2025 Mill & Overlay Update

Please see below for the updated schedule through next Wednesday, July 30.


Today (Wednesday, July 23)

  • Tree removal in Shorewood Oaks.
  • Filling behind the new curb and clean up Eureka Rd.
  • Patching in Shorewood Oaks around the remaining manholes and gate valves. 

 

Tomorrow (Thursday, July 24)

  • Paving will begin in the morning, starting on West Lane and moving toward Boulder Bridge.
  • Lowering iron on Eureka Rd will happen right away in the morning.
  • All remaining concrete work along Eureka Rd will be completed.
  • Raising iron along Yellowstone Trail. Yellowstone Trail will be closed.
  • Tree Removal in Shorewood Oaks.
  • Restoration including irrigation and dog fence corrections.

 

Friday, July 25

  • Tree Removal in Shorewood Oaks.
  • Depending on time, the remaining trees along Eureka Rd will be removed.
  • Restoration including irrigation and dog fence corrections.
  • Raising iron along Yellowstone Trail. Yellowstone Trail will be closed.

 

Monday, July 28

  • Tree removal along Yellowstone Trail. Yellowstone Trail will be closed.

 

Tuesday, July 29

  • Milling Eureka Rd & Orchard Cir. All curb that will be placed on Monday will not be affected by the milling operations.
  • Tree removal along Yellowstone Trail. Yellowstone Trail will be closed.

 

Wednesday, July 30

  • Tree removal along Yellowstone Trail. Yellowstone Trail will be closed.

 

Questions?

Questions on the overall project may be directed to Construction Project Representative Lauren Schmidt at (651) 421-0995.