Filming
Christy Schmid Productions
On Saturday, November 18 to Monday, November 20, Christy Schmid Productions, LLC will be filming scenes for an upcoming television series inside 325 North Wells Street. During the filming, parking at the following locations will be prohibited:
- Both Sides of Wells from Kinzie to Hubbard
- Both Sides of Lower Carroll from Wells to 150 W Carroll
- NORTH Side of Kinzie from Wells to LaSalle St
If you have any questions or concerns, please contact Ben Miner (location manager) at 574-707-5255.
Helicopter Lift: 225 N Wabash
On Saturday, December 2, there will be a helicopter lift at 225 N Wabash Avenue. During the lift, pedestrian and vehicular access will be prohibited at the following locations:
- North Wabash, from Wacker Drive to Lake Street.
- Wacker Place, form Garland to State
CDOT Construction: Pin & Link Plate Assembly and Expansion Joints
The Department of Transportation will begin a project to replace pin and link plate assemblies and expansion joints associated with the bridge structures of upper and intermediate Columbus Dr., Randolph St., and Stetson Ave. Pin and link plate assembly work will be performed from the underside of the bridge decks while expansion joint replacements will occur from above. The work is anticipated to begin on Monday, November 13th, 2023 and progress to completion (anticipated Fall 2024).
Work is to start along upper, intermediate, and lower levels of the following roadways:
- N. Columbus Drive between E. Wacker Drive and E. Randolph Street
- E. Randolph Street between N. Michigan Avenue and N. Field Boulevard
- N. Stetson Avenue between E. Wacker Drive and E. Lake Street
During construction, portions of these bridge structures will be barricaded off to prohibit vehicles and pedestrians directly over the active work.
- Vehicles will be shifted and/or detoured to allow the work to progress.
- The sidewalk on at least one side of the roadway and crosswalks at roadway intersections will remain open for pedestrians.
- Coordination of temporary access restriction may be required with private properties directly adjacent to the project.
Helicopter Lift: 57 E Delaware
Midwest Helicopter was hired by 57 E Delaware to lift HVAC units onto their roof. The lift will occur on Sunday, November 19, from 9am to 11am. During the lift, the following will be closed to vehicular and pedestrian access:
- Delaware, from State to Ernst Ct.
- Wabash, from Chestnut to Delaware
- Rush, from Chestnut to Walton
Street Resurfacing
The following resurfacing projects will begin at the beginning of November 2023:
- New Street, between East North Water and East Illinois
- New Street, between East North Water and River Drive
- River Drive, between North New Street and North McClurg Court
- McClurg Court, between River Drive and East North Water
- Huron, between Hudson and Sedgwick
- Erie, between Hudson and Sedgwick
Crews will grind away the top layer of asphalt first and return within two weeks to install new asphalt. The entire process can take 3 weeks to complete (weather dependent).
Canal Street Viaduct Project:
The Chicago Department of Transportation (CDOT) is performing viaduct repairs on Canal Street, between Jackson and Adams.
Vehicle access is prohibited to this stretch of Canal Street throughout the project. Since the viaduct is over Metra/Amtrack train tracks, this project is required to be conducted during the overnight hours.
The project is expected to be completed by early 2025.
PGL River North Project
Peoples Gas began a gas main project in River North. PGL will be working at the following locations:
- Franklin, from Huron to Chicago
- Superior, from Wells to Orleans
- Chicago, from Orleans to LaSalle
The project will be completed at the end of 2023.
Murphy Auditorium Renovation
Driehaus Museum purchased the Murphy Auditorium (50 E Erie) in June 2023, and began the following interior renovations:
- Offices are going to be renovated
- Stage has sunken – leveled out; fix accessibility issue
- New elevator to go all the way to the top floor
Throughout the project, the following will be in-place:
- Pedestrian canopy over the sidewalk in front of 50 E Erie
- 100' of curb lane will be closed in front of 50 E Erie for material deliveries and small crane
They will need to use a small crane periodically throughout the project to lift materials onto the roof that can't fit through the doorway.
** Crane lift planned on Tuesday, Oct 31 and Wednesday, Nov 1 (backup Thu Nov 2) from 9am to 4pm. While the lift is occurring, vehicular access to East Erie, between North Wabash and North Rush. The cane will remain up overnight. That said, the outriggers will be pulled in to allow for one lane of eastbound traffic.
Water Main project: Superior, from Orleans to Kingsbury
In Mid-October 2023, the Chicago Department of Water Management (DWM) began a water main project on West Superior Street, between North Orleans Street and North Kingsbury Street. This project will be completed in three phases.
