Featured in the Ashburn District
Monthly Wrap-Up Flyer
| |
Proposed Transmission Line Projects
-
Proposed Transmission Line Project: Aspen to Golden (Scroll Down for More Information)
| | | |
Loudoun County and Virginia News
| | | |
Upcoming Opportunities &
Community Engagement
| | | |
Comprehensive Plan Amendments & Zoning Ordinance Amendments | |
-
Comprehensive Plan Amendment to Remove the planned Gloucester Parkway Extension from the Countywide Transportation Plan (CTP) CPAM-2024-0006 (Scroll Down for More Information) Update
| | | |
Legislative Applications for Development | |
Significant By-Right Developments | |   |
The link for this edition of the Ashburn District Flyer can be found under today's date, which is located above the table of contents. | |   |
From the Office of the Ashburn Supervisor | |
|
Ashburn/Lansdowne Friends and Families,
There are simply no words to express our profound grief and shock over the tragic loss of several Loudoun County family and community members in last Wednesday’s air disaster. I’ve attended two events, one at the Ashburn Ice House used frequently by all of the skaters and their families, and one at Leesburg’s ION skating facility, another top skating venue. At this unbearably difficult time, each of us must remember to take care of ourselves and those around us, seek help when needed and offer help when able. If you would like to donate in support of the families affected and our first-responders, here is a link to the DCA Together Relief Fund. The Community Foundation has established this single point of giving to help ensure your donations are used properly.
Our hearts are heavy at this painful time, but we remain as one in remembering the joy and love we’ve shared with those lost.
Mike Turner
Ashburn District Supervisor
Vice Chair | Loudoun County Board of Supervisors
| |
Loudoun County Statement Regarding Airline Crash at National Airport | |
The Loudoun County Board of Supervisors, the county’s first responders, and county staff join our community and regional partners in expressing our deepest condolences to those impacted by the tragic crash involving American Eagle Flight 5342 and an Army Black Hawk helicopter near Reagan National Airport Wednesday evening. Our thoughts are with families, coworkers and friends of the victims’ families, military personnel, and the airline community who have experienced tremendous loss.
“On behalf of the Board of Supervisors and residents of Loudoun County, I offer heartfelt condolences and prayers to the families and loved ones of flight 5342,” said Board of Supervisors Chair At-Large Phyllis J. Randall. “We thank the first responders from Loudoun and across the Washington metro area for the heroic acts during this tragic incident.”
The county is aware that published reports have identified members of the Loudoun community as among the passengers on the plane. The county recognizes that this heartbreaking incident has impacted our friends and neighbors. We offer our sympathy to the Loudoun figure skating community. We join you in your grief as we wait for more information about the victims and the investigation into the cause of the crash.

“I join Chair Randall in expressing my most heartfelt condolences to the families of those lost in this tragedy, some of whom live here in Loudoun,” added Vice Chair and Ashburn District Supervisor Michael R. Turner. “Our entire community stands with them in this painful hour.”
The Board also expresses its sincere gratitude to all of the region’s first responders involved in the incident. We thank the Loudoun County Sheriff’s Office and Loudoun County Combined Fire and Rescue System who have supported our regional partners by providing relief staffing. Loudoun County’s public safety agencies and emergency management personnel have been engaged with state and regional entities to offer any mutual aid that is necessary to support the ongoing response near Reagan National Airport.
| | | |
Proposed Transmission Line Projects | |
|
The SCC has not made a final decision on Aspen-Golden Line.
The SCC Examiner recommended to the SCC on November 1, 2024, to approve of the Aspen-Golden transmission line without any portion being undergrounded.
Click here to access the PDF of the SCC’s Hearing Examiner’s recommendation from 11/01/2024.
Status remain the same since the 01/09/2025 Newsletter:
The county responded to the SCC Hearing Examiner’s Report. Here is a short summary of the county’s rebuttal. The rebuttal can be accessed here, the following summary is from page 33 of the PDF.
