Aberdeen Ave Safety Improvement Project

Thank you for your continued interest in the Aberdeen Ave Safety Improvement Project. See below for key project updates.

Delay to Roadway Paving Schedule

We previously shared that installation would take place in Spring or Summer, following roadway paving. However, the paving schedule has changed.


Updated Paving Timeline

Roadway paving is now expected to occur in late Summer or Fall 2025.

Please note: This schedule is subject to change based on construction and weather conditions.


Impact on Installation

Installation will be delayed until paving has finished.


We’ll continue to share updates on the timeline.

Upcoming Information Session - Late Summer or Early Fall

We’re planning a community information session before installation begins to walk through the project updates. These include changes made in response to feedback we’ve heard since our Fall 2024 open house.


We'll be in touch soon with more information!


In the meantime, you can:

  • View the Fall 2024 project open house recording. This provides a refresher on what is planned for the project.
  • View the project plans. In May of 2025, we posted project plans for the whole street. This includes more detailed dimensions of proposed pavement markings and flex-posts.

Contact Us


Andreas Wolfe, (he/him)

Street Design Project Manager, Department of Transportation

617-349-9162

awolfe@cambridgema.gov

Accessibility Information

The City of Cambridge does not discriminate, including on the basis of disability. We may provide auxiliary aids and services, written materials in alternative formats, and reasonable modifications in policies and procedures to people with disabilities. For more information contact the Department of Transportation at tpt@cambridgema.gov, 617-349-4700 (voice), or via relay at 711.

City of Cambridge

Department of Transportation

Keep in Touch!

Facebook  X  Instagram