MARCH 2026

"Let us arise and build!" So they strengthened their hands for the good work.

- Nehemiah 2:18

There is a LOT of great news to communicate as our Arise & Build Capital Campaign continues to move into the next phase!


We Did It ... But There's More


As we all know, GLORY TO GOD for bringing our community together to raise our initial $7.8 million campaign goal before the end of 2025! But as we also know, these projects are always bigger than initially thought, so we are not ending our fundraising for Arise & Build. We thank everyone who has pledged, donated, prayed and supported the Arise & Build project so far and hope to continue to encourage all parishioners to pledge to the campaign so we can reach 100% parish participation. These large-scale projects rarely follow a straight path and since we're only on this path once, we want it to be done right.


Currently, activity continues to build toward the official commencement of the construction phase. This phase consists of two parts - the Ministry Building renovation and the Church expansion project. Detailed updates on both buildings are explained in the FAQ's below.


Financial Update


As of March 25, we received over $7.8 million in pledges and collected more than $5.6 million (72%) of that! As the project moves forward, and we select a contractor, build a list of furniture, fixtures, equipment and other needs for the community, we will have a better understanding of the additional costs.


The original $7.8 million budget was estimated over one year ago and was based on a preliminary construction budget, prior to any detailed architectural design discussions or comments from the parish. As details were rolled out, we received suggestions from parishioners, the Metropolis of Architectural Committee, architects, interior designers and ongoing conversations with general contractors and other professionals. These conversations identified a variety of adjustments that needed to be made to the design on the buildings. The new items led to more discussions, and overall, much more was needed than originally outlined, including hurricane protection, more robust security, A/V system, stained-glass window removal and an updated narthex design after parishioner feedback.


As we have gone through the permitting process, we have been made aware of specific design changes we will also need to make to satisfy building codes—such as the ratio of parking spaces, pervious/impervious drainage—and these have resulted in some design changes which have increased cost and also delayed the process while we go through multiple revisions. 


Once we get a complete list of items and evaluate final bids from contractors, we will be in a better position to communicate more detailed information and associated costs to the community.

QUESTION:

Has a contractor been hired for the Ministry Building? If so, when will those renovations begin?


ANSWER: Not yet. Our goal is to hire one general contractor for the entire project, including the Ministry Building and the church renovation. We anticipate selecting a contractor by April. Working with a single contractor should help save time and money while allowing for more efficient management of all phases of the project.


Up to this point, we have been evaluating bids from five different contractors for the Ministry Building construction, and have recently narrowed the list it down further. We are currently working with the remaining bidders to ensure their proposals can be compared fairly so we can select the most qualified contractor.


We expect the plans for the church renovation to be completed by the end of March. At that time, those plans will be sent to the preferred contractors for pricing. Our goal is to hire the contractor and begin construction in the next couple of months.


QUESTION:

Why has the Ministry Building been empty since last summer and why was the tenant's lease allowed to expire, thus eliminating the revenue from our budget?


ANSWER: This is a question we've heard from many parishioners. There are both financial and logistical reasons why keeping the tenant's lease would not have fit into our plan.


Keeping the school open another year would have required very costly and necessary repairs. These included replacing the roof and mechanical system (i.e., elevators, HVAC units) costing an estimated $300,000 or more to fix. In fact, for a majority of the 2024-2025 school year, a large portion of the building's HVAC system was either inoperable or not fully functioning. This would've been paid out by the capital funds of the church, thus negating any revenue that would've been earned from another year of the school lease.


From the moment the school vacated the building in June 2025, not having a tenant has made it possible to completely empty the building, allowing architects, engineeers, subcontractors, surveyors, contractors, consultants and the Arise & Build committee to have access to the building during regular work hours during the design phase. These meetings have been critical to the progress of the project and if a tenant had been in the building, access to the building would have only been available after 6:30pm on weeknights and on weekends. With the end of the school year in May and the lease ending in June, it would not have been possible for the design plans to be anywhere near ready and would have further delayed the project.


QUESTION:

Why is the project almost six months behind schedule and how that impact the rest of the project?


There have been a lot of lessons learned with this campaign. Anyone who has ever been through a large scale renovation has dealt with setbacks and changes that affect the timeline. Our project is no different.


Since we are looking to use ONE general contractor for the project, which will save money, we must wait until the church design plans are completed so the firms that have provided detailed bids for the Ministry Building can also provide them for the church and other components of the project. This will save time and money in the long run due to the cost of design changes once construction begins.


QUESTION:

Will there be more naming opportunities available for buildings/items in the church or on the grounds?


There will be more naming opportunities identified once we have more clarity on the full list of furnishings, iconography and other items needed and actual costs of these items. Whenever the information is available, we will be sure to communicate it to the parish. Keep in mind, those who have already donated will be given first choice on whether they would like their name attached to something.


Please send any questions or comments to the Arise & Build email HERE.


www.ariseandbuild.com

Meet the Arise & Build Team:

Interior Designer

 

Interior Design/Construction Team


Longtime parishioner, Julie Palios always dedicated her talents to the church – her talent being interior design. Today, she’s a design consultant on the Arise & Build Capital Campaign and works closely with the construction team to manage the interiors of the renovated buildings. This includes choosing everything from furniture and wall colors to flooring, door handles, baseboards and everything in between. Read more about Julie on our Meet the Team page of the Arise & Build website HERE.


Connect with Arise & Build


Send any questions or ideas to the

Arise & Build email HERE


Stop by our information table in the Kourmolis Center. Get materials, ask questions, volunteer, offer suggestions or donate. You can also click

HERE to donate!



www.ariseandbuild.com


Follow us on social media:

Facebook  Instagram  YouTube
 

Proistamenos: Rev. Fr. Stavros N. Akrotirianakis

Arise & Build Capital Campaign Chairman: Mike Xenick

Project Management Co-Chair: Ione Wilsmann

Project Management Co-Chair: Laura Holland

Construction Chairman: Rip Panos

Finance Chairman: Gary Ward

Marketing/Events Chairman: Nicole Mantzanas

IT/Media/Logistics Chairman: Miguel Pineiro, Jr.

Administration/Volunteers Chairman: Sandra Pappas

813-876-8830 (Office) | 813-443-4899 (Fax) | stjohntpa.org

Facebook  Instagram  YouTube