Construction Update

January 16, 2025

Upcoming Activities

As early as Monday, January 27, work will begin on 700 West between 8800 South and 9000 South. Initial work consists of installing and upgrading the current storm drain line along and across 700 West.


Lasting through January 31, periodic daytime (8:00 a.m. - 4:00 p.m.) road and/or lane closures are expected on 700 West. When closed, use Sandy Parkway as a detour route (see detour map to the right).


Additional upcoming work on 700 West includes widening the roadway and installation of curb, gutter, and sidewalks.

Closure and detour map for 700 West at 9000 South showing work on the north side of the intersection and the detour route being Sandy Parkway.

Ongoing Activities

Sidewalk and driveway work continues on the south side of 9000 South. During sidewalk and driveway work, properties with more than one access will have one access closed while the other access is left open. Properties with only one access will be coordinated with the project team.


Pedestrians should continue to use the north side of 9000 South between 1000 West and Redwood Road and use the approved detour to cross the Jordan River.


The project is on schedule to be completed in July 2025.


Schedules are subject to change due to weather and material/equipment availability.

Question mark with a person standing next to it in a thinking pose.

Did you know?


Our crews have used over 647,000 pounds of reinforced steel during this project - most on the new bridge over the Jordan River! That's more than a 747 weighs!

Infographic with information on the progress of the construction project.
Infographic with information on the progress of the construction project.
Infographic with information on the progress of the construction project.

Infographics current as of December 31, 2024.

Traffic and Transit Information

Know before you go! Check UDOT Traffic before hitting the road. 

UDOT main logo
UTA Logo

UTA Bus Route F590 - Due to construction activities, the bus stops within work areas may have temporary closures and stop adjustments.

Visit UTA's website for specific stop information.

Safety

Pedestrians and bicycles are not allowed on 9000 South over the Jordan River. Please see the approved detour route for pedestrians and bicycles.

Contact the Team

This project has a dedicated Public Involvement Team to answer questions or concerns you may have throughout the duration of construction. If you are interested in joining our mailing list to receive weekly construction activity updates, please reach out to our team at the contact information below.


Project Hotline - 855-925-2801 Project #5626

Email - widen9000south@utah.gov

Project Website - www.udotinput.utah.gov/widen9000south