Retaining Wall Construction
Crews have completed pouring and curing leveling pads as part of the foundation for the new retaining wall along the northbound I-605 Katella Avenue on-ramp. Construction of the retaining wall has started and is expected to continue through the end of the month during both daytime and nighttime hours. Activities include placing structural backfill material and assembling wall components.
CLOSURES: This work will require nightly closures of the northbound I-605 Katella Avenue on-ramp, northbound straight off-ramp, and one outside lane on northbound I-605.
WHEN: 10 p.m. to 5 a.m. nightly, Monday, March 23 through Thursday, March 26 and 10 p.m. Friday, March 27 to 7 a.m. Saturday, March 28.
|