State & Lake Utility Relocations
On Monday, October 10, utility companies will start relocating utilities in advance of the State and Lake CTA project. Train services will not be disrupted during utility relocations.
At least 1 lane of traffic will remain open (1 lane each direction on State St) at all times, but other driving and parking lanes may be closed.
Construction equipment and materials will be stored on the street, including during time periods between active work. Work will primarily occur 9:00 AM to 4:00 PM weekdays and 8:00 AM to 8:00 PM on Saturdays, but there will be limited work during nights. Utility companies are aware of and required to abide by the Chicago noise ordinance, which limits noisy work in overnight hours.
Crane Lift: 6 South Clark Street
On Wednesday, October 12 at 8pm to Thursday, October 13 at 6am, there will be a crane lift at 6 South Clark Street. During the lift, Clark Street, between Madison and Monroe will be closed to vehicular and pedestrian access.
Crane Lift: 435 W Erie
On Friday, October 14 to Sunday, October 16 there will be a crane lift at 435 W Erie Street. During the lift, there will be a full closure of Erie, from Sedgwick to Hudson.
Crane Lift 311 W Huron
On Monday, October 17 to Wednesday, October 19, from 9am-5pm, there will be a crane lift at 311 W Huron Street. During the lift, vehicular and pedestrian traffic will be prohibited on Huron, from Franklin to Orleans.
Conduit/Street Light Pole Installation
Sunseys began installation on new conduit and street light pole in the sidewalk at 543-600 N Michigan Avenue. All work is expected to be completed by October 11, 2022.
Lumen
On Thursday, September 15, Lumen will began installing communication equipment on the south side of Kinzie, from Kingsbury to a pint 100' east there of.
This project is expected to be completed by November.
Randolph Street Viaduct Repair
CDOT restarted viaduct repairs on Randolph, between Columbus and Field. Work hours are Monday-Friday, from 8am-8pm.
Throughout the project, at least one lane of eastbound traffic will be open. Westbound lanes will not be disrupted.
The project is expedited to be completed mid-November (weather dependent).
150 E Ontario Construction
W.E. O'Neil began construction of a 23-story building at 150 East Ontario Street. Work hours will be Monday-Friday, from 9am-5pm (8pm during caisson pours). Some weekend work will occur.
Throughout the project, the following will be closed:
- 150' of sidewalk in front of 150 East Ontario
- 150' of curb lane in front of 150 East Ontario
Pedestrians will be directed to the sidewalk on the south side of the street at Ontario/Michigan and Ontario/St. Clair.
The entire project is expected to take 23 months to complete.
Filmings
Chicago Med
On Thursday, October 13, Chicago Med will be filming a car crash scene at Jefferson and Fulton. The scene includes vehicular stunts. During the filming, parking will be prohibited at the following locations:
- Both sides of Jefferson St from Lake St to 333 N Jefferson St (Dead End) (3am-3pm)
- Both sides of Fulton St from Clinton St to Desplaines St (3am-3pm)
- Both sides of Clinton St from Fulton St to Lake St (3am-3pm)
- North side of Lake St from Clinton St to Jefferson St (3am-3pm)
There will be full closures of the following streets:
- Jefferson St from Fulton to 333 N Jefferson St (Dead End) (3am-3pm)
- Fulton St from Clinton St to Desplaines St (3am-3pm)
- Jefferson St from Lake St to Fulton St (9am-3pm)
Additionally, there will be intermittent closures of the following streets:
- Alley from Jefferson St to Desplaines St, Fulton St to Lake St (9am-3pm)
- Alley from Jefferson St to Clinton St, Fulton St to Lake St (9am-3pm)
- Wayman St from Jefferson St to Desplaines St (9am-3pm)
If you have any questions or concerns, please contact Edward Eberwine III (location manager) at 312-841-7695.
Commercial Filming
On Wednesday, October 12 and Thursday, October 13 a commercial will be filmed inside Hotel Allegro located at 177 W Randolph. During the filming, parking at the following locations will be prohibited:
- North Side of Randolph from Wells to 188 W Randolph
- South Side of Randolph from Wells east 1⁄2 block
- East Side of Wells from Randolph to Washington
If you have any questions or concerns, please contact Gabrielle Roussos (location manager) at 310-339-3495.
