This is a question that Father Stavros and many of the Arise & Build team have been asked repeatedly - so here is some clarification about the order of the construction:
When the church expansion construction commences, the church sanctuary will move into the Kourmolis Center for one year. The Kourmolis Center will become the worship space for the duration of the church renovation. In other words, the Kourmolis Center will become our church. The altar, the pews, the icons, everything in the church will be relocated to the Kourmolis Center. Just like we don’t do anything else in our church sanctuary other than worship, during the period that the Kourmolis Center serves as our place of worship, nothing else will take place in there other than worshipping
The Zaharias Room will become a temporary storage room for church supplies, which means there will be no meeting space for the choir, Philoptochos, AHEPA, daughters, Sunday School music class and anyone else who utilizes the Zaharias Room. Again, there will be no functions other than worship in the Kourmolis Center while it serves as a church. So, that means no room for Bible study, luncheons, coffee hour, fellowship, or church festival in the Kourmolis Center. We will also lose parking around the front and the side of the church because it will be a construction zone.
The Ministry Building is being renovated first so that there will be space for fellowship and ministry while we don’t have the Kourmolis Center at our disposal. The Tuesday night Bible study, as an example, has about 30 people. The new small hall in the ministry building will be enough to accommodate this ministry. There will also be space available for coffee hour each Sunday, and a small warming kitchen to assist in providing a place for food to be set up and served. We will not be breaking down the church set up in the Kourmolis Center for any reason. If there is a luncheon, it will be held in the Ministry Building. If there is a festival during the church renovation, it will NOT be held in the Kourmolis Center.
Another reason why the Ministry Building is first is, quite simply, parking. The church administration offices will be moved into the Ministry Building. When the work begins on the church, there will be a construction zone around the front and side of the church. Doing the Ministry Building first allows us to knock down the current administration building and create temporary parking, which will help make up for what we will lose in the construction zone around the church. If we did the church expansion first, there would be no place for fellowship, and extremely limited parking, for a year. And that would not be healthy for the life of the community.
The most important thing we do here is worship Christ. The most important thing we have on this property is the tabernacle on the altar, which contains His Body and Blood. He sits on His glorious throne, the holy altar table. We honor Christ. We worship Christ. Our community, I believe, enjoys all of its success because of God’s amazing grace, given to us because we honor Christ. When we move the church to the hall, the tabernacle will be placed on the altar, right underneath the basketball hoop in front of the stage. Christ will be enthroned there, and we won’t move Him until the church is complete. We won’t move Him for a coffee hour, a basketball game, a festival, or anything else. Because He is the most important part of our community and nothing will change that.
|