Upcoming Activities

As early as Thursday, March 7 and again on Thursday, March 14 between 4:00 a.m. and noon, crews will begin pouring the concrete deck to construct the new, widened outside lanes across the Jordan River.

  • Work will have an early morning start lasting through early afternoon with no impacts to traffic.

As early as Thursday, March 7, crews will begin overnight work from 8:00 p.m. through 5:00 a.m. in the intersection of 1300 West 9000 South to install a new canal irrigation line. This work will take place nightly for a minimum of two weeks and consists of crossing the south side of 1300 West and the east side of 9000 South.

  • Motorists can expect lane closures on 9000 South and 1300 West along with periodic closures of southbound 1300 West. When 1300 West is closed, use Redwood Road to 9800 South as an alternate route.

Area residents may expect an increase in overnight/early morning construction related noise and vibration.

Ongoing Activities

Shifting lanes and lane closures at all hours for roadway maintenance (pothole repair, line painting, debris removal, etc.).


Short-term business driveway access interruptions while crews cross with new irrigation and storm drain lines along with utility relocations. Alternate business accesses are open and posted.


Shoulder work between 900 West and 1300 West for concrete and retaining wall installation. Please use extra caution as work is immediately adjacent to the roadway.

 

*Schedule is subject to change due to weather, equipment, or material delays.

Crews placing rebard on the new bridge on the north side of 9000 South over the Jordan River.

Crews placing rebar on the northern section of the 9000 South bridge over the Jordan River.

Crews forming the new bridge deck on the south side of 9000 South over the Jordan River.

Crews forming the southern section of the 9000 South bridge over the Jordan River.

Safety

35 MPH sign

Slow Down - Give 'em a Brake! 


The speed limit has been reduced to 35 miles per hour through the entire work zone from 600 West to Redwood Road. 

Road Worker Fatality statistics from the Bureau of Labor Statistics and the National Work Zone Awareness Week

Information for bicyclists and pedestrians


All bicycles need to use the approved detour and avoid 9000 South and pedestrians are prohibited from using 9000 South between 700 West and 900 West as there are no pedestrian pathways/shoulders on 9000 South.


See detour information below.

Bicycle Detour

Pedestrian Detour

Road Closure Information

1510 West Closed at 9000 South


Crews have closed 1510 West on the south side of 9000 South to install a new canal irrigation line across 1510 West. This closure will last for approximately two weeks. Business access will remain open.


Click for detour route.

Eastbound 9000 South left turn closed at 700 West


The left turning lane to 700 West from eastbound 9000 South has been closed through summer 2024.


Click for detour route.

Galilee Way Closure


Galilee Way has been closed at 9000 South through the end of March.


Click for detour route.

Area Projects

West Jordan City 1300 West Widening Project

Support Local Business

Supporting local businesses not only stimulates local economies, but the tax revenue made through sale taxes from local businesses supports local government. This is then used to reinvest in the community. During construction, it is especially important to make a commitment to shop locally and support small businesses along the corridor.


Accesses to all your favorite businesses will always be maintained - just maybe in a different location. #ShopLocal

Traffic/Transit Information

Know before you go. Check UDOT Traffic before hitting the road. 
UDOT main logo
UTA Logo

UTA Bus Route F590 - Due to construction activities, the bus stops within work areas may have temporary closures and stop adjustments. Visit UTA's website for specific stop information

Contact the Team

This project has a dedicated Public Involvement Team to answer questions or concerns you may have throughout the duration of construction. If you are interested in joining our mailing list to receive weekly construction activity updates, please reach out to our team at the contact information below.


Project Hotline - 855-925-2801 Project #5626

Email - [email protected]

Project Website: https://publicinput.com/widen9000south