Menetre Park Boat Launch


Construction of the new boat launch is proceeding nicely. Four piers will access three new ramps.


Contractor expects completion in early July.


Me … I don't give timelines.

An L-shaped pier has been constructed on the down stream side. Once a boat is launched, it can move to this "logistics pier" for loading and unloading … allowing others to use the ramps. That's cool.

Downtown Paving Projects

Phase I

Prior to repaving any roadway, the City assesses the subterranean infrastructure (particularly sewer lines and subsurface drainage). The hope is to make as many repairs as feasible BEFORE covering it with a new layer of asphalt. This process is tedious, time consuming and common sense.


We are now satisfied with the subterranean infrastructure below Rutland, Gibson and Hebert Lane and/or the plan to make repairs under them during the asphalt overlay phase. Construction contract currently under review.

Downtown Paving Projects

Phase II

New Hampshire, Columbia, Florida, Lee Rd and Lockwood

Smoke testing of these streets revealed a large number of failures in the sewer collection system … primarily where lines running from the property owner connect with the main sewer lines.


Our engineering department conceived the idea that these be repaired at the same time the street is being milled down for overlay. A scope of work to that effect is being created.


The plan is to begin this construction once Phase I is substantially complete or complete. This is to minimize street closures.

South New Hampshire, Covington Point

Paving Projects

Bid process has been completed for S. New Hampshire Street paving and contract is being prepared.


Budget allowed for us to include a section of Covington Point Drive : ).


Oh, the irony is not lost. We pave a street to make is smooth. Then we add speed bumps to make it bumpy. I've come to detest speed bumps. 96% of our drivers go the speed limit yet all are punished 100% of the time they pass over a bump. If only there was a better way … like everyone driving the speed limit?


Ozone Field Dugouts

Our men's softball team (the DC Dogs) began happily playing games and hosting tournaments at Ozone Field last year. No concession stand, no worry: Fans setup pop-ups serving sandwiches, snow balls and cotton candy. All Good.


No bathrooms, no worry: "Mayor, we're happy with the port-a-let."


No dugouts, well now we got a problem. Players waited for their turn on the field along the baselines. Dugouts, for safety's sake, became a priority. Skilled carpenters from across the Public Works department built two lovely dugouts. When work like this is done "in-house" by Public Works, it typically costs 60% less than contracting it out. Good Stuff.

The "big one" still missing at the Park is lights for the field … a beautiful field which cannot be used on hot summer nights. My hope is, once we get some of these other projects substantially complete, we can address the lighting.

Hubie Gallagher Tennis Courts


One by one, the City has been upgrading each park across town. 


Last year, it became Hubie Gallagher's (HG) turn. After numerous onsite visits and resident input, a few things came to light.


The tennis court is basically non-functional. The plastic grid surface does not allow the balls to bounce properly. I concluded that we (the city) have gotten our money's worth out of the court that has been there since I was a child. That was in a different century.


Of all the possible improvements we could consider at the park, replacing the courts became the priority. We immediately began moving at the Speed of Government. What I can do in private business in six months will take closer to 18 months. During the Fall budget process, Councilman Jimmy Inman and I requested $300,000 from the Council in the 2025 budget. The budget passed in November and the money became allocated on January 1, 2025.


Now, here's the kicker: In Government, no work is allowed on the project until the money is allocated. No design, no project scope, no advertising for bids. So, it wasn't until January that I was allowed to select a firm to create drawings and specifications for bid purposes … then wait on that contract to be created and executed. Afterwards, the firm spent several weeks creating the plans. Once in hand, we then (by law) had to advertise for bids for 30 days. Once bids were in hand, our engineering department (and by department, I mean 4 people) had to vet their bids and qualifications. That process was completed two weeks ago. The next step was to create the contract document and execute same. Last week I finally signed the contract ($267,000). Then and only then, can the contractor begin ordering materials. Currently, I offer no timeline for completion.



Demolition and removal of the court is currently being done "in-house" by our Public Works Department. Whenever we are able to use Public Works' employees and equipment, I estimate we usually save about 60% in cost. That's a good thing.


Strong consideration was given to pickle ball. Unfortunately the constant pop-pop-pop sound of the ball against the paddles is not a nice thing in a residential neighborhood. We have a site chosen at the Rec Park near the baseball fields, but no timeline. We need for a number of these current projects to get well underway before considering pickle ball from both a financial and a time-management perspective.

And, of course, Things to Do

Pool Opens May 30th

Tues - Sun, Free

11:00am - 6:30pm

Splash Pad Daily

9:00am - 9:00pm

Free

Tickets for Shows Here.


 Season Tickets Here.

7th Annual Falaya Float

June 7th

Benefitting St. Tammany Hospital's autism fund -

Click here for details.

Final Friday Block Party - May 30th

Sparks in the Park - June 28th

Mayor Mark's History Corner


At 8:30am on the 3rd Tuesday of each month, Lake Radio 94.7 has me as a guest. Most recently I gave my interpretation of the Louisiana Purchase and the Republic of West Florida. Here's 8 minutes and 43 seconds of your life you'll never get back:


Mayor Mark's History Corner

Replies to this e-mail go directly to Mayor Mark.

Rooted in History, Focused on the Future

Mayor's Page| by Mayor Mark