Chase Tower Clark Street Tunnel Project
In mid-July, Berglund Construction began repairs on the Chase Tower Clark Street tunnel at 23 S. Clark Street. The project scope consists of repairing Chase’s below-grade tunnel structures that cross below Clark Street at 23 S. Clark St, and will require excavation of Clark Street in that area to access the tunnel structures to perform repairs.
There will be one lane of southbound traffic open at all times. Berglund will have flaggers and barricades in-place throughout the project.
The project will last 26 months. Berglund would like to begin mid-June. Work hours will be Monday-Friday, from 8am-5pm.
Demolition Notice: 535 N. St. Clair Street
Precision Excavation & Demolition (PED) was hired to demo the parking structure at 535 N St. Clair Street. Demolition will begin in November, and work hours will be Monday-Friday from 8am-5pm.
PED plans to install a high bay pedestrian canopy on the north side of Grand, from St. Clair to a point 100' east thereof. Additionally, they plan to prohibit parking on the north side of Grand, from St. Clair to a point 100' east thereof. Both the canopy and parking restrictions will be in-place throughout the project.
The sidewalk on the east side of St. Clair, from Grand to appoint 100' north thereof will be closed for the first week of the project. Construction fencing will be put in-pace between the sidewalk and the site.
PED plans to demo the building from west to east. They will have dust mitigation in-place and bait for rodents before work begins. All demolition activities will occur on their property. The crane will not be on ROW.
The entire demolition will take one month to complete.
Cassidy Tire Demolition
On Monday, May 9, McHugh Construction began demolition of Cassidy Tire located at 344/350 N. Canal Street. McHugh's contractor (Atlas) will demo the building from the back (south side) to the front (north side). The demolition is expected to last 2 months.
Immediately after the demolition is completed, construction of the 33-story mixed-use building will begin. During demolition and throughout construction, McHugh Constriction will occupy the curb lane on the west side of Canal along 344/350 N. Canal Street's property line. The construction company has leased the area north of the building from the railroad to use as a staging area. Additionally, they will use the parking lot south of the building as a staging area too.
As a reminder, this project is contributing to numerous public benefits. Click here for a list of public benefits, and stay tuned to Reilly Reports for future updates on this project and the implementation of these public benefits.
All work is expected to take 24 months to complete (weather dependent).
311 W Huron Project
In June, ARCO Murray began construction of a new building at 311 W. Huron Street. Work hours will be Monday-Friday, from 9am-5pm (8pm during caisson pours).
Throughout the project, the following City right-of-way will be occupied:
-
Sidewalk/curb lane on the south side of Huron, from Franklin west to the end of 311 W Huron's property line - approximately 150'. The sidewalk will be used to store their concrete pump, dumpster, and hoist dock. Trucks will back into the site at this location too. Jersey barriers will be placed in the curb lane to create a protected pedestrian path.
- 3' of the sidewalk on the west side of Franklin, from Huron to the first alley south thereof. This leaves 6' of clearance. They will need to push the fence out a few feet during excavation.
- 150' of the east/west alley bounded by Huron, Franklin, Erie, and Orleans will be closed. The closure is from Franklin to a point 150' west thereof.
The project is expected to be completed in September 2023 (weather dependent).
Peoples Gas Main Installation Project: Bellevue, from Lake Shore Drive to Rush
At the end of May 2022, Peoples Gas began installing a 900' gas main on the south side of Bellevue Place, from Inner Lake Shore Drive to Rush Street.
The main will be installed in sections of 150'. Once the gas main is installed, service lines will be connected from the new main to each building on the north side of the street.
This will require trenching from the south to north side of the street. All work is expected to be completed in mid-September (weather dependent). Curb-to-curb restoration will occur in October.
