36th Street Construction Starting Soon

We have exciting news! 



Construction is starting on 36th Street as funded through general obligation bond 20-351.


What is happening?

36th Street between Main Street and Commercial Avenue is a minor collector serving nearby businesses and neighborhoods. The pavement is starting to delaminate, so a timely mill and overlay will extend its life and help avoid more costly reconstruction later. The project also includes ADA upgrades at existing ramps to improve accessibility and meet ADA requirements.


When will the work happen?

The contractor will begin staging traffic control and preparing the site, 

including saw cutting, the week of April 20. Construction is expected to 

start the week of April 27 and is scheduled to be completed no later than September 30, 2026.


How will this affect me? 

Local access to homes and businesses will be maintained during construction, though temporary lane closures, driveway closures, and no parking zones will occur. You may experience changes to normal travel routes, along with construction noise, dust, and heavy equipment. Advance notice will be provided before any driveway, parking, or lane closures.


Thank you for your patience and understanding as we work to improve 36th Street.

Click the button below for more project details and updates.

 

36th Street between Main Street and Commercial Avenue, before construction begins

 
Help Others Stay Informed

Forward this email to other community members you know who may like to be informed about the GO Bond Measure street repair projects. vThey can use the button below to sign up to receive these email updates automatically!

 
 

Questions?

Kristi Krueger, P.E.

Capital Engineering Manager

541-726-4584

kkrueger@springfield-or.gov