be used for District 2's Progresso Neighborhood Stormwater Improvements Project, which includes the replacement of aging, undersized, and fragmented stormwater management infrastructure as well as construction of new infrastructure. These improvements will reduce the frequency, intensity, and duration of flooding in the neighborhood and reduce the risk of flooding during heavy rain events.

 

Stormwater Drainage in Middle River Terrace


The city will soon be starting two exciting projects to improve Middle River Terrace’s stormwater system. First, the city received a $23 million FEMA grant to restore the stormwater drains in eight neighborhoods -- including Middle River Terrace! They will be unclogging drains and cleaning out the silt in a massive project to restore the stormwater drainage system. Second, the proposed city budget includes $480,702 to upgrade the stormwater drainage system on Holly Heights Drive and adjacent streets east of Middle River Terrace Park.  

 

NE 4th Ave. between Sunrise Blvd. and NE 13th Street Intersection Traffic Improvement in South Middle River/Middle River Terrace

 

The City of Fort Lauderdale will begin improvements on NE 4th Avenue, between Sunrise Blvd and NE 13th Street to enhance traffic safety for our neighbors. This project includes widening sidewalks, landscaping, irrigation systems, decorative pavement treatments, addition of a district sign, and infrastructure improvements. Construction is set to begin next week and be completed by mid-September 2024. I want to thank staff who, at my request, scheduled additional meetings with the Middle River Terrace Neighborhood Association and the South Middle River Civic Association before we approved this construction agreement.

 


Execution of the Water and Infrastructure Finance and Innovation Act (WIFIA) Loan Agreement with the United States Environmental Protection Agency (EPA) for Stormwater Improvement Projects in Seven City Neighborhoods including District 2’s Progresso Village, Victoria Park, and Southeast Isles


On September 19th, Staff recommended that the City Commission adopt a Resolution approving and authorizing the execution of the Water and Infrastructure Finance and Innovation Act (WIFIA) Loan Agreement with the United States Environmental Protection Agency (EPA) to finance a portion of the cost of construction of stormwater improvements in seven (7) City neighborhoods: River Oaks, Dorsey Riverbend, Durrs, Progresso Village, Victoria Park, Melrose Manors, and Southeast Isles.


Back on April 19, 2016, the City initiated the Stormwater Master Plan Modeling and Design Implementation Program, designed to resolve chronic flooding in seven (7) neighborhoods including District 2’s Progresso Village, Victoria Park, and Southeast Isles. The seven targeted neighborhoods suffer major flooding due to rainfall and/or high tides. The existing stormwater infrastructure in these areas is either nonexistent, undersized or in excess of fifty (50) years old, which is well beyond its operational lifespan.

Several of the neighborhoods were impacted by the flash flooding that occurred on April 12, 2023, further highlighting the necessity of stormwater improvements. The proposed stormwater improvements will install all new infrastructure to address the water quality and quantity needs of these areas. The improvements will minimize recurring flooding incidents/severity and promote an adaptable and resilient coastal community for the future.


Total construction costs are estimated at $244,885,772, of which up to $119,994,028 (49%) (the “WIFIA Loan”) can be financed through the WIFIA program. The WIFIA program accelerates investment in our nation’s water infrastructure by providing long-term, low-cost supplemental loans for regionally and nationally significant projects. The City submitted a letter of interest to the EPA and was one (1) of fifty-five (55) municipalities nationally that received an invitation to submit a WIFIA application. On June 6, 2023, the City Commission adopted Resolution No. 23-112, authorizing the issuance of Stormwater Utility System Special Assessment Revenue Bonds, Series 2023A, in an amount not to exceed $210,000,000 (CAM #23-0116). As a result of the WIFIA Loan, the principal amount of the Series 2023A Bonds issued by the City was reduced to $88,485,000.

 

Isle of Venice Stormwater Improvement Project



In July, the City of Fort Lauderdale worked with Southern Underground Industries, Inc. to make improvements to the stormwater system at 40 Isle of Venice Drive that will help reduce tidal flooding. This project included replacing approximately 130 feet of 15-inch stormwater pipe and associated structures, restoring curb as needed and replacing a tidal valve. I am happy to report that this was completed at the end of August!



 

Existing Project Updates


A1A Streetscape project improvement


The City of Fort Lauderdale is working with Weekley Asphalt Paving, Inc. to make streetscape improvements along A1A from the Fort Lauderdale Beach Parking Lot entrance (near SE 5 Street) to Sunrise Boulevard. This project will enhance pedestrian lighting and safety and create a signature hardscape pattern at the intersection of A1A and Las Olas Boulevard.

