March/April 2019 - Phase 3A Volume 9 | April 3, 2019
Brownsburg High School's renovation and expansion project is expected to be completed in June of 2020. This message goes to families who have children in Brownsburg Schools in grades 8-12 in 2018-2019, to BCSC staff, and to anyone who has subscribed through our website. These emails are sent quarterly to provide information specific to each phase of the project, focusing on areas that impact students and their daily routines at BHS.

The current phase of construction, Phase 3A, continues with the Team Offices - now much more accessible after Spring Break (photo of progress below). Much of the work happening behind construction barriers still isn't visible to those visiting BHS. The view from the west side of the building (above) shows the progress of the new west entrance, cafeteria, auditorium, and 53 new and renovated classrooms and science lab that will be completed in the remaining phases. The artists' renderings in the bottom photo show the new BHS west entrance when the project is complete in the summer of 2020. (The bus is not an actual BCSC bus.)

Click the button below to see past BHS-TV coverage of construction tours with BHS Principal, Dr. Bret Daghe.
Overview of Phases 1B, 2A, 2B, 2C, 2D, 2E & 3A
WHAT: Construction activities have continued behind temporary walls in the main part of the high school building through the first three quarters of the school year. A temporary wall just inside the main entrance has been removed over Spring Break to give greater access to the Team areas. Contractors are finishing up the work this week (pictured).

  • Phase 1B, 2A, 2B, 2C, 2D, 2E - These phases are effectively complete with the opening of the Team 2020 Office when students return from Spring Break.
  • Phase 3A - (see timeline below) This phase will continue through the end of 2019. Since Spring Break 2018, the BHS auditorium has been closed. It will reopen in January 2020.

WHY: The core of the Brownsburg High School building has been relatively unchanged since it opened in 1971. With 13 additions over the last 46 years, the infrastructure of the building is in dire need of an upgrade. These upgrades will accommodate technology needs for teachers and students that weren't in place in 1971 and maintain a comfortable learning environment with updates to the aging HVAC system.

COMPLETION DATE FOR CURRENT PHASES OF WORK:
Phase 1A – Effectively complete
Phase 1B - Effectively complete
Phase 2A – Effectively complete
Phase 2B – Effectively complete
Phase 2C - Effectively complete
Phase 2D - Effectively complete
Phase 2E – Effectively complete
Phase 3A - January 2020
Impacted Areas
Building Access
  • No changes. Entry #1 remains open to the public. Students will have greater access to the Team 2020, 2021, and 2022 offices with the removal of the temporary wall just inside entry #1. The student pick up / drop off line continues to have car riders entering at entry #12 and #14. Bus riders continue to enter through entry #3. There should be no student drop off on Odell. Map is posted on the BHS website and also below.

Student Parking
  • There continues to be no parking or entrance from Sycamore or Grant. New student drivers can still get a parking pass in the main office.

Visitor Parking
  • Visitor parking during the school day continues to be across Odell and entry #1 near the BHS track

Pick up/Drop Off
  • The pick up/drop off procedures have not changed. See map below for new students. For the safety of pedestrians, there is traffic control (officers directing traffic) during pick up and drop off on Odell in front of entry #1 - in addition to Tilden and Bulldog Way.

Possible Services Affected
  • None

Classrooms & Relocation
  • There are no classroom changes happening after Spring Break.
2018-19 BHS Pick up / Drop Off Map
What's Next
Phase 3A continues through the end of 2019. Students will return from Spring Break to see that the Team offices are now complete with easier access to Team 2020, 2021, and 2022. There will be no major changes to the occupied part of the building through the end of this school year. Much of the work in this phase is only visible from the west side of the building near Grant Street.
CLICK HERE to open a printable PDF of the timeline. (view below)