BOND MEASURE HH NEWS AND UPDATES

SEPTEMBER 2025

SAN DIEGO MESA COLLEGE

 
 

A MESSAGE FROM VICE CHANCELLOR

DR. JOEL PETERSON

Dear Colleagues and Community,


Every Measure HH project is more than bricks and mortar - they are a reflection of us all.


As we begin the next stage of Measure HH, one factor stands out as more important than any other. Time. Every day matters.

Acting quickly means we can:

  • Contain rising costs by minimizing the effects of construction inflation.
  • Take advantage of favorable financing while interest rates remain in our favor.
  • Reduce risks from the unknown - such as tariffs, supply chain disruptions, or other global shifts.
  • Engage our campus communities early and often, ensuring that the voices of students, faculty, staff, and neighbors shape the decisions we make together.


The longer we wait, the more expensive and uncertain the path becomes. But by acting now - and with your input - we can provide the high-quality facilities that our students, faculty, staff, and community deserve.


Thank you for your continued support.


Sincerely,



Dr. Joel Peterson

Vice Chancellor & Executive Operations Officer

San Diego Community College District

SDCCD Awards Contracts for Landmark Design-Build Projects


SDCCD is taking a major step forward in delivering on the promise of Measure HH - building facilities that provide high-quality academic and career training facilities worthy of our students, faculty, and staff.


The Board of Trustees has approved contracts with eight design-build teams to launch the first phase of new construction and modernization across all three credit colleges and the College of Continuing Education.


Together valued at more than $153 billion, these projects represent one of the most ambitious capital investments in the district’s history - bringing new classrooms, labs, theatres, and student-centered space to every campus in the district that will genuinely reflect the future of education in San Diego. This is where our planning turns into action.


The district received 69 progressive design-build proposals - an extraordinary figure that reflects the interest of the design and construction community in our district. Our scoring committees reviewed over 5,000 pages of proposal documents. We thank our program management teams, bond program leaders, college leaders, and Chancellor Smith for their contributions to the careful and thorough selection process, resulting in selections of teams known for both design excellence and construction expertise.


The awards for Mesa are as follows:


Performing Arts Center/Administration & Parking Structure Project - HGA Architects / PCL Construction Services

Mesa College will build a new 54,000-square-foot Performing Arts Center to support theater, music, and dance. The state-of-the-art facility will feature a main stage theater, rehearsal, and instructional spaces.

 

Sports & Kinesiology Sciences - LPA Design Studios / C.W. Driver

The Sports & Kinesiology Project will transform Mesa’s athletics and exercise science facilities with 70,000 square feet of new, modern space. The project will feature a new three-court gym, expanded Aquatics Center, upgraded training areas, and new athletic fields.


In the months ahead, these teams will begin working with campus stakeholder groups to shape designs and prepare projects for construction. Each project will go through a “programming” phase where groups of students, faculty, and staff will help define how the spaces will be used and what features are needed to support teaching, learning, and community activities.


You can read more about the Phase I project awards here. If you’d like to see the presentations to the Board, you can view the meeting recording here, starting at approximately 2:20:40.

San Diego Community College District Chancellor Gregory Smith (center) and Vice Chancellor and Executive Operations Officer, Dr. Joel Peterson (center right) stand with members of all selected design-build teams at the September 11 Board of Trustees meeting.

But Wait - There’s More!

Dozens of Capital Renovation and Repair Projects!


The two design-build projects are just part of the facility transformation happening at Mesa College. There are also dozens of capital renovation and repair projects that will be taking place, transforming facilities from all corners of the campus. Here’s what’s coming up through spring of next year.

Building(s)

Project(s)

Bidding Timeframe

Bid Estimate

LRC

Emergency diesel generator replacement

11/10/25 - 12/10/25

<$1M

Pool

Double door replacement - exterior equipment area

11/10/25 - 12/10/25

<$1M

CDC

Roof - fluid applied (mechanical equipment area)

10/6/25 - 11/9/25

<$1M

Multiple

Roof replacements

12/8/25 - 1/22/26

>$1M

MC

Roof concrete patio area

11/10/25 - 12/10/25

<$1M

Multiple

Replace lighting inverter

11/9/25 - 12/18/25

<$1M

Multiple

Intrusion alarm system and components replacemnt

5/18/26 - 6/18/26

>$1M

Coming up in spring, we’ll be revisiting Miramar’s Facilities Path to 2035 as we identify and refine the scope of projects to be included in Phase II of our Measure HH implementation.