This project remains on time and on budget. With 70% of the project being completed, construction is expected to be completed in December 2023. Almost all areas where open-trench installation is required for pedestrian lighting due to conflicts with existing utilities have been completed (90 out of 120 linear feet) and Sub-contractor UEG has completed work on all 117 concrete spread footers and installing pull boxes for light poles along southbound A1A.


Las Olas Undergrounding


The following is a look at the work that has taken place over the past month by Contractor & Sub-Contractors Ferreira, International Drilling, Inc. (IDD), Voss Engineering, OY Underground, and Best Underground.

  • Completed installing vaults and junction boxes for AT&T and Comcast on all streets. The missile borers for residential service have been completed on all streets. Ferreira completed the installation of handhole and pedestals for AT&T and Comcast on all streets.
  • Ferreira/IDD completed installing the 4-inch Comcast conduits on Las Olas Boulevard, which go under the vaults.
  • FPL completed locates for proposed streetlights. L&S (FPL’s lighting contractor) has completed the installation of the junction boxes that go next to each streetlight. Streetlight poles have been staged on Las Olas Boulevard.
  • Completed installation of FPL Vista switches within the Isle of Capri Drive median and all along Las Olas Boulevard.
  • Ferreira has completed debris removal and asphalt patches on all streets.


Substantial completion is expected in November 2023 and final restoration work is expected to be completed by the end of 2023. 


Thank you to all of our District 2 residents who consistently give their input on projects that come before the Commission. As we move towards the fourth quarter of 2023, I am very excited for the upcoming projects and funding that have been allocated to our District. We have made and will continue to make great strides in improving our infrastructure and not only beautifying our neighborhoods, but also preparing for sea level rise and becoming resilient.



Michael Phelps Making a Splash in Fort Lauderdale

A1A Streetscape Improvement Project

Post Date: September 22, 2023 6:00 PM

Recently Completed Activities

  • Work Complete: 71%
  • Schedule Complete: 59%
  • Daily lane closures along southbound A1A from the southwest corner of Sunrise Boulevard towards Seville Street and along northbound A1A from north of the Fort Lauderdale Beach Parking Lot to north of Castillo Street.
  • All areas where open-trench installation was required for pedestrian lighting due to conflicts with existing utilities have been completed.
  • Sub-contractor UEG has completed the installation of light poles and pull boxes and is almost done with the installation of the new light fixtures.


Upcoming Activities (Through 10/6/23)

  • Continue operations along southbound and northbound A1A.
  • Continue connecting load centers at each light pole location.
  • Sub-Contractor UEG will continue installing light fixtures (88 out of 117 have been completed, which is 75%) and running wires and interconnections on both southbound and northbound A1A.
  • The contractor will continue working on decorative concrete along the east sidewalk near the beach entrance at Las Olas Boulevard. This beach entrance will be temporarily closed for approximately 3 weeks. Pedestrians will be detoured to beach entrances north and south of this location.
  • The contractor will continue working on hardscaping operations on the east sidewalk from the Fort Lauderdale Beach Parking Lot toward Poinsettia Street along northbound A1A.
  • The contractor will continue to install pavers as needed.


Traffic Impacts

  • Daytime operations (Monday through Friday, 8 a.m. to 4 p.m.) will continue for the installation of light fixtures and wiring along the sidewalk on the west side of southbound A1A and along the west side sidewalk of northbound A1A from north of the Fort Lauderdale Beach Parking Lot to north of Castillo Street.
  • Along northbound A1A, the contractor will coordinate the required lane and sidewalk closures for hardscaping and lighting operations along both sidewalks of northbound A1A as well as the landscaping and irrigation operations to minimize impacts to traffic and maintain pedestrian safety.
  • Partial closures along A1A in both directions:
  • Southbound: 1 lane (outside) from the southwest corner of Sunrise Boulevard to the northwest corner of Seville Street.
  • Northbound 1 lane (inside or outside) from north of the Fort Lauderdale Beach Parking Lot to north of Castillo Street.


Please follow posted signs and exercise caution when traveling in the

area. We apologize in advance for any inconvenience and thank our neighbors for their patience as we work to complete this project.


