Algonquin Construction Updates
September 3, 2026
| | High Hill Sanitary Sewer Relocation - Phase I | | |
Project Overview:
The Village of Algonquin is moving forward with Phase 1 of the High Hill Sanitary Sewer Relocation Project, an important infrastructure improvement located along Ratt Creek between Kirkland Drive and Hanson Road, within and adjacent to High Hill Park Nature Preserve. This project involves replacing an aging sanitary sewer with a new, larger sewer relocated out of environmentally sensitive wetlands. The improvements will increase system reliability, reduce maintenance challenges, protect the environment, and provide capacity for future growth.
Project Update:
All landscaping restoration is complete, and the multi-use path is now open. The project is substantially complete, with any remaining punch list items to be addressed in spring/summer 2027.
| | |
Contact Information:
Raz Calin, Capital Project Manager, Engineer III
Village of Algonquin
847-658-1239 / RazCalin@algonquin.org
| | Willoughby Farms Rehabilitation - Section 3 | | |
Project Overview:
The Village began the Willoughby Farms Subdivision Rehabilitation – Section 3 project in spring 2026, with anticipated completion by fall 2026. The project focuses on roadway rehabilitation and base stabilization along the through streets and resurfacing in the cul-de-sacs, pedestrian accessibility improvements, water system reliability upgrades, and drainage enhancements to extend the service life of existing infrastructure within the subdivision.
Project Update:
Crews are nearing completion of watermain infrastructure improvements on Notting Hill Road. Over the past two weeks, crews milled, cement-stabilized, and paved roadways south of Notting Hill with binder. Over the next two weeks, crews will complete the remaining watermain and storm sewer upgrades on Notting Hill, while the concrete crew will begin removing and replacing concrete. Landscaping crews will also continue restoration work throughout the subdivision.
| | |
Contact Information:
Ahren J. Ludwig, Construction Technician III
Christopher B. Burke Engineering, Ltd.
847- 823-0500 / Email: aludwig@cbbel.com
| | Willoughby Farms Park Reconstruction | | |
Project Overview:
The Village of Algonquin began the Willoughby Farms Park Renovation Project in summer 2026, with completion anticipated by spring 2027, weather permitting. This project includes the complete renovation and reconstruction of one of the Village’s larger public parks located within the Willoughby Farms Subdivision, just northwest of Westfield Community School. The improvements will modernize park amenities, expand recreational opportunities, and enhance accessibility to better serve current residents and anticipated growth in the surrounding area.
Project Update:
Tree removal, tree protection installation, and silt fence installation are complete. The team also removed the existing chain-link fencing around the baseball field and basketball court. Demolition of the existing basketball court is currently underway. Additional site demolition activities will continue, including topsoil stripping and delivery and storage of playground equipment over the next two weeks as the project moves into the next phase of construction.
To Learn More:
www.algonquin.org/willoughbypark
| | |
Contact Information:
Raz Calin, Capital Project Manager, Engineer III
Village of Algonquin
847-658-1239 / Email: RazCalin@algonquin.org
| |
Gaslight Terrace North Subdivision Improvements -
Pavement Management Program
| | |
Project Overview:
The Village of Algonquin will complete roadway improvements within the Gaslight Terrace North Subdivision as part of the 2026 Pavement Management Program. The project includes resurfacing selected neighborhood streets north of Edgewood Drive and east of Hanson Road. Approximately 1.25 miles of roadway are anticipated to be improved, with final limits subject to field conditions and construction coordination. The Village’s State allotment of Motor Fuel Tax (MFT) funds will be used to complete this project.
Project Update:
Paving of HMA surface patches on the southeast side of the Village is complete. Remaining HMA surface patches on the northeast side of the Village, along with bike path reconstruction at Spella Park, are scheduled for the second week of September.
To Learn More:
https://www.algonquin.org/egov/apps/document/center.egov?view=item&id=13184
| | |
Contact Information:
Raz Calin, Capital Project Manager, Engineer III
Village of Algonquin
847-658-1239 / Email: RazCalin@algonquin.org
| | |
Project Overview:
The Boyer Road Improvements Project is a comprehensive corridor improvement effort scheduled to begin in late summer 2026 and to be completed by summer 2027, weather permitting. The project will improve roadway and rideability conditions, enhance pedestrian and bicycle connectivity, upgrade underground utilities, and improve safety and reliability along Boyer Road.
Project Update:
ComEd continues relocating utility poles and overhead lines south of County Line Road to provide the necessary clearance for the proposed water main and multi-use path. Pole relocations are expected to continue for the next two weeks. Berger Excavating is anticipated to install traffic-control signage and begin mobilizing for construction in mid-September.
To Learn More:
https://www.algonquin.org/egov/apps/document/center.egov?view=item&id=13133
| | |
Contact Information:
Cliff Ganek, P.E.
Deputy Director of Public Works/Village Engineer
847-658-2700 | Email: CliftonGanek@algonquin.org
| | Algonquin Shores Lift Station Project | | |
Project Overview:
The Algonquin Shores Lift Station Project is the first phase of a two-phase infrastructure improvement initiative designed to enhance the reliability and efficiency of the Village’s wastewater system. The project includes replacing the remaining 6-inch force main with a new 10-inch force main to improve system capacity and flow, while addressing aging infrastructure identified during the Souwanas Trail improvements. These upgrades will strengthen the overall system and help reduce the potential for future service disruptions.
Project Update:
Fence installation outside the station is complete, along with interior painting and piping insulation. Paving outside the station is complete, and landscaping restoration is expected to be completed during the first week of September.
To Learn More:
www.algonquin.org/construction
| | |
Contact Information:
Lindsay Muth, Project Manager
Trotter & Associates, Inc.
331-725-6139 | l.muth@trotter-inc.com