Westbound Katella Avenue Activities

Lanes on westbound Katella Avenue were restriped and traffic shifted to allow crews to complete the removal of the sidewalk. Motorists should be advised that the outside lane will require them to enter onto the I-605 north on-ramp. Additional signs were installed to direct motorists to the on-ramp.


Following the demolition of the sidewalk, utility relocation is expected to begin next week before the sidewalk is reconstructed later this year.


Eastbound Katella Avenue Activities

Contractors are planning to begin preliminary activities on eastbound Katella Avenue including restriping lanes, saw cutting, and placing temporary concrete barriers. These activities are expected to take place at night. Additional information will be available in future communications.


Sidewalk Access

Signs are in place detouring pedestrians and bicyclists to use the sidewalk on eastbound Katella, which will be maintained throughout construction.

This work may be loud. The schedule is subject to change due to inclement weather or unforeseen operational issues.

Retaining Wall Construction

Crews are preparing to construct the first of three retaining walls along westbound Katella Avenue within the Coyote Creek Channel. Expected to begin next week, this will require the installation of cast-in-drilled-hole (CIDH) piles to form the foundation of the new wall. CIDH piles are formed drilling a hole into the ground and filling it will reinforced concrete to support large structures. Click the infographic to learn more about the CIDH process.

Upcoming Closures

Please plan ahead and expect delays during these times. The following closures are expected to be in place nightly beginning as soon as 9 p.m. to 7 a.m., Monday, Sept. 8 through Friday, Sept. 12 (into Saturday morning):


  • Outside lanes on eastbound and westbound Katella Avenue/Willow Street,

at least one lane will be open to traffic at all times 





Closures and Detours Map

An interactive "Closures and Detours Map" is updated regularly highlighting major activities and associated closures and detours. We encourage users to bookmark the link for quick access to real-time construction information. Click on the image to be redirected.

About the Project

The Orange County Transportation Authority (OCTA), in cooperation with Caltrans, is improving the local interchange at Interstate 605 (I-605) and Katella Avenue. The project will enhance safety and traffic flow by modifying existing on- and off-ramps, making improvements on Katella Avenue, and improving bicycle and pedestrian facilities.