Undergrounding Aspen-Golden along as much of Route 7 as possible will not only conform with the County’s 2019 General Plan, preserve the Belmont Viewshed Easement, promote economic development, minimize adverse impacts to the extent reasonably practicable, and be responsive to public opinion. It will also educate the Company, the County, the Commission, and all of us, about the technical and logistical aspects of undergrounding, so that we do not look back on these proceedings ten years from now, throttled by criss-crossing transmission lines, wondering what could have been.
Background:  Dominion Energy has developed proposals for a project named “Aspen to Golden,” a potential transmission route that calls for the construction of new transmission lines that will run from a future Leesburg substation (Aspen) to a future Ashburn substation, near Loudoun County Parkway (Golden). During their virtual and in-person meetings on January 9, 2024, and January 11, 2024, Dominion announced updated proposed routes along Route 7 and Loudoun County Parkway. To view a picture of the proposed routes for Aspen to Golden, click here. For an interactive map of the proposed routes, click here, scroll down and click "Continue as guest".
Stay Informed:
-
General information landing page for Dominion’s NOVA projects: dominionenergy.com/nova
-
“GeoVoice,” an interactive mapping tool that gives members of the public the ability to review and provide feedback on Dominion’s proposed project routes: geovoice.com/dominion/LoudounCounty
-
“NOVA Virtual Open House,” an interactive website that includes information about all of Dominion’s transmission route plans for Loudoun County: engage.com/novareliability
Contact Dominion Energy:
Dominion Energy has provided the following contact information for questions:
| | | |
It's Electric! New Battery Electric Buses Join Loudoun County Transit Fleet | The buses will be available for Local Bus Service routes. | | | |
Loudoun Board Reduces Motor Vehicle Licensing Fee to Zero | The Loudoun County Board of Supervisors voted on January 22, 2025, to reduce from $25 to zero the annual licensing fee for motor vehicles, motorcycles and trucks located in the county. | | | |
Supplemental Real Estate and Personal Property Tax Deadline is February 5 | Loudoun County Treasurer Henry C. Eickelberg reminds taxpayers that the deadline for payment of supplemental real estate and personal property taxes is Wednesday, February 5, 2025. | | | |
2024 Loudoun County Animal Services Infographic | |
Upcoming Opportunities & Community Engagement | |
Loudoun Offers Mental Health Education & Substance Abuse Prevention Trainings in February | |
Classes are free; most require registration.
For more information on the prevention and intervention services offered by the Loudoun County Department of Mental Health, Substance Abuse and Developmental Services, visit loudoun.gov/MHSADSPrevention or send an email.
| | | |
Loudoun County Schedules Grant Application Training Series | Loudoun County is hosting a virtual Grant Application Training Series designed to help organizations seeking grants learn how to craft successful grant applications. | | | |
|
Loudoun Symphony Orchestra Presents Tchaikovsky with David Kim
Sunday, February 16, 2025
3:00 PM - Lightridge High School, Aldie
Violinist David Kim, concertmaster of the Philadelphia Orchestra, joins the LSO to perform Tchaikovsky’s Violin Concerto. He started playing violin at the age of three, began studies with the famed pedagogue Dorothy DeLay at the age of eight and later received his bachelor’s and master’s degrees from the Julliard School. The concert also includes the Sibelius Symphony No. 1 and the joyous Carnival Overture. Visit www.loudounsymphony.org for details and tickets.
| |
|
A Message from Visit Loudoun:
Visit Loudoun Tourism Survey

Please take a few minutes to complete our survey on tourism in Loudoun County. It’s open to residents, business owners, past visitors and those considering a visit. All responses are anonymous and at the end of the survey, participants will have a chance to enter to win gift certificates to Loudoun tourism businesses.
