WHAT: Construction activities have been mostly unseen to students and staff during the school year behind temporary walls in the main part of the high school building.
- Phase 1B, 2A, 2B, 2C, 2D, 2E - These phases are effectively complete.
- Phase 3A - (see timeline below) This phase will continue through the end of 2019. Since Spring Break 2018, the BHS auditorium has been closed. It will reopen in January 2020.
- Phase 3B - This phase includes the renovation of the former BHS cafeteria into specialized classrooms space for classes in Project Lead the Way, TV broadcasting.
WHY: The core of the Brownsburg High School building has been relatively unchanged since it opened in 1971. With 13 additions over the last 46 years, the infrastructure of the building was in dire need of an upgrade. These upgrades are accommodating technology needs for teachers and students that weren't in place in 1971 and are maintaining a comfortable learning environment with updates to the aging HVAC system.
COMPLETION DATE FOR CURRENT PHASES OF WORK:
Phase 1A – Effectively complete
Phase 1B - Effectively complete
Phase 2A – Effectively complete
Phase 2B – Effectively complete
Phase 2C - Effectively complete
Phase 2D - Effectively complete
Phase 2E – Effectively complete
Phase 3A - January 2020
Phase 3B - Summer 2020