Longitudinal Joint Sealant: 2 days, beginning Monday, July 13
An approved 6:00 a.m. start has been granted to take advantage of cooler morning temperatures and minimize vehicle traffic crossing the freshly placed sealant, reducing the potential for material tracking and ensuring proper adhesion and curing.
HMA Surface Course: 4 days, beginning Tuesday, July 14
Aggregate Shoulders: 1 day
Topsoil and Seeding Restoration: 2 days
Thermoplastic Pavement Markings: 1 day
Final Project Walk-Through: Date to be determined
Please use caution, follow all traffic-control signage, and avoid driving over freshly placed joint sealant. The sealant is typically traffic-ready within 30–60 minutes. Thank you for your patience as these final improvements are completed.
|