Construction Update

May 31, 2024

Ongoing Activities


Pedestrian Ramp Upgrades


  • Construction crews are upgrading pedestrian ramps on eastbound 400/500 South at selected locations to comply with current ADA standards.
  • Concrete requires several days to cure; please avoid using new ramps for up to seven days.
  • Follow posted pedestrian detours for your safety.
  • Traffic signal work and pedestrian push button upgrades are occurring concurrently with the ramp work.


Utility Adjustments


  • Utility access adjustments are underway, including lowering manholes and valves.
  • Jackhammers are breaking the concrete surrounding utility accesses.
  • Temporary asphalt will fill gaps to allow machinery to remove old asphalt without damaging utilities.
  • Expect increased percussive noise from jackhammering in nearby areas.


Traffic Impacts


  • Sunday, June 2, 7 a.m. - 12 p.m., eastbound 400/500 South between 800 East and 1300 East will be reduced to one travel lane. Between 12 p.m. - 5 p.m., westbound 400/500 South will be reduced to one travel lane from 1300 East to 800 East. These lane closures are necessary to adjust utilities in the travel lanes.

Schedule & Impacts

  • Pedestrian Ramps: Daytime work Sunday through Friday 7am to 7pm.
  • Roadway: Nighttime work Sunday through Thursday 8pm to 7am.
  • Temporary sidewalks closures during ped ramp demolition and reconstruction.
  • Lane shifts and temporary lane closures during construction. 
  • Nearby residents will notice construction-related noise and vibration.

Project Highlights:


This project involves removing old asphalt and placing new asphalt pavement to enhance this crucial east-west route. it also involves:


  • ADA Ramp Upgrades: Modifications ensure sidewalk transitions are accessible to everyone.
  • Adjusting Manholes: Lowering utility accesses (i.e., manholes and water valves) to allow for milling.
  • Milling: Removing old asphalt which will make the roadway rough temporarily.
  • Paving: Applying new asphalt for a smooth finish.
  • Raising Manholes and Valves: Adjusting utility access points to the new roadway surface.
  • Roadway Striping: Applying final paint for striping/crosswalks/messages to new pavement.

Safety

Sidewalk Closures


Construction of updated pedestrian ramps will require temporary sidewalk closures. Crews are working along the south side of 400/500 South throughout the corridor. Pedestrians are encouraged to use the north side of 400/500 South and follow posted detours.

Other Area Projects

Support Local Business

Shopping locally boosts the economy, generates tax revenue, and supports small businesses during construction, ensuring continued access to your favorite spots.

UTA Information

We do not anticipate this project to interfere with UTA routes/stops along 400 South/500 South.


Click the UTA logo at left for route and schedule information

Project Background

The Utah Department of Transportation (UDOT) undertaking a pavement rehabilitation project on 400/500 South (SR-186) from State Street to 1300 East in Salt Lake City. The project is anticipated to last through August 2024 and also includes upgrading selected pedestrian sidewalk ramps to meet current Americans with Disabilities Act (ADA) standards. 

Contact the Team

This project has a dedicated Public Involvement Team to answer questions or concerns you may have throughout construction. If you are interested in joining our mailing list to receive weekly construction activity updates, contact our team using the information below:


Project Hotline - 800-292-3557

Email - 400SouthImproved@utah.gov

Project Website: https://publicinput.com/400SouthImproved

There are several other regional projects taking place this construction season.

For the latest information regarding this and other UDOT construction

projects, download the free UDOT Traffic app on any iPhone or

Android device or visit udottraffic.utah.gov.