Link to Survey: https://www.surveymonkey.com/r/LCVATourism
Visit Loudoun Strategic Planning Sessions
Visit Loudoun is developing its next three-year strategic plan, effective July 1, 2025, and your input is essential. As Loudoun County's destination marketing organization (DMO), Visit Loudoun is dedicated to promoting the region and its towns to attract visitors, drive economic growth and enhance the community’s quality of life. These strategic planning sessions are a critical part of shaping our future priorities and objectives. We’re seeking feedback from tourism and hospitality industry stakeholders like you to help define the vision for Loudoun’s tourism landscape.
Each session is organized by industry segment. Please select the session that best matches your business and register accordingly. If your designated session time isn’t convenient, feel free to register for one of the open sessions. Attendance is required for only one session, but please note that space is limited.
Monday, March 3
Location: Walsh Family Wine - 16031 Hillsboro Rd, Purcellville, VA 20132
Tuesday, March 4
Location: Kimley-Horn Loudoun - 19775 Belmont Executive Plaza Suite 250, Ashburn, VA 20147
| |
Comprehensive Plan Amendments & Zoning Ordinance Amendments | |   |
|
The Loudoun County Board has the authority to make changes to the 2019 Comprehensive Plan and the Loudoun County Zoning Ordinance through a Comprehensive Plan Amendment (CPAM) and a Zoning Ordinance Amendment (ZOAM) process.
The Zoning Ordinance regulates land use throughout the county and is the primary implementation tool for the 2019 Comprehensive Plan, a policy document that provides a flexible framework and implementation strategy to meet the county’s future land use and transportation needs. Although CPAMs and ZOAMs are frequently undertaken together, not every project requires both.
The priority for this section is to provide our constituents with up-to-date information about any Board initiated CPAMs and ZOAMs that will impact the Ashburn District
|  
|   |
Comprehensive Plan Amendment to Remove the Planned Gloucester Parkway Extension from the CTP
CPAM-2024-0006
| |
Description: During the January 10th, 2024 Board of Supervisors Public Hearing, a motion was made by Supervisor Turner, and supported by the Board of Supervisors, that directed county staff to initiate and prepare a Comprehensive Plan Amendment to remove the planned Gloucester Parkway extension from the Countywide Transportation Plan (CTP). This planned extension requires construction of a bridge over the Goose Creek to connect Gloucester Parkway to Crosstrail Boulevard.
New Update: The Gloucester Parkway CPAM will be coming to the March 4, 2025 Board of Supervisors Business Meeting.
-
Previous Update: Estimated completion is Spring 2025.
-
Previous Update: The proposed amendment will be referred to the Planning Commission for a future public hearing.
|  
| | |
LandMARC Progress Updates | |
|
On August 14, 2023, Loudoun County launched LandMARC (Land Management, Applications, Research, Coordination). LandMARC is the county's online land management system. More information about LandMARC can be found here.
Stay Informed
Beginning September 26, 2023 there will continue to be twice-weekly updates to share the progress in processing permits. These updates will be posted online at Loudoun.gov/bdpermits. The link to this information is also posted in the LandMARC self-service portal. Loudoun.gov/LandMARC remains the landing page for all industry to get information about the system, including system status, help and how-to guides, and read important updates on the LandMARC blog.
| | | |
Legislative Applications for Development in the Ashburn District | |
Luck Stone Leesburg Plant
Application Number LEGI-2023-0084
| |
Description: "Luck Stone Leesburg Plant" is a Zoning Concept Plan Amendment (ZCPA) Application to amend proffers and development conditions to allow for expansion of mining operation in quarry B, on the east side of Goose Creek, underneath the current processing plant, resulting in the processing plant and point of sale to move to the west side of the property. On the west side of Goose Creek, the application is amending the development conditions to allow for Stonewater Lane to be used for shipping mined materials off-site and to rezone a portion of Luck Stone’s property to allow for data center uses. According to Luck Stone, if this application is approved, the timing of the relocation of the point of sale to Stonewater Lane and the expansion of mining operations in quarry B is subject to several variables but is not currently anticipated for approximately 25 years.
