900 South Construction Update | October 10, 2019*

  • Crews will be finishing the construction of driveway approaches by the end of this week.

  • Starting next week, Monday, October 14, crews will begin paving activities along the south side of 900 South from 950 East to McCleland Street.

  • During this time, they will also begin excavating the section between McClelland Street and 1100 East.

  • Today traffic was switched to the north side of 900 South at the 1100 East intersection so that crews can begin excavation activities at the south side of the roundabout.

  • Gilmer Drive at the 1100 East intersection will be closed temporarily until this work is completed.

  • Additional underground utility work at the south side of the roundabout will be conducted, before paving activities begin the week of October 21.

  • Once this utility work is completed, paving will extend south along 1100 East to approximately 930 South.

  • Crews are on schedule to complete the project by November 1.

  • The project is now 80% complete.

*Construction schedule is subject to change due to weather or unforeseen circumstances.