Meet the Mesa College Program Management Organization (PMO): Kitchell CEM


As we mentioned in last month's newsletter, the district brought on board three program management organizations to help lead and coordinate construction and design activities across the SDCCD campuses. 


At Mesa College, we'll be partnering with Kitchell CEM for significant new construction and renovation projects. We're also partnering with the Cumming Group for hundreds of capital renovation and repair projects over time, and we'll be profiling them in a future issue.


Kitchell CEM - Ed Dajani, Program Director

In simple terms, what is your role in the Measure HH program?

As Program Director with the PMO, I help oversee the finance, controls, planning, design, and construction of bond-funded projects across the district. My role is to make sure the projects move forward smoothly, align with district goals, and deliver the facilities our students, faculty, and staff need.

 

What projects are you currently managing, and what stage are they in?

Right now, we're supporting a range of projects at Mesa, including new construction and improvements. Most are in the early planning and design phases, where we work closely with users to define needs. The projects are listed below, and together they all move us toward improving the learning environment campuswide.

  • Mesa College Athletics Complex
  • Mesa College Performing Arts Center/Administration and Parking Structure

 

How do you work with campus leaders, faculty, and students to keep projects aligned with college needs?

Collaboration is key. We engage campus leaders, faculty, and students early in the process through planning meetings, governance committees, and design workshops. Their input shapes the scope and priorities of each project so the end result truly reflects the needs of the campus community.

 

What steps do you take to help ensure projects stay on schedule and within budget?

We start with careful planning, setting realistic budgets, timelines, and expectations. Throughout the project, we track progress closely, communicate regularly with stakeholders, and address challenges quickly. Our goal is always to deliver projects that are both fiscally responsible and on time.

 

What part of this work do you find most rewarding?

The most rewarding part is seeing the direct impact on students and faculty. Walking through a completed building and knowing it will serve generations of learners is incredibly fulfilling. It's also rewarding to know that our work helps create safe, modern, and inspiring spaces that support teaching and learning across the district.

 

Who are your PMO team members?

In addition to me, you will also have the opportunity to meet Sam Garcia, our Senior Project Manager. Joshua Beltran, our Program Controls Manager, works behind the scenes, overseeing project schedules, budgets, and scopes, and helping to identify and mitigate issues that could impact the projects.

From L-R: Ed Dajai, Program Director; Sam Garcia, Senior Project Manager; and Isaac Ruiz, Program Controls Manager.

What's happening elsewhere?

Meet Brokk: Our New Robotic Teammate


Move over, jackhammers, there’s a new demolition specialist in town. For the Educational Cultural Complex Theatre remodel at the San Diego College of Continuing Education, the district brought in Brokk, a state-of-the-art demolition robot, to help tackle some of the most challenging parts of the project.


Compact and remotely operated, Brokk can work safely in tight spaces, breaking down concrete and handling heavy demolition while operators stay clear of dust and debris. Its light frame allows it to climb stairs and move through confined areas, making it especially useful for a theatre renovation with narrow access points.



The addition of Brokk helps the project team complete difficult work more efficiently and safely - an essential advantage as Measure HH projects move forward. You can see him in action here.

Additional Reading


What is Progressive Design-Build?


Why Acting Now Saves Millions Later


Engagement at the Earliest Stages


On Time, On Budget, On Mission

Connect With Us


With projects now underway and many more in the pipeline , Measure HH is transforming facilities that serve 90,000 students annually. Visit the Measure HH website to learn more.


If you are interested in learning more about Measure HH and would like to schedule a presentation for your campus organization or a community group you belong to, or have ideas for future stories, please email us at SDCCDMeasureHH@sdccd.edu.


We look forward to sharing updates going forward!