Following the realignment and traffic shift of the segment of Live Oak Drive near the Langley Swim and Tennis Club toward the new noise wall, work is underway to rebuild the Club’s exit and install curb and gutter. Construction in this area will be completed no later than Thursday, May 15, ahead of the start of the Club’s swim season on Saturday, May 24 (certain additional work may occur later, but it will not impact access to the Club).
Alongside Live Oak Drive, from the Club’s parking lot to approximately 1,300 linear feet north (beyond Private Live Oak Drive), areas behind recently constructed curbs are in the process of being cleared and will be graded, covered with topsoil, and seeded.
Extended work hours, including flagging operations directing alternating one-way traffic, are necessary to complete construction in this section of Live Oak Drive.
|