Status remains the same since the 05/23/2023 Newsletter: County staff from multiple departments are reviewing this application with the applicant.
For more information on this application, click here. To review the application documents, scroll down to the middle of the page and click the “Attachments” tab. To leave a public comment for county staff, click here. Supervisor Turner also invites you to share your thoughts and opinions about this application with him via email at mike.turner@loudoun.gov.
| | | |
Belmont Cove Rezoning
Application Number: LEGI-2023-0074
| |
Description: “Belmont Cove” is a Zoning Map Amendment application to rezone 8 acres to allow for the construction of 80 multifamily residential units. The residents are currently zoned to Newton-Lee Elementary School, Belmont Ridge Middle School, and Riverside High School.
New Update: The Planning Commission has forwarded this application to a future Planning Commission Work Session.
-
Previous Update: This application is scheduled to come to the January 28, 2025, Planning Commission Public Hearing.
-
Previous Update: This application has been removed from the July 30, 2024, Planning Commission Public Hearing schedule, and another date has yet to be determined.
-
Previous Update: This application is scheduled to come to the July 30, 2024 Planning Commission Public Hearing.
-
Previous Update: County staff from multiple departments are reviewing this application with the applicant.
For more information on this application, click here. To review the application documents, scroll down to the middle of the page and click the “Attachments” tab. To leave a public comment for county staff, click here. Supervisor Turner also invites you to share your thoughts and opinions about this application with him via email at mike.turner@loudoun.gov.
| | | |
|
Description: "Century Corner at Goose Creek Village" is an application to amend the concept plan and proffers from a previously approved application (ZMAP-2015-0008) to increase the maximum number of Independent Living (IL) units permitted to be developed from 80 to 120 units (40 additional units) on the Property.
Status Remains the Same as the 01/21/2025 Newsletter: At the January 15, 2025, Board of Supervisors Public Hearing, the Board voted to send this application to the February 4, 2025 Board of Supervisors Business Meeting.
-
Previous Update: At the November 26, 2024, Planning Commission Public Hearing, the Planning Commission voted to send this application to the January 15, 2025, Board of Supervisors Public Hearing.
-
Previous Update: This application is scheduled to come to the November 26th Planning Commission Public Hearing.
-
Previous Update: County staff from multiple departments are reviewing this application with the applicant.
For more information on this application, click here. To review the application documents, scroll down to the middle of the page and click the “Attachments” tab. To leave a public comment for county staff, click here. Supervisor Turner also invites you to share your thoughts and opinions about this application with him via email at mike.turner@loudoun.gov.
| | | |
West Belmont
Application Number: LEGI-2024-0018
| |
Description: "West Belmont" is an application to rezone approximately 27 acres to allow for development of approximately 367 residential units and 11,000 square feet of retail.
Status remains the same since the 07/02/2024 Newsletter: County staff from multiple departments are reviewing this application with the applicant.
For more information on this application, click here. To review the application documents, scroll down to the middle of the page and click the “Attachments” tab. To leave a public comment for county staff, click here. Supervisor Turner also invites you to share your thoughts and opinions about this application with him via email at mike.turner@loudoun.gov.
| | | |
National Conference Center Residential
Application Number: LEGI-2024-0024
| |
Description: "National Conference Center Residential" is an application for a Zoning Map Amendment of 46.62 acres to (Suburban Compact Neighborhood-8) SCN-8 (36.42 acres) and (Suburban Compact Neighborhood-16) SCN-16 (10.20 acres) to introduce a mix of single-family detached, single-family attached, and multifamily attached dwellings.
Status remains the same since the 07/02/2024 Newsletter: County staff from multiple departments are reviewing this application with the applicant.
