2025 Mill & Overlay Update & Upcoming Schedule

Significant progress has been made along Eureka Rd. Contractors were able to complete their work and bring the new gas main live last Friday afternoon on July 11. The contractor has also started to dig out for the new curb around the intersections and some main line work.


Earlier today, July 15, crews finished raising iron along Yellowstone Trail and continued to work on cutting out for the new curb along Eureka Rd. Patching was also done along West Lane. The tree contractor worked on removing the remaining trees along Boulder Bridge.


Tomorrow (Wednesday, July 16) - Paving will start in the Boulder Bridge neighborhood. Work will continue along Eureka Rd and any final touches that are needed along West Lane. The tree contractor is anticipated to remove trees along Shorewood Oaks and/or Yellowstone Tr.


Thursday, July 17 - Paving is scheduled to continue around town. String line and curb placement is scheduled along Eureka Rd. The tree contractor will continue to remove trees around the project.


Friday, July 18 - Paving of remaining roads (minus Eureka Rd and Orchard Cir) is scheduled, as well as flat work concrete along Eureka Rd.

 

Milling Eureka Rd and Orchard Cir has been moved to Thursday, July 24. Paving has not been rescheduled at this time, but may occur on Friday, July 25 or early during the week of July 28-August 1.

Questions?

Questions on the overall project may be directed to Construction Project Representative Lauren Schmidt at (651) 421-0995.