Upcoming Activities

As early as Friday, October 18, crews will shift eastbound traffic back to the center of 9000 South to allow room to install sidewalks and make driveway approach connections.


Drivers should reduce their speed and be prepared for the new traffic pattern.

As early as Friday, November 1 at 8:00 p.m. through Monday, November 4 at 5:00 a.m., crews will close 1300 West across 9000 South while crews rebuild the intersection. Traffic on 1300 West will be allowed to turn right onto 9000 South along with 9000 South traffic being able to turn right onto 9000 South. No left turns will be allowed. Use Redwood Road as a detour route.

1300 West Work in the center detour map

Ongoing Activities

Left turning movements across 9000 South will be restored by Friday morning. Thank you for your patience and for patronizing local businesses!

Crews have paved the center section of 9000 South and are working on painting lane lines and raising utility covers.

Crews have paved the center section of 9000 South and are working on painting lane lines and raising utility covers.

Crews preparing the center section of 9000 South for asphalt between 1510 West and Redwood Road. Looking west.

Crews cutting the asphalt to expose the utility cover and then will raise the cover with concrete. 

Nearby residents and business may have an increase in noise, dust, and vibration as work takes place.

Crews continue on the center section of new bridge over the Jordan River along with installing new traffic signal poles and street lighting conduit.

Crews forming and placing rebar on the center section of the 9000 South bridge over the Jordan River. Looking west.

Crews forming and placing rebar on the center section of the 9000 South bridge over the Jordan River.

Traffic accessing the River Oaks Driving Range may only access the parking lot from eastbound 9000 South. Westbound traffic may only make a U-turn at 1300 West. See the detour map.

Traffic and Transit Information

Know before you go! Check UDOT Traffic before hitting the road. 

UDOT main logo
UTA Logo

UTA Bus Route F590 - Due to construction activities, the bus stops within work areas may have temporary closures and stop adjustments.

Visit UTA's website for specific stop information.

Safety

Shoulder Drop Off Sign

Drivers should not drive into the work zone as hazards including significant drop-offs will be present. 


For safety, drivers should make legal U-turns at signalized intersections.

View of 1600 West 9000 South showing drop off into work zone and approved business driveway access marked

Pedestrians and bicycles are not allowed on 9000 South over the Jordan River. Please see the approved detour route for pedestrians and bicycles.

35 MPH sign

As a reminder, the speed limit has been reduced to 35 miles per hour along the entire corridor.

Give 'em a brake safety sign

Contact the Team

This project has a dedicated Public Involvement Team to answer questions or concerns you may have throughout the duration of construction. If you are interested in joining our mailing list to receive weekly construction activity updates, please reach out to our team at the contact information below.


Project Hotline - 855-925-2801 Project #5626

Email - widen9000south@utah.gov

Project Website - www.udotinput.utah.gov/widen9000south