Westbound Katella Avenue Activities
Lanes on westbound Katella Avenue were restriped and traffic shifted to allow crews to complete the removal of the sidewalk. Motorists should be advised that the outside lane will require them to enter onto the I-605 north on-ramp. Additional signs were installed to direct motorists to the on-ramp.
Following the demolition of the sidewalk, utility relocation is expected to begin next week before the sidewalk is reconstructed later this year.
Eastbound Katella Avenue Activities
Contractors are planning to begin preliminary activities on eastbound Katella Avenue including restriping lanes, saw cutting, and placing temporary concrete barriers. These activities are expected to take place at night. Additional information will be available in future communications.
Sidewalk Access
Signs are in place detouring pedestrians and bicyclists to use the sidewalk on eastbound Katella, which will be maintained throughout construction.
|