WHAT: Construction activities have continued behind temporary walls in the main part of the high school building through the first three quarters of the school year. A temporary wall just inside the main entrance has been removed over Spring Break to give greater access to the Team areas. Contractors are finishing up the work this week (pictured).
- Phase 1B, 2A, 2B, 2C, 2D, 2E - These phases are effectively complete with the opening of the Team 2020 Office when students return from Spring Break.
- Phase 3A - (see timeline below) This phase will continue through the end of 2019. Since Spring Break 2018, the BHS auditorium has been closed. It will reopen in January 2020.
WHY: The core of the Brownsburg High School building has been relatively unchanged since it opened in 1971. With 13 additions over the last 46 years, the infrastructure of the building is in dire need of an upgrade. These upgrades will accommodate technology needs for teachers and students that weren't in place in 1971 and maintain a comfortable learning environment with updates to the aging HVAC system.
COMPLETION DATE FOR CURRENT PHASES OF WORK:
Phase 1A – Effectively complete
Phase 1B - Effectively complete
Phase 2A – Effectively complete
Phase 2B – Effectively complete
Phase 2C - Effectively complete
Phase 2D - Effectively complete
Phase 2E – Effectively complete
Phase 3A - January 2020