Week of June 23, 2025

Haga clic acquí para ver esta información en español.

Preconstruction Activities

Starting the week of June 23, crews are expected to begin daytime work to prepare the interchange for construction activities. Work hours are Monday through Friday, from 6 a.m. to 4 p.m., and will include installing construction signs, testing irrigation, and removing vegetation. 

Upcoming Ramp Closures

Anticipated to begin after the Fourth of July holiday, several on- and off-ramps are expected to be closed at night in order for crews to safely:


  • Install temporary concrete barriers
  • Restripe Katella Avenue
  • Demolish and reconstruct the center median on Katella Avenue/Willow Street beneath the freeway


Night work will generally occur between 9 p.m. and 5 a.m. Specific details regarding ramp closures will be available in next week's communications.


This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Katella Avenue Improvements Map

The rendering below highlights various improvements along Katella Avenue between Coyote Creek Channel and Epson Way. Improvements include:


  • Modification of the northbound on- and off-ramps from its existing configuration to a T-intersection
  • Addition of Class II bike lanes with hatched markings to identify bike lane transitions
  • Installation of a new traffic signal to guide traffic existing the northbound I-605/Katella Avenue off-ramp, as well as upgraded traffic signals
  • Painted crosswalks and newly constructed sidewalks



To view a larger image of the Katella Avenue rendering, click here.

Closures and Detours Map

An interactive "Closures and Detours Map" will be updated regularly highlighting major activities and associated closures and detours. We encourage the community to bookmark the link for quick access to real-time construction information. Click on the image to be redirected.

In the Community

The Public Outreach team has been in the community over the past several months to prepare the public for project construction. The team is dedicated to continue providing regular communications and community engagement during this time.


On Saturday, June 14, the team hosted a meeting in Rossmoor to share project information, inform residents about upcoming construction activities, and address questions from the community.


If your organization or community group is interested in receiving a project presentation, please email the Outreach Team at 605KatellaInfo@octa.net.


About the Project

The Orange County Transportation Authority (OCTA), in cooperation with Caltrans, is improving the local interchange at Interstate 605 (I-605) and Katella Avenue. The project will enhance safety and traffic flow by modifying existing on- and off-ramps, making improvements on Katella Avenue, and improving bicycle and pedestrian facilities.

STAYCONNECTED

Facebook  Instagram

octa.net/605Katella | 800-200-3302 | 605KatellaInfo@octa.net | @605Katella