For more information on this application, click here. To review the application documents, scroll down to the middle of the page and click the “Attachments” tab. To leave a public comment for county staff, click here. Supervisor Turner also invites you to share your thoughts and opinions about this application with him via email at mike.turner@loudoun.gov.
| | | |
Northstar Square
Application Number: LEGI-2023-0020
(Formerly known as "Mercer Crossing")
| |
Description: "Northstar Square” is a proposed application to rezone 110.86 acres to allow the construction of 1,138 dwelling units. These include 297 single-family attached units, 485 multi-family stacked units, and 356 multi-family attached units. The residents are currently zoned to Newton-Lee Elementary School, Belmont Ridge Middle School, and Riverside High School.
Status remains the same since the 07/02/2024 Newsletter: The applicant has sent an update to the county that they are sending “an updated Land Development Application”.
-
Previous Update: The Northstar Square rezoning application was removed from the September 13th (2023) BOS Public Hearing agenda, by the developer. The developer has indefinitely deferred this application.
-
Please see the application for this parcel in the “Significant By-Right Developments in the Ashburn District” section below, under the application titled "Belmont Landbay KK Data Center."
-
Previous Update: At the June 8th (2023) Planning Commission Work Session, the Planning Commission voted to send the Northstar Square application to the September 13th (2023), Board of Supervisor's Public Hearing, with a recommendation of approval.
-
Previous Update: After the Planning Commission voted to send the Northstar Square application to the Board of Supervisors, with a recommendation of denial, the applicant requested that the recommendation be reconsidered, the recommendation was rescinded, and was sent back to the Planning Commission’s Work Session on June 8th (2023).
-
Previous Update: At the April 13th (2023), Planning Commission Work Session, the Planning Commission voted to send this application to the June 14th Board of Supervisors Public Hearing.
-
Previous Update: At the February 9th (2023) Planning Commission Work Session, the Planning Commission voted to send this application to future work session on April 13th (2023).
-
Previous Update: This application is scheduled to come to the February 9th (2023) Planning Commission Work Session.
-
Previous Update: County staff from multiple departments are reviewing this application with the applicant.
For more information on this application, click here. To review the application documents, scroll down to the middle of the page and click the “Attachments” tab. To leave a public comment for county staff, click here. Supervisor Turner also invites you to share your thoughts and opinions about this application with via email at mike.turner@loudoun.gov.
| | | |
Spring Valley Technology Park
PMTG-2024-0058
(Potential Application)
| |
Disclaimer: The information about this potential application comes from a pre-application meeting, which is an initial review between the applicant and county staff of development concepts and is not legally binding. Due to the nature of this initial review, it is common for applicants to modify details of a proposed development before submitting an official application. To eliminate confusion, our office prefers to share application details only once an official application has been submitted. However, many constituents have contacted our office to inquire about this potential development and have asked us to keep them informed. We will continue to provide updates as more information becomes available.
Description: A Zoning Map Amendment to rezone land along Evergreen Mills Rd between Reservoir Rd and Ryan Rd from Transitional Residential—10 (TR-10) to Industrial Park (IP) to establish data centers
New Update: A pre-meeting (PMTG-2024-0194) was held on Monday, October 28, 2024. A “formal application” for this proposed development concept does not currently exist. The details in the description are subject to change.
For more information on this application, click here. Supervisor Turner also invites you to share your thoughts and opinions about this application with via email at mike.turner@loudoun.gov.
| | | |
Significant By-Right Developments in the Ashburn District | |   |
By-right: A "by-right" development is an application that does not require approval from the Board of Supervisors. The approval/denial of applications for by-right developments are managed administratively by county staff and must conform to the current zoning ordinance. | |   |
|
Description: “CyrusOne Broadlands Data Center” is a by-right application which plans to build a 41,000sf data center on 58 acres. The underlying zoning in Planned-Development Industrial Park (PD-OP). Data Centers are allowed by-right on PD-OP zoned land.
Status remains the same since the 01/26/2024 Newsletter: County staff from multiple departments are reviewing this application with the applicant.