Millennium Park Music Festivals
The Department of Cultural Affairs and Special Events (DCASE) announced the return of the following free summer music festivals in Millennium Park:
- Chicago Jazz Festival (citywide and in Millennium Park including Jay Pritzker Pavilion): Thursday – Sunday, September 1–4
- Chicago House Music Festival and Conference (Jay Pritzker Pavilion in Millennium Park): Friday, September 16
- World Music Festival Chicago (citywide): Friday, September 30 – Sunday, October 2
Gas Main Replacement - Michigan, Monroe to Lake
On Monday, February 7, Peoples Gas began a gas main replacement on the west side of Michigan Avenue, from Monroe to Lake. Work hours will be 9am-4pm. This project is expected to be completed in August 2022 (weather dependent).
214 West Erie Street Renovations
On Monday, December 13, Crane Construction began renovations of 214 West Erie Street. During construction, the following will be closed:
-
Sidewalk/curb lane in front of 214 West Erie Street. The curb lane will be used as a pedestrian walkway. Crane Construction will place jersey barriers and ramps in the curb lane to protect pedestrians and provide wheelchair access.
-
Close 100' of the north/south alley adjacent to 214 W Erie Street. This is a T alley and residents of 222 W Erie will still be able to access their parking garage from the alley entrance on Franklin and Huron.
This project is expected to be completed summer of 2022 (weather dependent).
LG Construction: 751 N. Hudson and 451 W Chicago
LG Construction has recently broken ground at 751 N. Hudson Avenue and 451 W. Chicago Avenue, which are adjacent parcels. Work hours will be 8am-5pm, Monday-Friday.
Throughout the project, the following will be closed:
- Sidewalk/curb lane/traffic lane of the east side of Hudson, from Chicago to the first alley south thereof
- Sidewalk/curb lane/traffic lane on the west side of Sedgwick, from Chicago to the first alley south thereof
- Sidewalk/curb lane on the south side of Chicago, from Hudson to Sedgwick
There will be a protected pedestrian walkway in the curb lane on the south side of Chicago Avenue, from Hudson Avenue to Sedgwick Street.
This project is expected to take 18 months to complete (weather dependent).
354 North Union Construction
The Onni Group is constructing a 33-story residential building with 373 units. Work hours will be 8am-8pm, daily.
Parking will be prohibited on North Union, from West Kinzie to the cul-de-sac west thereof throughout the project. All construction equipment and vehicles will be staged on the Onni Group’s property. This project will take approximately two years to complete.
430 N. Michigan Lobby Renovation
In September 2021, GNP Realty Partners began renovating the lobby at 430 N. Michigan Avenue. Throughout the project, there will be a 40’ urban canopy on the sidewalk in front of the building. In order to place the canopy on the sidewalk, the planter bed and City Information Panel (CIP) at this location will be temporarily removed. Both the planter bed and CIP will be reinstalled upon completion of the project. The project is expected to be completed in July 2022.
Overnight Closure: Lake Shore Drive Bridge
CDOT has identified Lake Shore Drive Bridge adjustments that need to be made. This project will occur during the overnight hours to accommodate weekly boat runs during the day. This work will occur on Mondays and Thursdays beginning June 9. The project is expected to be completed in early August.
Upper Lake Shore Drive will be closed from Illinois Street to Monroe Street and Lower Lake Shore Drive will be closed from Grand Ave. to Lower Wacker Drive.
Detour Route:
Southbound traffic will be directed off onto westbound Grand Ave., to southbound Columbus Ave., to eastbound Monroe St. and back to LSD. Northbound traffic will be directed off at westbound Monroe St., to northbound Columbus Ave., to eastbound Illinois St. and back to LSD.
Dearborn Street Bridge Project
CDOT has scheduled emergency work on the Dearborn Bridge to begin June 13 (weather dependent). They will be conducting the following work:
- Replacing both sidewalks
- Replacing all of the bridge gratings
- Replacing the beam structures
The project is expected to be completed in December 2022 (weather dependent).
The bridge will be reduced to one lane of traffic/sidewalk at a time. Bike traffic will be detoured to Clark Street via the north side of Upper Wacker Drive.
|