Additional Information


For more information or questions, contact:

Gary Foster, Senior Project Manager

954-828-6233 or [email protected]

City of Fort Lauderdale 24-Hour Neighbor Service Center

954-828-8000 or [email protected] 

Las Olas Isles Utility Undergrounding

Project Updates

Post Date: September 22, 2023 5:30 PM

Recently Completed Activities

The following is a look at the work that has taken place over the past few days:

  • Completed installing vaults and junction boxes for AT&T and Comcast on all streets. The missile borers for residential service have been completed on all streets. Ferreira completed the installation of handhole and pedestals for AT&T and Comcast on all streets.
  • Ferreira/IDD completed installing the 4-inch Comcast conduits on Las Olas Boulevard, which go under the vaults.
  • FPL completed locates for proposed streetlights. L&S (FPL’s lighting contractor) has completed the installation of the junction boxes that go next to each streetlight. Streetlight poles have been staged on Las Olas Boulevard. Streetlights will not be installed until the wood poles are removed as they will be installed in the same holes.
  • Completed installation of FPL Vista switches within the Isle of Capri Drive median and all along Las Olas Boulevard.
  • Ferreira has completed debris removal and asphalt patches on all streets.


Upcoming Activities (Through 10/6/23)

The following is a look at the work that is scheduled to take place over the next few days:

  • Ferreira will continue work on FPL feeders and primary cables for the switches on Las Olas Blvd.
  • Ferreira will commence electric meter upgrades on all streets in preparation for the power conversion. Some residences will have grounding stakes installed to bring them up to code.
  • All streets have been released to AT&T and Comcast for cable prewiring. Comcast has completed the prewiring on all streets except Royal Plaza and Isle of Palms. Comcast has commenced individual residence fiber optic wiring on Isle of Capri and Bontona Avenue.
  • Ferreira has painted the transformer bases and will continue restoration of areas affected by the work.
  • FPL has been requested to prepare the switches on Isle of Capri for energizing.


Access

As crews work on installing new FPL electric service connections and AT&T and Comcast conduit connections to individual residences, they will require access to the exterior of properties where this work is taking place. Access inside homes is not required, and all construction team members will have visible proof of identification. Click here to see a flyer with additional details about this work.


Traffic Impacts

  • A single lane along each isle may be closed during work hours. Traffic control personnel will assist motorists as needed. Please follow posted signs and drive with caution in the area.
  • There may be times when equipment or materials temporarily block access to driveways during work hours. Crews in the field will coordinate with neighbors during these situations.
  • Driveway and roadway access will be restored at the end of each work shift.


We apologize in advance for any inconvenience and thank our neighbors for their continued patience as we work to complete this project as quickly as possible.


For more information or questions, contact:

Gary Foster, Senior Project Manager

954-828-6233 or [email protected]

City of Fort Lauderdale 24-Hour Neighbor Service Center

954-828-8000 or [email protected]

Southeast Isles Seawall Replacement Project

Post Date: September 21, 2023 6:00 PM

 DC Alexander Park 

Across the street from the Fort Lauderdale Aquatic Center

Parks & public spaces are among our Commission's top priorities! DC Alexander Park is undergoing a $9.6M renovation that will transform it into a beautiful and welcoming spot for locals and visitors alike, complete with:

  • Improved lighting for pedestrians.
  • An elevated platform overlooking the ocean.
  • A new playground.


For more info on this and other large projects, visit: fortlauderdale.gov/majorprojects.

Thank you to Visit Lauderdale for telling the world the story of our community. It is so important that Fort Lauderdale be known as the welcoming, inclusive, and diverse City that we are.

Seven on Seventh Featured on NBC 6

This grant application includes projects in District 2's

Lake Ridge and South Middle River!

A message from our partners at Broward County Government:


The Property Assessed Clean Energy (PACE) program is administered by private companies and is not a rebate or grant managed/operated by Broward County.  Beware of contractors falsely using the County's logo to market themselves.


PACE is a way to finance energy efficiency projects that is offered by external parties to Broward County home/business owners. Program participants will repay this loan through a non-ad valorem special assessment or lien added to their annual property tax bill.


Eligible PACE projects:

  • Rooftop solar panels
  • Solar water heater
  • Energy-efficient air conditioning unit
  • Cool roof
  • Impact windows
  • Insulation


More info: [email protected] | ftlcity.info/pace


You Must Re-Apply to Vote by Mail

Due to a change in state law, Florida Voters who wish to receive a Vote-by-Mail ballot for 2023 through 2024 elections are required to complete a new Vote-by-Mail ballot request.