Phase 1 will include prep work, utility locating, tree trimming, and infrastructure trenching. The trenching will begin at West Superior and North Kingsbury and move eastward.
DWM is coordinating all water shut offs with each affected building property managers. Work hours will be 7:30am to 7:00pm, Monday through Friday. All work is expected to be completed by the end of February 2024 (weather dependent). If you have any questions related to this project, please contact Bobby Lyons (project manager) at 773-724-1594 or John Bania (site foreman) at 773-663-8648.
LSD Bridge & Viaduct Project - September 25 to Summer 2024
The Chicago Department of Transportation (CDOT) began working on the Lake Shore Drive Bridge and Viaduct Network between Monroe and Ontario. This work will include removing and replacing link plates, stainless steel pins, and Teflon bushings and expansion joint rehabilitation.
Upper Level Lake Shore Drive will have one permanent lane closure in each direction and an additional lane closure during off-peak hours.
Intermediate Level Lake Shore Drive will have two permanent lane closures in each direction.
This project is expected to be completed summer of 2024.
Temporary Bus Stop Elimination
Until March 2024, the westbound bus stop at Grand and St. Clair will be temporarily removed.
- Stop ID Number: 761
- Route Stopping: #29 – State, #65 – Grand, #120 – Ogilvie/Streeterville Express, #121 – Union/Streeterville Express
State & Lake Utility Relocations
Utility companies began relocating utilities in advance of the State and Lake CTA project. Train services will not be disrupted during utility relocations.
At least 1 lane of traffic will remain open (1 lane each direction on State St) at all times, but other driving and parking lanes may be closed.
Construction equipment and materials will be stored on the street, including during time periods between active work. Work will primarily occur 9:00 AM to 4:00 PM on weekdays and 8:00 AM to 8:00 PM on Saturdays, but there will be limited work during nights. Utility companies are aware of and required to abide by the Chicago noise ordinance, which limits noisy work during overnight hours.
150 E Ontario Construction
W.E. O'Neil began construction of a 23-story building at 150 East Ontario Street. Work hours will be Monday-Friday, from 9am-5pm (8pm during caisson pours). Some weekend work will occur.
Throughout the project, the following will be closed:
- 150' of sidewalk in front of 150 East Ontario
- 150' of curb lane in front of 150 East Ontario
Pedestrians will be directed to the sidewalk on the south side of the street at Ontario/Michigan and Ontario/St. Clair. The entire project is expected to take 23 months to complete.
Street Sweeping
During street sweeping season (April 1 to mid-November) the Chicago Department of Streets and Sanitation uses mechanical street sweepers to remove debris and litter from streets, weather permitting. Throughout the season, DSS deploys mechanical street sweepers at regularly scheduled times to clear debris from Chicago streets. Starting this week, dozens of street sweepers have begun clearing the debris and leaves that have accumulated during winter months on both residential and arterial streets.
On weekdays, from 9am to 2pm, this Sweeper Tracker map will show real-time locations of city street sweepers. For more information, please review the 42nd Ward Map and street sweeping schedule. Residents can also call 311 to find the dates and locations of street sweeping in their area.
Please check for the bright orange signs announcing temporary parking restrictions. These signs are posted two days prior to scheduled street sweeping events. Some streets also have permanently posted signs that specify a once-per-week period when parking is prohibited for street sweeping.
Kennedy Expressway Bridge Rehabilitation
In 2023, IDOT began rehabilitating the Kennedy Expressway (Interstate 90/94), from the Edens Expressway (I-94) junction to Ohio Street.
The estimated $150 million project consists of rehabilitating 36 bridges and the Reversible Lane Access Control system, replacing overhead sign structures, installing new signage and modernized LED lights, pavement patching, and structural painting. Additionally, Hubbard’s Cave, from Grand Avenue to Wayman Street, will be painted and new LED lighting installed.
The work will take place over three consecutive construction seasons, broken down into the following stages:
-
2023 – Inbound Kennedy: Click here for stage 1 fact sheet.
-
2024 – Reversible Express Lanes: Click here for stage 2 fact sheet.
-
2025 – Outbound Kennedy: Click here for stage 3 fact sheet.
The Kennedy Expressway officially opened in November 1960, with the last major rehabilitation completed in 1994. The project will improve safety, traffic flow and reliability for the more than 275,000 motorists who use the expressway each day.
Click here for a project overview.
Click here for a FAQ
Click here to see photos and videos of the project.
|