For more information on this administrative application, click here. To review the application documents, scroll down to the middle of the page and click the “Attachments” tab.
| | | |
|
Description: “Belmont Landbay KK Data Center” is a by-right site plan approval request to develop data centers on approximately 51 acres that is zoned for Planned Development Office Park (PD-OP). The applicant proposes developing two data center buildings, one substation and one office building.
Status remains the same since the 01/26/2024 Newsletter:
County staff from multiple departments are reviewing this application.
For more information on this administrative application, click here. To review the application documents, scroll down to the middle of the page and click the “Attachments” tab.
| | | |
Road Improvements in the Ashburn District | |
|
Waxpool Road & Faulkner Parkway Roundabout
Application Number: CPAP-2021-0039
(Road Improvement)
| |
Description: CPAP-2021-0039 is a construction plan profile (CPAP) for the design of a two-lane roundabout, to be built at the T-intersection of Waxpool Road and Faulkner Parkway. This roundabout was proffered as a part of the Waxpool Crossing application (ZMAP-2019-0020), which was approved by the Board of Supervisors in 2021.
New Update: The Construction Plans and Profiles (CPAP-2021-0039) for the Waxpool Road and Faulkner Parkway Roundabout have received final approval from Loudoun County on November 4, 2024. Please see above for a photo of the final plan. The project, which includes a two-lane roundabout at the intersection, is now ready to proceed, with the following remaining permit requirements:
- Soil Tests & Pavement Approval: Soil tests must be conducted on the constructed subgrade to determine actual CBR values and must be approved before paving.
- Grading Permit: If offsite grading is required, letters of permission must be obtained before submitting the grading permit application.
- VDOT Permit: Any work within the VDOT right-of-way requires a permit from the Leesburg VDOT office before construction begins.
-
Previous Update: The applicant is working to secure permits for this project, as well as acquiring easements from adjoining property owners, and coordinating utility relocations with Dominion Energy, Verizon and Washington Gas. The outstanding permits for this project are a grading permit, a VDOT Right of Way (ROW) permit, as well as VDOT's approval of the proposed Maintenance of Traffic Plan.
-
Previous Update: Engineering plans have been approved. County staff is working with the applicant to complete any outstanding items that remain.
-
Previous Update: Engineering plans were submitted by the applicant and are being reviewed by county staff from multiple county departments.
For more information on this application, click here. To review the application documents, scroll down to the middle of the page and click the “Attachments” tab.
| | | |
VDOT 511
511 provides users with real-time, accurate traffic information from the Virginia Department of Transportation (VDOT) about road conditions, traffic congestion, and highway construction anywhere you are, anytime you need it.
More information on VDOT 511 can be found here.
| |
Online Process for Building Permits, Land Development Applications
Homeowners and residential contractors can submit their completed application form and supporting documentation, including drawings and plats, in PDF format for most residential construction projects to the Department of Building and Development online. More information about the online submission process and requirements is available here.
| |
Residential Traffic Calming Guide
Loudoun County’s Department of Transportation and Capital Infrastructure (DTCI) manages an eight-phase process to address traffic calming, which considers residents’ concerns regarding speeding, safety and overall quality of life on publicly-maintained residential streets.
| |
Who Maintains my Street?
To identify which entity responsible for maintaining your road/street, Loudoun County made an online color coded mapping system which helps residents determine who to contact when work needs to be done.
| |
Report a road problem
VDOT created an easy to use online form to report unsafe and hazardous road conditions. Similarly, work requests for state-maintained roads can also be made here.
| |
Paving Schedule
VDOT reports what roads will be paved during the fiscal year and updates their website with progress updates.
See VDOT's Paving Schedule here.
| |   |
As your representative on the Loudoun County Board of Supervisors, my top priority has been to serve your needs and work towards the betterment of our community. Please don’t hesitate to contact me directly or my staff with any input and ideas you may have for the Ashburn District. The best way to reach me is by email, which I monitor on a regular basis. | |   | | | |