In 2021, Florida legislators passed a new law that changed the basic rule for mail-in ballots. Previously, a Florida voter's request for a mail-in ballot would be good for two general election cycles, meaning a new request would not be needed for four years. The new law reduces that duration to once per general election cycle, or every two years. As a result, every vote-by-mail request expired at the end of 2022. 


To renew your Vote-by-Mail request, in Broward, click on this link: Mail Ballot Request Service.


For additional information, click here to visit the State of Florida Division of Elections Vote by Mail information page.

Sign up for the City's E-News

Sign up here 

Fort Lauderdale may not have falling leaves, but we can still celebrate the season with Pumpkins and Palm Trees! The 3rd Annual Pumpkins & Palm Trees Fall Fest returns to The LOOP on Fort Lauderdale Beach with an expanded weekend-long celebration, Oct. 20–22. The festive atmosphere and family-friendly event welcome everyone to enjoy tasty fall flavors, local vendors, live music, contests, and activities as we celebrate Fall’s arrival, Florida-style.

 

Highlights of the weekend include the new Friday Night movie, Pet-Friendly Saturday Experience, and a Lifesize Pumpkin House and Pumpkin Patch that will be the talk of everyone's Insta feed. Professional and Cottage Industry bakers are once again invited to share their pumpkin spice and everything nice in the annual Pie Baking competition

 

View the full schedule at: theloopflb.com/fallfest

Are you subscribed to #AlertFTL yet?  Stay connected with us during an emergency- we send out notifications to keep you in the know.

Visit  fortlauderdale.gov/alertftl to sign up today.

We love Fort Lauderdale and we love our volunteers! If you're looking to make a difference in our community, look no further- Team FTL's Neighbor Support office has programs & special volunteering days throughout the year! To get involved, visit ftlcity.info/volunteer.

King Tides and High Tides in Our Community

With seven miles of shoreline; 300 miles of waterway coastline; a flat topography; and shallow, porous aquifer, Fort Lauderdale is vulnerable to the effects of climate change and sea level rise. Flooding in low-lying areas is more likely when the close proximity of the moon, higher than average tides called king tides, rising sea levels, and inclement weather conditions combine to exacerbate flooding risks. Rainfall and wind strength and direction can have a significant impact on the height of the tides causing them to come in higher or lower than predicted. Also note that high water tables (groundwater level) due to rain events can raise the probability of localized flooding. 


Predicted 2023 King Tides  

Each year, the City of Fort Lauderdale reviews the National Oceanographic and Atmospheric Administration's (NOAA) predicted tide elevations. This year, king tides are predicted on at least 28 days. While these dates reflect the current prediction for seasonal higher tides, greater than average tides can occur anytime of the year under varying conditions.



  • September 26 - October 3
  • October 15-17
  • October 26 - November 1
  • November 12-16
  • November 24-28

Check out FTL Connect!

Click on the image below to check out the progress on the Las Olas Marina video cam to watch what is happening in snapshots live or timelapse views.  

International Swimming Hall of Fame Project

Ever since the September 19th City Commission Meeting, there has been an incredible buzz in town and elsewhere about the International Swimming Hall of Fame project; the two buildings will bookend and complete that peninsula in spectacular fashion and compliment beautifully what we have already accomplished there with the new pools and high-dive tower.

Articles

Brightline launches South Florida to Orlando line
Check out Broward Hot Spots with Free Bogo Admission in September
Fort Lauderdale approves $190M overhaul of International Swimming Hall of Fame
Fort Lauderdale housing complex offers stable homes for homeless, cheap rents for local workers
Fort Lauderdale Police Chief Patrick Lynn is retiring
Fort Lauderdale to spend at least $3 million leasing space for police while new station built
Swimming Hall of Fame complex in line for stunning $190 million makeover
You can get free at-home COVID tests again. Here’s how to order them by mail

We have the following Board Vacancies below. Please email Erica Franceschi [email protected] if you are interested in serving on a Fort Lauderdale City Board.  



Board of Adjustment

Cemetery System Board of Trustees

Central City Redevelopment Advisory Board

Code Enforcement Board

Community Appearance Board

Community Services Board 

Nuisance Abatement Board

Boards and Committees Information

The greatness of our community starts with passionate citizens like you. 


Please do not hesitate to contact our Outreach Coordinator, Ashley Cacicedo, with any questions, comments or thoughtful suggestions [email protected] or 954-828-5923.

Fort Lauderdale City Calendar
City News Center
Visit the District 2 Website
Follow us on Facebook
Steve Glassman
Fort Lauderdale City Commissioner, District 2 
Visit our website