Upcoming Activities

Tonight, Wednesday, October 9, crews will make an emergency repair to a water line under 9000 South near 1230 West. This work will start at 8:00 p.m. and require one eastbound lane to close through 5:00 a.m. Thursday morning. Additional night work is possible.


Area residents may experience an increase in overnight construction related noise and area lighting. Drivers should reduce speed through the work zone and watch for shifting traffic lanes and sudden stopping traffic.

All left turns between Redwood Road and 700 West (except 1300 West) have been temporarily closed (see detour maps below).


Due to material availability, the work in the 1300 West intersection has been rescheduled for November 1 - 4 (weather permitting).

Ongoing Activities

Crews have shifted eastbound traffic onto the new asphalt between Redwood Road and the Jordan River and have started work in the center of the roadway.



During this time, left turning movements across 9000 South will not be allowed. Vehicles exiting driveways or other side streets will be required to turn right. Drivers should not enter the work zone as there will be severe drop-offs as crews will be removing 7"-12" of asphalt. Please make U-turns at Redwood Road, 1300 West, or 450 West. See detour maps below.

Map of work area and turning movements on 9000 South between 700 West and Redwood Road.
Map of work area and turning movements on 9000 South between 700 West and Redwood Road.

Detour maps while work takes place in the center of 9000 South.

Left - Section between 1300 West and Redwood Road.

Right - Section between 1300 West and 700 West.

Crews removing the old asphalt from the center section of 9000 South between 1300 West and the Jordan River. Looking west.

Crews removing the old asphalt down the center of 9000 South between 1300 West and the Jordan River.

Crews preparing the center section of 9000 South for asphalt between 1510 West and Redwood Road. Looking west.

Crews preparing the center section of 9000 South for new asphalt between Redwood Road and 1510 West.

Nearby residents and business may have an increase in noise, dust, and vibration as work takes place.

Crews continue on the center section of new bridge over the Jordan River along with installing new traffic signal poles and street lighting conduit.

Crews forming and placing rebar on the center section of the 9000 South bridge over the Jordan River. Looking west.

Crews forming and placing rebar on the center section of the 9000 South bridge over the Jordan River.

Traffic accessing the River Oaks Driving Range may only access the parking lot from eastbound 9000 South. Westbound traffic may only make a U-turn at 1300 West. See the detour map.

Traffic and Transit Information

Know before you go! Check UDOT Traffic before hitting the road. 

UDOT main logo
UTA Logo

UTA Bus Route F590 - Due to construction activities, the bus stops within work areas may have temporary closures and stop adjustments.

Visit UTA's website for specific stop information.

Safety

Shoulder Drop Off Sign

Drivers should not drive into the work zone as hazards including significant drop-offs will be present. 


For safety, drivers should make legal U-turns at signalized intersections.

View of 1600 West 9000 South showing drop off into work zone and approved business driveway access marked

Pedestrians and bicycles are not allowed on 9000 South over the Jordan River. Please see the approved detour route for pedestrians and bicycles.

35 MPH sign

As a reminder, the speed limit has been reduced to 35 miles per hour along the entire corridor.

Give 'em a brake safety sign

Contact the Team

This project has a dedicated Public Involvement Team to answer questions or concerns you may have throughout the duration of construction. If you are interested in joining our mailing list to receive weekly construction activity updates, please reach out to our team at the contact information below.


Project Hotline - 855-925-2801 Project #5626

Email - widen9000south@utah.gov

Project Website - www.udotinput.utah.gov/widen9000south