Please see below for the updated schedule through next Wednesday, July 30.
Today (Wednesday, July 23)
- Tree removal in Shorewood Oaks.
- Filling behind the new curb and clean up Eureka Rd.
- Patching in Shorewood Oaks around the remaining manholes and gate valves.
Tomorrow (Thursday, July 24)
- Paving will begin in the morning, starting on West Lane and moving toward Boulder Bridge.
- Lowering iron on Eureka Rd will happen right away in the morning.
- All remaining concrete work along Eureka Rd will be completed.
-
Raising iron along Yellowstone Trail. Yellowstone Trail will be closed.
- Tree Removal in Shorewood Oaks.
- Restoration including irrigation and dog fence corrections.
Friday, July 25
- Tree Removal in Shorewood Oaks.
- Depending on time, the remaining trees along Eureka Rd will be removed.
- Restoration including irrigation and dog fence corrections.
-
Raising iron along Yellowstone Trail. Yellowstone Trail will be closed.
Monday, July 28
-
Tree removal along Yellowstone Trail. Yellowstone Trail will be closed.
Tuesday, July 29
- Milling Eureka Rd & Orchard Cir. All curb that will be placed on Monday will not be affected by the milling operations.
-
Tree removal along Yellowstone Trail. Yellowstone Trail will be closed.
Wednesday, July 30
-
Tree removal along Yellowstone Trail. Yellowstone Trail will be closed.
|