Items 13.1, 13.2, and 13.3
Justice Center Project - Construction and Design Approvals
The Board of County Commissioners will consider three important items related to the new Douglas County Justice Center—a long-planned project to meet our community’s growing public safety and judicial needs. This project is the result of a multi-year planning effort that began in 2014, when the County identified that the current Judicial Law Enforcement Center (JLEC) had reached capacity and could not accommodate future growth. After evaluating multiple alternatives, building a new facility proved to be the most cost-effective long-term solution.
Earlier work, including the widening Buckeye Road, site grading, utility installation, and building a central utility structure, has already been completed. This next phase further advances the County’s objective of delivering a modern, purpose-built space for court and judicial functions.
13.1 Contract for Construction Quality Control Testing
Commissioners will consider approving a contract of up to $355,570 with Construction Materials Engineers, Inc. This firm will provide material testing services during construction of the Justice Center to ensure the work complies with all plans, codes, and quality specifications. The contract is structured on a time-and-materials basis and is funded through the same project account.
13.2 Approval of $47.9 Million Construction Contract
The Board will vote on a contract with CORE Construction to begin full-scale construction of the new Justice Center building. This second and final phase follows earlier work that included road widening, site grading, and utility installation. CORE Construction was selected through a competitive process and has partnered with the County before on the Community & Senior Center project. The project team also includes TSK Architects.
This Construction Manager at Risk (CMAR) approach allows for close coordination among the County, contractor, and design team to ensure the project is delivered on time and within budget. The proposed construction cost is just under $47.9 million, and notably, the final bid came in $2 million below previous estimates. Several local and regional subcontractors will be involved in the project.
13.3 Additional Design Services by TSK Architects
The County will vote on whether to approve a $350,000 supplemental payment to TSK Architects, the project’s lead design firm. This request reflects additional work that was requested by the County during the design phase. That work included:
- Redesigning the building to reduce square footage from 72,000 to a more efficient footprint
- Supporting a two-phase construction strategy to speed up early site work
- Creating a design concept for a separate Juvenile Probation Office for cost analysis
- Extending the planning process to ensure broader stakeholder and community input
These design services were not part of the original scope of work but were requested by the County to ensure the best long-term outcome for the community.
These decisions reflect Douglas County’s commitment to fiscal responsibility, community engagement, and long-term planning. We encourage residents to attend the meeting in person or follow along online to stay informed about this and other important County projects.
|