BAT service delivery project timeline
We've noticed there's some confusion out there about the timeline for considering a self-performance model for BAT.
Most importantly, no decision has been made on this topic by the Board of Commissioners, beyond allowing the exploration of how a self-serve model would work.
Here are the highlights of the tentative schedule for the next two years:
Summer/fall 2026: Public listening sessions to gather input from BAT riders and community members
Late 2026/early 2027: Board of Commissioners to consider and vote on draft implementation plan for self-performance
Spring 2027: IF Board of Commissioners approves draft implementation plan, build BAT operations into 2027-29 Proposed Budget
May 2027: 2027-29 Budget to be finalized, determining how BAT services are to be delivered in the future
2028: County would begin delivering BAT services IF Budget Committee and Board of Commissioners approve funding for BAT self-performance in May 2027
|