North Sea Pines Drive Infrastructure Improvement Project
Sea Pines CSA has identified approximately 1.3 miles of North Sea Pines Drive from the Sea Pines Ocean Gate to the Lighthouse Road intersection to undergo extensive storm water drainage repairs and road resurfacing in 2020 and 2021.
The project is currently out to bid and will be executed in two (2) phases. Phase 1 (storm water improvements) are expected to take place from November of 2020- March 2021 and Phase 2 (road resurfacing) is expected to take place from September-December 2021.
Background on North Sea Pines Drive:
- The roadway, infrastructure, and leisure trails from Ocean Gate to the Lighthouse Road intersection are in need of redesign, repairs and reconstruction.
- Sea Pines Drive is the oldest roadway in all of Sea Pines. The useful life of this roadway the volume of traffic had exceeded the initial design and construction.
- Numerous stormwater failures have occurred along this section of roadway and the adjacent streets due to the condition of the system. This is largely due to the deteriorating corrugated metal and orangeburg pipes throughout the system.
Project Details:
Phase 1: Anticipated to begin November 2020 and completed by February/March 2021 to address drainage improvements in preparation for Phase 2. CSA will be reaching out to property owners who live within the project zone to communicate how they will be impacted by this work and we will to update the community on our traffic management plan.
Phase 2: Expected to begin in September 2021 and be completed by the end of 2021. The improvements will include stabilizing, realigning, and resurfacing of the roadway and leisure trails within the project area.
We look forward to keeping you updated as we move through this process. For questions, please contact the Sea Pines CSA Maintenance Department by phone at 843.671.7849 or by email at csamaintenance@csaseapines.com